City of Conneaut v. Allegheny Surety Co.

716 N.E.2d 760, 128 Ohio App. 3d 724
CourtOhio Court of Appeals
DecidedJune 29, 1998
DocketNo. 97-A-0012.
StatusPublished
Cited by1 cases

This text of 716 N.E.2d 760 (City of Conneaut v. Allegheny Surety Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Conneaut v. Allegheny Surety Co., 716 N.E.2d 760, 128 Ohio App. 3d 724 (Ohio Ct. App. 1998).

Opinion

Ford, Presiding Judge.

This is an appeal from the Ashtabula County Court of Common Pleas. Appellant, the United States Department of Labor, Wage and Hour Division (“USDL”), appeals from a judgment entry overruling its motion for summary judgment and granting the motion for summary judgment of appellee, Allegheny Surety Company.

The following facts are not generally in dispute and are taken largely from the trial court’s judgment entry and the parties’ stipulations. On July 27, 1993, the city of Conneaut contracted with Parmenter Excavating, Inc. (“Parmenter”) to be the general contractor for the Gateway Sewer Project. The contract price was $152,106, and the project was to be funded by the United States Department of Housing and Urban Development. The agreement between Conneaut and Par-menter was subject to the labor standards of Sections 1440(g) and 5310, Title 42, U.S.Code, and Sections 327 through 332, Title 40, U.S.Code.

Parmenter breached the contract by failing to complete the project. Accordingly, numerous parties asserted claims against Parmenter. First, Conneaut claimed breach of contract. Second, appellant asserted that Parmenter had failed to pay some of its employees appropriate wages. Third, John Fithian Contract *727 ing Company (“Fithian”) and Knickerbocker Equipment Company (“Knickerbocker”), subcontractors on the project, alleged that Parmenter had failed to pay for services rendered pursuant to their agreements with Parmenter. Appellee was the surety for Parmenter’s performance on the agreement.

The dispute in this case arose from competing claims to $58,064.64 held by Conneaut in escrow. Pursuant to the parties’ agreement, the court distributed $15,000 of that amount to Fithian and $11,785.71 to Allegheny. Therefore, $31,278.93 remains in the Conneaut escrow fund, and that amount is subject to competing claims by appellant and appellee.

Fithian filed a perfected mechanic’s lien pursuant to R.C. 1311.25 et seq. against the sum held by Conneaut in the amount of $22,400, and assigned and transferred this mechanic’s lien to Allegheny on June 14, 1996. Therefore, appellee was subrogated to Fithian’s rights, if any, to the funds held by Conneaut.

Knickerbocker also perfected a mechanic’s lien pursuant to R.C. 1311.25 et seq. against Conneaut for the sum of $24,193.13, with ten percent interest. Appellee paid Knickerbocker $18,000 on its lien. Appellee was subrogated to Knickerbocker’s rights, if any, to the remaining funds held in escrow by Conneaut. Therefore, appellee is subrogated to the rights of Parmenter, Fithian, and Knickerbocker to the remaining $31,278.93 held in escrow by Conneaut.

Appellant conducted a labor standards investigation of Parmenter’s performance with respect to the Gateway Sewer Project. On September 2, 1994, appellant notified Conneaut to withhold $31,278.93 from payments to Parmenter because appellant’s investigation revealed that Parmenter failed to pay its employees $31,278.93, including $29,578.18 in prevailing wages and $2,700 in overtime wages. Appellant notified Parmenter of its investigative findings on September 9, 1994. On May 12, 1995, appellant charged Parmenter with labor violations. Parmenter failed to respond to the charges, and appellant’s assessment of $31,278.93 in back wages became final.

Accordingly, the parties disputed whether appellant or appellee had the superior claim to the $31,278.93 remaining in the Conneaut escrow account. Both parties filed complaints seeking those funds and ultimately moved for summary judgment on the issue of priority to those funds. In a judgment entry filed on January 20, 1997, the trial court granted appellee’s motion for summary judgment and overruled appellant’s motion. Therefore, the court held that appellee had lien priority to receive the remaining $31,278.93 held in escrow by Conneaut. Appellant timely filed a notice of appeal and asserts the following assignment of error:

*728 “The trial court erred in holding that mechanic’s liens filed in accordance with Ohio law have priority over the Department of Labor’s interest in contract funds to satisfy the contractor’s unpaid wages under the Davis-Bacon and related Acts.”

The sole issue in this case is which party has priority to the funds held in escrow by Conneaut. Appellant asserts that it has priority to the escrow account pursuant to its ability to withhold payment from the general contractor for a violation of the Davis-Bacon Act, Section 276 et seq., Title 40, U.S.Code. Appel-lee, on the other hand, contends that since it was subrogated to the rights of parties with perfected mechanic’s liens on the escrow fund, it has priority.

In the case at bar, the parties stipulated that the labor standards of Section 1440(g), Title 40, U.S.Code apply to the contract between Parmenter and Conneaut. According to that statute, the provisions of the Davis-Bacon Act, Section 276a et seq., Title 42, U.S.Code apply to Parmenter’s contract with Conneaut. The Davis-Bacon Act regulates the wages to be paid by a contractor to mechanics and laborers working on the construction of federally funded projects, and further provides that in federally funded projects the contract shall contain:

“[A] provision stating the minimum wages to be paid various classes of laborers and mechanics which shall be based upon the wages that will be determined by the Secretary of Labor to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the city, town, village, or other civil subdivision of the State in which the work is to be performed * * *. [TJhere may be withheld from the contractor so much of accrued payments as may be considered necessary by the contracting officer to pay laborers and mechanics employed by the contractor or any subcontractor on the work the difference between the rates of wages required by the contract to be paid laborers and mechanics on the work and the rates of wages received by such laborers and not refunded to the contractor, subcontractors, or their agents.” Section 276a(a), Title 40, U.S.Code.

When the contractor or subcontractor fails to meet these requirements:

“[T]he Federal agency, upon its own action or upon written request of an authorized representative of the Department of Labor * * * shall take such action as may be necessary to cause the suspension of the payment * * * of funds until such time * * * sufficient funds are withheld to compensate employees for the wages to which they are entitled * * *.” Section 5.9, Title 29, C.F.R.

In summary, the USDL may withhold payment from the general contractor of a federally funded construction project when the contractor fails to pay *729 those wages required by the Davis-Bacon Act. Universities Research Assn. v. Coutu (1981), 450 U.S. 754, 757, 101 S.Ct. 1451, 1454-1455, 67 L.Ed.2d 662, 667.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Safeair Contrs., Inc. v. Alabasi Constr., Inc.
2017 Ohio 7951 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
716 N.E.2d 760, 128 Ohio App. 3d 724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-conneaut-v-allegheny-surety-co-ohioctapp-1998.