In Re Wm. Cargile Contractor, Inc.

151 B.R. 854, 1993 Bankr. LEXIS 408, 23 Bankr. Ct. Dec. (CRR) 1771, 1993 WL 60689
CourtUnited States Bankruptcy Court, S.D. Ohio
DecidedMarch 3, 1993
DocketBankruptcy 1-92-04791
StatusPublished
Cited by4 cases

This text of 151 B.R. 854 (In Re Wm. Cargile Contractor, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Wm. Cargile Contractor, Inc., 151 B.R. 854, 1993 Bankr. LEXIS 408, 23 Bankr. Ct. Dec. (CRR) 1771, 1993 WL 60689 (Ohio 1993).

Opinion

DECISION ON MOTION OF NATIONAL AMERICAN FOR DIRECT PAYMENT

BURTON PERLMAN, Bankruptcy Judge.

This contested matter is before the court pursuant to a dispute between a surety, National American Insurance Company (“National”), and the Unsecured Creditors’ Committee (“UCC”) oyer the disposition of money held by Messer Construction Company (“Messer”), construction manager for a public construction project at the University of Cincinnati which is owned by the state of Ohio for work at the University of Cincinnati. The debtor, William Cargile Contractor, Inc. (“debtor”), is a subcontractor with respect to the project, and itself in turn employed subcontractors (hereafter “debtor’s subs”). Before debtor filed its Chapter 11 petition, National issued performance bonds for certain construction work to be completed by debtor. These bonds guaranteed payment by debtor to debtor’s subs and materialmen (referred to hereafter collectively as “debtor’s subs”), including Carlisle Construction, TYS Construction and Baker Construction. Much of the work on the project has been completed. Debtor’s subs, however, are owed approximately $60,000.00 for their work under subcontracts with debtor that were guaranteed by the bonds.

National seeks an order from this court authorizing Messer to pay debtor’s subs directly, which right National asserts is based on provisions contained in the construction contract between Cargile and the University. National states that allowing the debtor’s subs to receive the funds directly would allow debtor’s subs to pay their labor expenses without having to expend the cost and effort of making claims against National. According to National, a direct payment of the funds would also reduce the ultimate claim against debtor by the amount equal to the payment. National bases its motion on two arguments. First, National asserts that debtor’s subs are secured creditors based on properly filed mechanic’s liens, which, although filed postpetition, nevertheless relate back to the first day work was performed. National states that since debtor’s subs are fully secured, allowing them to be paid directly would not prejudice the rights of unsecured creditors, since those creditors have no right to the monies. Additionally, National asserts that the monies are not property of the estate pursuant to § 541 because of a trust agreement between itself and debtor arising out of the performance bonds, on the one hand, and out of the contract between debtor and the State, on the other.

This court has jurisdiction of this matter pursuant to 28 U.S.C. § 1834(b) and the General Order of Reference entered in this District. This is a core proceeding arising under 28 U.S.C. §§ 157(b)(2)(A).

We will first address the issue of whether debtor’s subs are secured creditors. We note that debtor filed its Chapter 11 petition in September, 1992, and notices of debtor’s subs’ liens pursuant to Ohio Revised Code (“ORC”) § 1311.26 were filed in December, 1992. National contends that although debtor’s subs filed their liens postpetition, those liens nevertheless relate back to the first day each debtor’s sub performed work on the job pursuant to ORC § 1311.13 and 11 U.S.C. § 546(b) of the Code. 1 In support of its relation back argument, National cites three cases: In re Bain, 64 B.R. 581, 583 (W.D.Va.1986); In re Yobe Electric, Inc., 30 B.R. 114 (Bankr.W.D.Pa.1983), aff' d, 728 F.2d 207 (3d Cir.1984); and In re Fiorillo & Co., 19 B.R. 21, 24 (Bankr.S.D.N.Y.1982). The courts in those cases found that 11 U.S.C. § 362(b)(3) and § 546(b) work together to create an exception to the automatic stay. Those *856 sections provide that the postpetition perfection of a lien does not violate the automatic stay if applicable local law allows the lien to relate back prepetition and therefore defeat the rights of a hypothetical lien creditor pursuant to 11 U.S.C. § 544. See also 4 Collier on Bankruptcy § 546.03[2], at 546-14 (15th ed. 1992).

Whether the liens of debtor’s subs performing work on public works projects, then, relate back to the first day work was performed, depends on whether Ohio law so provides. The UCC asserts that ORC §§ 1311.26-32 provides the exclusive statutory framework under which subcontractors may file liens for work done on public projects. See State, ex. rel. General Electric Supply Co. v. Jordano Electric Co., 53 Ohio St.3d 66, 558 N.E.2d 1173, 1175 (Ohio 1990). The UCC states further that since there is no relation back provision within ORC §§ 1311.26-32, and that ORC § 1311.13 specifically excludes public projects from the relation back provision, the legislature did not intend for such a provision to apply to public construction projects. The UCC contends that since the liens do not relate back to the first day of performed work, § 546(b) is inoperative, for the relation-back provision of that section depends on “generally applicable law that permits perfection of an interest in property to be effective against an entity that acquires rights in such property before the date of such perfection.” The UCC concludes that since the liens are effective only upon filing, their postpetition filing violated the automatic stay under § 362(a)(4), and thereby rendered them void and without effect.

National’s response to the UCC’s statutory argument is that the sections of the Ohio Revised Code relating to mechanic’s liens must be interpreted holistically, and that such an interpretation compels the conclusion that the relation back provision applies to both private and public construction projects. Rather than interpreting ORC §§ 1311.01-.24 and .26-32 as distinctly applying to private and public projects respectively, as the UCC suggests, National argues that § 1311.26 is not a substantive statute, and thus, liens are not “created” pursuant to it; it is an enforcement statute which, together with ORC § 1311.28 merely create “stop notices,” which grant an assignment of monies remaining due from the owner to the prime contractor. See Turzillo Contracting Co. v. Cincinnati Metropolitan Housing Authority, 10 Ohio St.2d 5, 225 N.E.2d 255, 259 (1967). 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
151 B.R. 854, 1993 Bankr. LEXIS 408, 23 Bankr. Ct. Dec. (CRR) 1771, 1993 WL 60689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-wm-cargile-contractor-inc-ohsb-1993.