L.E. Myers Co. v. Jordano Electric Co.

547 N.E.2d 1014, 47 Ohio App. 3d 132, 1988 Ohio App. LEXIS 2152
CourtOhio Court of Appeals
DecidedApril 19, 1988
Docket87AP-949
StatusPublished
Cited by5 cases

This text of 547 N.E.2d 1014 (L.E. Myers Co. v. Jordano Electric Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.E. Myers Co. v. Jordano Electric Co., 547 N.E.2d 1014, 47 Ohio App. 3d 132, 1988 Ohio App. LEXIS 2152 (Ohio Ct. App. 1988).

Opinion

McCormac, J.

Defendant-appellant, Ohio Department of Transportation (“ODOT”), appeals the trial court’s granting of a summary judgment to plaintiff-appellee, L.E. Myers Company (“Myers”), in a mandamus action in which ODOT was ordered to pay Myers $69,372.11. Myers, a subcontractor, first filed a statutory lien *133 against ODOT pursuant to R.C. 1311.26 et seq. because the prime contractor, Jordano Electric Company (“Jordano”), had failed to pay Myers for its work and materials used on an ODOT highway lighting project.

Then Myers filed an amended complaint against Jordano and its surety, Merchants’ and Manufacturers’ Insurance Company (“M & M”), which included a mandamus claim against ODOT seeking payment for materials and labor which it used on the ODOT project. ODOT cross-claimed against Jordano and its surety for $202,826.50, for failure to complete the highway lighting project. The court sua sponte stayed the proceedings against M & M pending the outcome of its liquidation proceedings.

The court overruled ODOT’s motions for summary judgment and granted Myers’ motion for summary judgment against ODOT and awarded it $69,372.11. Although the trial court did not dispose of the claims and cross-claims against Jordano’s surety, it included Civ. R. 54(B) language in its order causing the summary judgment against ODOT to be a final appealable order.

Defendant-appellant appeals the summary judgment and asserts the following assignments of error:

“I. Because no subsequent payments were due from the appellant to the prime contractor it was error for the court of common pleas to allow recovery on filed liens.

“II. The common pleas court erred in failing to allow appellant to set off amounts owed to it by the prime contractor against amounts claimed by ap-pellee pursuant to filed liens.

“HI. The court of common pleas erred as a matter of law in finding that liens filed by the appellee were valid.

“IV. The court of common pleas erred by failing to find the existence of genuine issues of material facts:

“A. The court failed to find that the amount owed to the appellee by the prime contractor was a genuine issue of material fact.

“B. The court of common pleas erred in finding filed liens valid despite genuine issues of material fact.

“C. The court of common pleas erred in failing to find that genuine issues of material fact existed as to the amount of subsequent payments due from the appellant.

“V. The court of common pleas lacked subject matter jurisdiction to order an award for money damages against appellant.

“VI. It was error for the court of common pleas to grant an award of prejudgment interest from the date of the lien filing against the state of Ohio.”

In 1984, Jordano, the prime contractor, signed an agreement with ODOT promising to install electrical facilities at a rest area on Interstate 71 for $207,986.65. Jordano then entered into an agreement with Myers, a subcontractor, to perform a certain portion of this work for $83,700.

Jordano and Myers began work on the project and ODOT made periodic payments to Jordano for the work completed. Jordano did not pay Myers for work it had done.

With the exception of one day in February 1986, Jordano stopped working on the project on December 20, 1985. ODOT made its last payment to Jordano on January 21, 1986.

Jordano was scheduled to return to work on April 1, 1986, but did not and, due to this failure, ODOT terminated the contract and, on April 17, 1986, requested M & M, the contractor’s surety, to complete the project. Because of financial problems and an eventual liquidation order, M & M refused to perform and ODOT contracted with another firm to complete the work for a price of $229,557.

*134 On March 6, 1986, Myers filed its first notice of lien with ODOT totalling $58,236.25 and, on May 6,1986, filed a second notice of lien with ODOT total-ling $11,135.86. Myers had previously submitted invoices to Jordano for work performed on the project totalling the total amount of the two liens.

ODOT did not owe, nor did it pay, Jordano any money after it was notified of Myers’ first lien. However, there was remaining $70,197.66 of the amount of the contract with Jordano of $207,986.65. This amount was not paid to Jordano because Jordano had not even completed all of the work for which payment was made. Since Jor-dano had received more payment than work completed, nothing was due Jor-dano at the time it was removed from the job. ODOT’s contract with the new contractor required payment of substantially more than the remaining $70,197.66 (actually $229,557) to complete the work Jordano should have completed. There is no evidence in the record, however, that Myers’ subcontracted work was not properly completed.

The trial court granted Myers’ motion for summary judgment against ODOT and ordered payment by ODOT to Myers of the total of the two liens, which was slightly less than the amount retained by ODOT of the original contract price prior to its new contract with another contractor to complete the job.

In appellant’s first assignment of error, it argues that the court of common pleas erred when it allowed Myers to recover on its liens since ODOT owed no subsequent payments to Jor-dano.

The Ohio Legislature has established a statutory scheme whereby any subsequent payments to a contractor must be retained by the owner after a subcontractor files a notice of lien pursuant to R.C. 1311.26 et seq.

In R.C. 1311.26, a subcontractor who performs road or public improvements under an agreement with the contractor may, not more than four months after the subcontractor’s performance, file with the owner an itemized statement of its labor performed and materials furnished. R.C. 1311.28 states that an owner, upon receiving the subcontractor’s R.C. 1311.26 notice, shall detain from the principal contractor all subsequent payments as do not in the aggregate exceed the subcontractor’s claims and place them in an escrow account. R.C. 1311.31 requires that an owner shall, or a lien claimant may, furnish the principal contractor with a copy of the R.C. 1311.26 notice. The principal contractor must give notice of its intention to dispute the claim within ten days of its receipt. If it does not within ten days, then it has assented to the notice’s correctness. The amount in escrow shall be used to pay claims that have been filed. R.C. 1311.32 provides that the duty to pay lien claimants may be enforced by a mandamus action against the owner. A subcontractor may recover against the owner the whole or a pro rata amount of his claim, “not exceeding in any case the balance due to the principal contractor.”

In Lee Turzillo Contracting Co. v. Cincinnati Metro. Housing Auth. (1967), 10 Ohio St. 2d 5, 39 O.O. 2d 3, 225 N.E. 2d 255, the Supreme Court held, as follows, in paragraph one of the syllabus:

“Section 1311.26 et seq.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Wm. Cargile Contractor, Inc.
151 B.R. 854 (S.D. Ohio, 1993)
Monarch Carpet Services, Inc. v. Department of Admin. Serv.
8 Ohio App. Unrep. 543 (Ohio Court of Appeals, 1990)
Poenisch v. Kingsley-Dunbar, Inc.
582 N.E.2d 1071 (Ohio Court of Appeals, 1990)
Neal-Crane Co. v. Trio Construction Services, Inc.
583 N.E.2d 993 (Ohio Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
547 N.E.2d 1014, 47 Ohio App. 3d 132, 1988 Ohio App. LEXIS 2152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/le-myers-co-v-jordano-electric-co-ohioctapp-1988.