Idaco Lumber Co. v. Northwestern Savings & Loan Ass'n

265 Cal. App. 2d 490, 71 Cal. Rptr. 422, 1968 Cal. App. LEXIS 1643
CourtCalifornia Court of Appeal
DecidedSeptember 5, 1968
DocketCiv. 24765
StatusPublished
Cited by10 cases

This text of 265 Cal. App. 2d 490 (Idaco Lumber Co. v. Northwestern Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaco Lumber Co. v. Northwestern Savings & Loan Ass'n, 265 Cal. App. 2d 490, 71 Cal. Rptr. 422, 1968 Cal. App. LEXIS 1643 (Cal. Ct. App. 1968).

Opinion

BROWN (H. C.), J.

This is an appeal by Northwestern Savings and Loan Association (Northwestern), the construction project lender, from a judgment awarding Idaco Lumber Company (Idaco) the full amount specified in a stop notice claim for the value of materials furnished under a building construction contract. Idaco also appeals, claiming a greater amount of interest and that the allowance for costs for bond premium should be increased.

Northwestern contends that the payments to the general contractor W. F. Baekes Construction Co., Inc. (Backes), from the Jebb Development Company (Jebb) loan account were rendered insufficient to pay all claimants in full and that each claimant, including Idaco, was entitled only to a pro rata share from the balance in the account. The trial court awarded Idaco payment in full because Idaco was the only claimant that established a lien on the loan fund by perfecting its stop notice claim pursuant to the provisions of Code of Civil Procedure section 1190.1, et seq.

The Facts: On April 2, 1963, Northwestern loaned Jebb $135,000 and received a note secured by a deed of trust. The loan conformed to the statutory requirements for construction *493 loans made on the basis of an appraisal of the unimproved land and the plans and specifications for the proposed building. (See Fin. Code, §§ 1227, 7153, 7153.4. Loans by lending institutions are limited to a percentage of the appraised value of the property.)

The purpose of the loan was to enable the borrower to construct on its real property improvements to be known as Larkspur Plaza. The loan agreement provided that the funds were to be held by Northwestern in an account labeled “Jebb Development, Inc.,” loan and were to be paid to the general contractor Backes in ten installments as the work progressed. By February 1964, Northwestern had paid to Backes $97,422.69, leaving $37,577.31 in the Jebb loan account. This balance was insufficient to pay subcontractors the amounts due them which were in excess of $60,000.

There was due Idaco a sum in excess of $10,000. Because of this delinquency, Idaco on February 13, 1964, pursuant to section 1190.1, subdivision (h) of the Code of Civil Procedure, 1 served a verified bonded stop notice on Northwestern. The notice specified the type and value of materials furnished, that payment was due and to withhold in the fund sufficient to pay the claim. Northwestern thereafter made no further payments to Backes, the building contractor, or Jebb, and work on the job was discontinued. Section 1190.1, subdivision (c) states in part as follows: “Upon such notice being given it shall be the duty of the person to whom, such notice is given to .. . withhold from his contractor . . . sufficient money . . . due or that may become due to such contractor to answer such claim ...” (Italics added.)

By May 4, 1964, 19 stop notices in the total sum of $62,846.14 had been delivered to Northwestern on behalf of the subcontractors and materialmen. At this time the balance due Idaco was $10,099. On May 7, 1964, Northwestern transferred the entire balance of $37,577.31 out of the Jebb account into its general fund and applied that amount to the reduction of Jebb’s indebtedness to Northwestern. Thereafter Northwestern paid the $37,577.31 on a pro rata basis to all of the stop notice claimants except Idaco which demanded payment in full with interest. Northwestern made the pro rata payments to the other claimants prior to the expiration of the statutory period for stop notice claimants to file suit. In addi *494 tion to the pro rata payments, Northwestern voluntarily paid from its general funds to the stop notice claimants, except Idaco, and to three mechanics lien claimants who had not filed stop notices, the balance of their claims so that each claimant except Idaco received 100 percent of its stop notice claim or lien claim. The record is silent as to Northwestern’s reason for not including Idaco when it voluntarily made payments in full to other claimants.

