Diamond Match Co. v. Silberstein

131 P. 874, 165 Cal. 282, 1913 Cal. LEXIS 418
CourtCalifornia Supreme Court
DecidedApril 9, 1913
DocketSac. No. 1976.
StatusPublished
Cited by15 cases

This text of 131 P. 874 (Diamond Match Co. v. Silberstein) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diamond Match Co. v. Silberstein, 131 P. 874, 165 Cal. 282, 1913 Cal. LEXIS 418 (Cal. 1913).

Opinion

HENSHAW, J.

This is a consolidated action under the Mechanics’ Lien Law to enforce liens for material and labor against land and the building thereon owned by defendant and appellant Silberstein. Prom the judgment and from the order denying his motion for a new trial Silberstein appeals.

• Defendant had entered into a valid contract with an original contractor, the Burnight-Kennedy Company, for the erection of a building upon his land for the contract price of forty-one thousand five hundred dollars. By the terms of the contract progress payments in the sum of two thousand dollars each, representing seventy-five per cent of the work done, were to be made from time to time upon the architect’s certificate. Thus, under the terms of the contract, there would be due to the contractor upon the completion of its work a payment of three thousand one hundred dollars and thirty-six days after completion, the sum of ten thousand four hundred dollars. The contractor, however, did not complete its work but abandoned it, after having received all the progress payments contemplated by the contract and two thousand dollars of the three thousand one hundred dollars completion payment. The owner took possession on March 21, 1910, and finished the building under the terms of the contract at a cost of $885.31. The building was actually completed on April 14, 1910, and notice of completion was filed on April 15, 1910.

Touching the liens and personal judgments awarded against his property and himself appellant contends that the progress payments which he had made were justifiable, being called for by his contract; that the contract between himself and his contractor being admittedly valid, there remains in his hands . subject to the demands of the claimants ten thousand four hundred dollars, the final payment, and $214.69, the balance *285 of the completion payment after deducting the two thousand dollars which he had paid the contractor and the $885.31 which he had expended in finishing the building, making a total available for the demands of the claimants of $10,614.69. For this, and this alone, appellant contends that he is liable.

By respondents it is shown that the Diamond Match Company served upon appellant the notice to withhold under section 1184 of the Code of Civil Procedure. This notice was served upon September 15, 1909, and was for the sum of $5,617.10. After the service of this notice appellant paid to his contractor many thousand dollars in excess of this sum. Wygant & Collins served a like notice on December 26, 1909, to withhold the sum of $1,751.20. Thereafter the appellant paid to his contractor the sum of four thousand dollars. The Chico Construction Company served its similar notice on January 4, 1910, to withhold $205.40,- and thereafter the appellant paid to his 'contractor the sum of two thousand dollars. W. W. Montague & Company served its notice to withhold $1,774.04 upon February 10, 1910. Other similar notices were served before the date of completion, but those here enumerated are all that it is necessary to mention in exposition of the legal questions involved. The principal of these questions concerns the construction of section 1184 of the Code of Civil Procedure which section at all the times covered by this litigation provided as follows:

“Any of the persons mentioned in section 1183, except the contractor, may at any time give to the reputed owner a written notice that they have performed labor or furnished materials, or both, to the contractor, or other person acting by authority of the reputed owner, or that they have agreed to do so, stating in general terms the kind of labor and materials, and the name of the person to or for whom the same was done, or furnished, or both, and the amount in value, as hear as may be, of that already done or furnished, or both, and of the whole agreed to be done, or furnished, or both. ... Upon such notice being given, it shall be the duty of the person who contracted with the contractor to, and he shall, withhold from his contractor, or from any other person acting under such reputed owner, and to whom by said notice the said labor or materials, or both, have been furnished, or agreed to be furnished, sufficient money due, or that may become due *286 to such contractor, or other person to answer such claim and any lien that may be filed therefor for record under this chapter.”

Appellant’s argument as to the meaning of this section may be illustrated as follows: Under the notice of the Diamond Match Company it became the duty of the appellant to withhold $5,617.10, but he had the right to withhold this sum out of money “that may become due” the contractor. He was under no duty or compulsion to withhold it out of the first moneys due or to become due. Therefore he was justified in making all the subsequent payments to his contractor which he did make down to the time and point when, excepting the final payment of $10,400, there should be due to the contractor only the sum of $5,617.10. It should be considered that this is what the appellant did and that this $5,617.10 would be represented by the full amount of the completion payment of $3,100 and something over two thousand dollars of the last progress payments. In contemplation of law, therefore, so argues appellant, he is to be considered as having withheld this $5,617.10 to meet the demand of the Diamond Match Company, wherefore there was no money under his control due or to become due to the contractor upon the dates of the services of the subsequent notices upon him. ' In fact, as has been said, the appellant did not so withhold these moneys at all but he insists that in contemplation of law he is to be treated as having withheld them out of these last payments and the effect is to render nugatory the subsequent notices to withhold. Such, however, is not the meaning of section 1184 of the Code of Civil Procedure, and such a construction under most obvious considerations would result in “confusion worse confounded. ” It is the clear duty of the owner under service of such a notice to withhold from the moneys due, or from the first moneys that may become due, a sum sufficient to protect him against the demand of the notice. If he does not do this he becomes justly liable under later notices to withhold which may be served upon him. No materialman is charged with knowledge that another materialman has served the owner with such notice to withhold, still less with knowledge that the owner contemplates withholding the funds out of the last payments that may become due the contractor. The materialman reading the contract and learning from the terms of it that *287 moneys are to become due serves his notice and is entitled to rely upon the fact that sufficient of these later payments will be withheld to meet his claim. Of course, if all of those payments have, in fact, been absorbed under the demands of the earlier notices, the owner would be entitled to show that fact. But he can do this only under the construction here set forth,—namely, that from the time of the service of each notice upon him he has withheld out of the moneys due, or first to become due, funds to meet the previous demands.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Systems Investment Corp. v. National Automobile & Casualty Insurance
25 Cal. App. 3d 1057 (California Court of Appeal, 1972)
Idaco Lumber Co. v. Northwestern Savings & Loan Ass'n
265 Cal. App. 2d 490 (California Court of Appeal, 1968)
Miller v. Mountain View Savings & Loan Ass'n
238 Cal. App. 2d 644 (California Court of Appeal, 1965)
A-1 Door & Materials Co. v. Fresno Guarantee Savings & Loan Ass'n
394 P.2d 829 (California Supreme Court, 1964)
Fredericksen v. Harney
199 Cal. App. 2d 189 (California Court of Appeal, 1962)
Calhoun v. Huntington Park First Savings & Loan Ass'n
186 Cal. App. 2d 451 (California Court of Appeal, 1960)
L. W. Blinn Lumber Co. v. Pioneer Drainage District
195 P. 732 (California Court of Appeal, 1920)
Fuller v. Towne
193 P. 88 (California Supreme Court, 1920)
General Electric Co. v. American Bonding Co. of Baltimore
182 P. 444 (California Supreme Court, 1919)
Southern California E. Co. v. McDonald
173 P. 760 (California Supreme Court, 1918)
Silberstein v. Kitrick
169 P. 250 (California Court of Appeal, 1917)
Stettin v. Wilson
166 P. 6 (California Supreme Court, 1917)
Sweeney v. Board of Trustees of Auburn School District
165 P.2d 42 (California Court of Appeal, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
131 P. 874, 165 Cal. 282, 1913 Cal. LEXIS 418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diamond-match-co-v-silberstein-cal-1913.