Lee Turzillo Contracting Co. v. Cincinnati Metropolitan Housing Authority

225 N.E.2d 255, 10 Ohio St. 2d 5, 39 Ohio Op. 2d 3, 1967 Ohio LEXIS 361
CourtOhio Supreme Court
DecidedMarch 29, 1967
DocketNo. 40140
StatusPublished
Cited by19 cases

This text of 225 N.E.2d 255 (Lee Turzillo Contracting Co. v. Cincinnati Metropolitan Housing Authority) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lee Turzillo Contracting Co. v. Cincinnati Metropolitan Housing Authority, 225 N.E.2d 255, 10 Ohio St. 2d 5, 39 Ohio Op. 2d 3, 1967 Ohio LEXIS 361 (Ohio 1967).

Opinion

Schneider, J.

Jurisdiction of this appeal was accepted for the reason that the operative effect of the controlling legislative enactments, although of long standing, has never received [8]*8more than the cursory attention of this court. See State, ex rel. Nixon, v. M err ell, 126 Ohio St. 239; 127 Ohio St. 72.

Portions of the statutes (in effect prior to amendments effective September 30, 1963) pertinent to the issues here involved and to their resolution read as follows:

“Section 1311.26. Any subcontractor . . . who has performed labor or furnished material, . . . who is performing labor or furnishing material, ... or is about to perform labor or furnish material, . . . for the construction . . . of . . . [a] public building provided for in a contract between ... [a] public authority and a principal contractor, and under a contract between such subcontractor . . . and a principal contractor ... at the time of beginning to perform such labor ... or at any time, not to exceed four months from the performance of the labor or the delivery of the . . . material, may file with the [public authority] ... a sworn and itemized statement of the amount and value of such labor performed, and to be performed, [and] material , . . furnished . . . .”

Section 1311.28. Upon receiving the notice required by Section 1311.26 of the Revised Code, such . . . public authority . . . shall detain in . . . [its] hands all subsequent payments from the principal [contractor] ... to secure such ... [claim].”

“Section 1311.31. The [public authority], . . . upon the receipt of the statement referred to in Section . . . [1311.26] of the Revised Code, shall, or the lien claimant [subcontractor] ... in the name of such . . . [public authority] may, furnish the principal contractor . . . with a copy thereof, within five days after receiving it. If such principal [contractor] . . . fails within five days after such receipt by him, to notify, in writing, such . . . [public authority] of his intention to dispute such claim, he has assented to its correctness. Thereupon such subsequent payment shall be applied by such . . . [public authority] pro rata, upon such claim, and the amounts, when due, of such claim or estimates as have been meanwhile filed by other subcontractors, . . . and assented to or adjusted as provided for in Sections 1311.01 to 1311.68, inclusive, of the Revised Code 5 J

“Section 1311.32. If within five days after his assent to ... any claim, a head contractor . . . fails to pay to the subcon[9]*9tractor . . . the amount thereof and costs incurred, the . . . [public authority] when due, shall pay the whole or a pro rata amount thereof, as provided in Sections 1311.30 and 1311.31 of the Revised Code, out of payments subsequently falling due. On ... [its] failure to do so, within ten days thereafter, the subcontractor . ! . when due, may recover against the . . . [public authority] in an action for money had and received, the whole or a pro rata amount of his claim or estimate, not exceeding in any case the balance due to the principal contractor.” (Emphasis supplied.)

In granting summary judgment against Messer on its finding that Messer’s letter of notice did not express an “intention to dispute” Turzillo’s claim, the trial court necessarily considered that single fact as constituting, under Sections 1311.31 and 1311.32, Revised Code, a complete truncation of all of Messer’s rights against Turzillo. This view is entirely too severe upon the party against whom the statute was employed, and its liberality in favor of the party benefited places the law far beyond the reach of the purpose sought to be accomplished.

We regard the statutes under consideration as affording a species of garnishment to protect the subcontractor against the risk of loss of the payments properly due him should they reach his principal contractor in whose hands they may be subject to the latter’s creditors or to his own caprice. (It is here noted that the general statutes relating to attachment and garnishment [Section 2715.01 et seq., Revised Code] would not provide the remedy apparently intended by the Legislature in enacting Section 1311.26 et seq., Revised Code. The former are generally applicable upon a suggestion of the contract debtor’s fraudulent intent to hinder the collection of the debt by absence or abscondment, and, in all but several instances, require a bond in double the amount of the property to be seized. Manifestly, they would not be adequate to protect a construction subcontractee under a contract which ordinarily provides for periodic payments as the work progresses.)