On July 1, 1964, Idaco filed its action herein for the balance of $10,000 due on the Larkspur Plaza project, plus interest at 7 percent per annum from January 15, 1964, and in a second cause of action for $393.05 principal, due on another project known as the Sonoma Village project, plus interest at 7 percent from October 29, 1963. In the Sonoma Village project Idaco also had been tendered a pro rata payment but rejected it claiming the full amount due plus interest.

Except for the dollar amounts and the dates of delivery, the facts relating to the Sonoma Village project in the second cause of action are similar to those relating to Larkspur Plaza. Idaco and Northwestern stipulated that the court’s determination as to Larkspur Plaza would be controlling with respect to Sonoma Village.

At the trial Idaco stipulated that all stop notice claimants had performed services or furnished materials and that those services and materials were of the reasonable value claimed. Idaco did not stipulate that all claimants and mechanics lienors could be paid from the loan fund on a pro rata basis without perfecting their claims. Nor was it stipulated that Northwestern’s pro rata distribution was made in conformity to statutory requirements. This stipulation did not affect Idaco’s claim as the issue before the court was not whether the services performed and the materials furnished by the various claimants represented true value but whether those claimants were entitled to participate in a pro rata distribution of the fund which would proportionately reduce the amount to be paid to Idaco which had perfected its claim.

The court found that Idaco’s stop notice claim was verified, bonded, served, and in all other respects complied with the requirements of section 1190.1, subdivision (h); that Idaco brought its action within the 90-day period provided by section 1197.1, subdivision (a), and that Idaco gave Northwestern registered-mail notice of the action within five days after commencing its action as required by section 1197.1, subdivision (b). Idaco’s bond in support of its stop notice claim was *495 in the sum of $44,699.20 (the original amount of all of its claims), more than four times the aggregate total amount claimed on the two projects covered by Idaco’s complaint. (Code of Civil Procedure section 1190.1, subdivision (h) requires that the bond be in an amount equal to 125 percent of the claim. The required bond secured payment of costs and damages in the event the owner or general contractor be awarded judgment.)

The trial court concluded that Idaco was entitled to the full amount of the principal and interest on its stop notice claims. Further, the court adjudged Northwestern personally liable to Idaco jointly and severally with Jebb and Baekes for the balance of $10,000 with respect to the Larkspur Plaza project, and jointly and severally with Baekes for a balance of $393.05 on the Sonoma Village project, but that Northwestern’s liability to Idaco for interest on said principal amounts at the legal rate of 7 percent per annum did not commence to accrue until August 1,1964.

After judgment, on a motion by Northwestern to tax costs, the court held that Idaco should be allowed $199.20 per annum as premium on the stop notice bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S. HIGHLANDS CMTY. ASS'N. VS. SAN FLORENTINE AVE. TRUST
2016 NV 3 (Nevada Supreme Court, 2016)
Magnum Builders v. Preferred Bank CA2/7
California Court of Appeal, 2014
Familian Corp. v. Imperial Bank
213 Cal. App. 3d 681 (California Court of Appeal, 1989)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
A. J. Setting Co. v. Trustees of the California State University & Colleges
119 Cal. App. 3d 374 (California Court of Appeal, 1981)
Connolly Development, Inc. v. Superior Court
553 P.2d 637 (California Supreme Court, 1976)
Smith v. Union Bank & Trust Assn.
15 Cal. App. 3d 413 (California Court of Appeal, 1971)
Bohannan Bros. v. Lo Jean Development Co.
3 Cal. App. 3d 200 (California Court of Appeal, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
265 Cal. App. 2d 490, 71 Cal. Rptr. 422, 1968 Cal. App. LEXIS 1643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaco-lumber-co-v-northwestern-savings-loan-assn-calctapp-1968.