The conclusion we reach is required if equal weight is to be accorded to every feature of the statutes and if conflict is to be avoided and a balance maintained between two precepts, viz., -that remedial laws, on the one hand, are to be liberally construed [10]*10and that statutes purporting to confer a substantive right in derogation of common law, on the other, will be resolved against one claiming their benefits. Robert V. Clapp Co. v. Fox, 124 Ohio St. 331, 178 N. E. 586; American Guaranty Co. v. Cliff Wood Coal & Supply Co., 115 Ohio St. 524, 155 N. E. 127; Sabol v. Pekoc, 148 Ohio St. 545, 553, 76 N. E. 2d 84; Penoyar v. Kelsey, 150 N. Y. 77, 44 N. E. 788.

It is not to be ignored that Section 1311.26, Revised Code, authorizes the subcontractor, even before the performance of the work, to actuate the procedure culminating in Section 1311.32, Revised Code, by filing with the owner “a sworn and itemized statement of the amount and value” of the work “performed, and to be performed.” In Section 1311.28, Revised Code, this statement is referred to as a “notice,” but also, in that and subsequent sections, alternatively as a “claim” or a “statement.” The net effect of Sections 1311.26 and 1311.28, Revised Code, taken together, constitutes a “stop notice” to the owner (Tile Wholesalers and Importers, Inc., v. Ruppert, 125 N. J. L. 597, 17 A. 2d 607) and a form of assignment or subrogation regulated by statute (L. W. Blinn Lumber Co. v. Pioneer Drainage District, 50 Cal. App. 364, 195 P. 750; Diamond Match Co. v. Silberstein, 165 Cal. 282, 131 P. 874). The subcontractor secures an assignment pro tanto of the money remaining due from the owner to the prime contractor and the right to control and direct its payment to himself. Bates v. County of Santa Barbara, 90 Cal. 543, 27 P. 438.

Prom the time of the receipt of the “notice,” the owner cannot safely pay any amount owing to the principal contractor until the amount claimed to be due the subcontractor is fixed. Therefore, the office of subsequent Section 1311.31, Revised Code, is to provide the method for determining the extent of the fund “assigned” or the amount of moneys to which the subcontractor is entitled. But the prime contractor is given the opportunity to dispute either an unreasonable claim or an asserted excess over the agreement between him and his subcontractor.

If, either by way of reply or by the failure of a timely reply, the principal contractor fails to manifest “his intention to dispute such claim, he has assented,” not to the payment of [11]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Cincinnati v. Scheer & Scheer Development
862 N.E.2d 122 (Ohio Court of Appeals, 2006)
Intercargo Insurance Co. v. Municipal Pipe Contractors, Inc.
2003 Ohio 7363 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 2003)
State Ex Rel. Gray Road Fill, Inc. v. Wray
673 N.E.2d 198 (Ohio Court of Appeals, 1996)
In Re Wm. Cargile Contractor, Inc.
151 B.R. 854 (S.D. Ohio, 1993)
Deaton v. Dreis & Krump Manufacturing Co.
134 F.R.D. 219 (N.D. Ohio, 1991)
Poenisch v. Kingsley-Dunbar, Inc.
582 N.E.2d 1071 (Ohio Court of Appeals, 1990)
Neal-Crane Co. v. Trio Construction Services, Inc.
583 N.E.2d 993 (Ohio Court of Appeals, 1989)
State ex rel. Dinneen Excavating Co. v. Sykes
531 N.E.2d 1309 (Ohio Supreme Court, 1988)
L.E. Myers Co. v. Jordano Electric Co.
547 N.E.2d 1014 (Ohio Court of Appeals, 1988)
Talco Capital Corp. v. State Underground Parking Commn.
324 N.E.2d 762 (Ohio Court of Appeals, 1974)
Krause v. Rhodes
471 F.2d 430 (Sixth Circuit, 1972)
Lee Turzillo Contracting Co. v. Frank Messer & Sons, Inc.
261 N.E.2d 675 (Ohio Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
225 N.E.2d 255, 10 Ohio St. 2d 5, 39 Ohio Op. 2d 3, 1967 Ohio LEXIS 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lee-turzillo-contracting-co-v-cincinnati-metropolitan-housing-authority-ohio-1967.