THE COURT.

Action to foreclose liens of materialmen and sub-contractors. The court gave the plaintiff, as assignee of the original claimants, a judgment against the owners for $2988.40, with interest, and also for the foreclosure of a lien upon the property for said amount. The said owners appeal from the judgment and from an order denying their motion for a new trial.

The complaint is in six counts, each setting up the claim of one of plaintiff’s assignors. The plaintiff alleged the due execution and filing of a written contract between the appellants, as owners, and the defendants Jordan & Cram, as contractors, for the erection of a four-story and basement brick building for the agreed price of fourteen thousand dollars. It is averred that Jordan & Cram proceeded with the construction of the building until on or about the seventeenth day of April, 1906, when said contract was abandoned, but no notice of *437 cessation of labor has ever been filed. The assignors of plaintiff filed their respective claims of lien, and each, during the progress of the work, served upon the owners written notice of the furnishing of materials and the performing of labor, in the amounts claimed. (Code Civ. Proc., sec. 1184.) Bach count alleges, upon information and belief, that at the time of so serving notice, and. at all times since, there was and now is due and unpaid from the owners to the contractors, on account of the contract price, more than five thousand dollars, “which is applicable to the aforesaid claim, and the lien therefor.”

The answers of the owners undertake to deny (although the denial is perhaps insufficient in form), that, at the time of the service of the notices, or thereafter, anything was due from the owners to the contractors. They deny the furnishing of labor or materials by the respective assignors of plaintiff, and allege, affirmatively, that the building was, on the eighteenth day of April, 1906, destroyed by fire. They allege further, that the contract has never been completed, and that no money is due or owing to the original contractors.

The court found that all the allegations of the complaint (except the third count thereof) were true. "With reference to the affirmative matter pleaded, there was a finding “that on the 19th day of April, 1906, a general conflagration took place in the above city and county, by which said building was partially destroyed, without any fault of defendants, but that a material part thereof of the value of $5000 remained intact; that at the time of said fire said building was almost but not entirely completed and had not been accepted, but there was then due to the contractors, Jordan & Cram, by said owners, pursuant to the terms of said contract between them for the erection of said building, the sum of $5500, no part of which has ever been paid.” Judgment followed as above stated.

The briefs of counsel are, in large part, devoted to a discussion of the question whether the rule declared in Humboldt Lumber Mill Co. v. Crisp, 146 Cal. 686, [106 Am. St. Rep. 75, 81 Pac. 30], is applicable here. In that case it was decided that a mechanics’ lien for work and materials furnished for the construction of a building could not attach where the building had, without the fault of the owner, been destroyed before it was completed and before the claim of lien was filed. *438 This conclusion was based upon the “peculiar language of our mechanics’ lien law,” providing for a lien, not only upon the building, but also upon the land covered by it and so much other land as may be required for its convenient use and occupation, a mode of expression which, as the court says, “looks to an existing house that can be occupied in the future, and not to a vacant lot upon which no house exists.” A further reason for denying a lien in case of the destruction of the structure was found by the court in the view that the true consideration for the lien is the benefit conferred upon the owner by placing labor and materials in his building, and that where the building is destroyed before completion, no such benefit can be enjoyed by the owner.

We think neither of these grounds is applicable where the destruction is only partial and a substantial part of the structure remains to the owner. There can be no insurmountable difficulty in determining the amount of ground necessary for the convenient use and occupation of a building which has been damaged, but which may be restored and completed so as to be fit for occupancy. Nor is the owner, by such partial de-. struction, necessarily deprived of all benefit of the labor and materials which have gone into the structure of which a material part remains.

Where a valid contract has been filed, as was done here, the lien claimants are merely substituted to the original contractors, and their right to enforce their liens against the owners depends on whether or not the original contractor has a money demand against the owner growing out of the building contract. “The liability of an owner, who has on his part complied with all the terms of a valid contract, is limited to the price which by his contract he has agreed to pay.” (Hoffman-Marks Co. v. Spires, 154 Cal. 111, [97 Pac. 152]; Kellogg v. Howes, 81 Cal. 179, [6 L. R A. 588, 22 Pac. 509]; Stimson Mill Co. v. Braun, 136 Cal. 122, [89 Am. St. Rep. 116, 57 L. R. A. 726, 68 Pac. 481]; Latson v. Nelson, (Cal.) 11 Pac. C. L. J. 589.) But up to this limit of liability, the claimants, by filing their liens, acquire a right to share in any money owing from the owners to the original contractors on account of the contract, and their right, to this extent, is secured by a lien on the property. The court in this case found that at the time of the fire there was due from the owners to the contractors, under the contract, *439 the sum of fifty-five hundred dollars, no part of which has been paid. The effect of the filing of the liens was to transfer from the contractors to the lien claimants the right to receive this money, so far as necessary to satisfy the liens. If the owners are liable for the amount, it does not concern them whether they pay it to the contractors or to the lienors. There being a substantial structure to which the liens may attach, they should be held good to the extent of the amount due from the owners to the contractors.

The finding that this balance was due from the owners to the original contractors, justified also the personal judgment against the owners. The service of notices to withhold pursuant to the provisions of section 1184 of the Code of Civil Procedure, operated, in effect, as a garnishment or equitable assignment of the amounts due or thereafter becoming due to the contractors under the contract, and entitled the persons serving the notice to receive so much of said amounts as would satisfy their claims. (Bates v. Santa Barbara Co., 90 Cal. 543, [27 Pac. 438]; Bianchi v. Hughes, 124 Cal. 24, [56 Pac. 610].) The appellants attack, as unsupported by the evidence, this finding that fifty-five hundred dollars was due from the owners to the contractors and was applicable to the payment of the liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A-1 Door & Materials Co. v. Fresno Guarantee Savings & Loan Ass'n
394 P.2d 829 (California Supreme Court, 1964)
Fredericksen v. Harney
199 Cal. App. 2d 189 (California Court of Appeal, 1962)
Calhoun v. Huntington Park First Savings & Loan Ass'n
186 Cal. App. 2d 451 (California Court of Appeal, 1960)
Fisher v. Groff
3 Pa. D. & C.2d 49 (Lancaster County Court of Common Pleas, 1955)
Caird Engineering Works v. Seven-Up Gold Mining Co., Inc.
111 P.2d 1267 (Montana Supreme Court, 1940)
Albuquerque Lumber Co. v. Montevista Co.
38 P.2d 77 (New Mexico Supreme Court, 1934)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
G. Ganahl Lumber Co. v. Weinsveig
143 P. 1025 (California Supreme Court, 1914)
Dorris v. Alturas School District
142 P. 795 (California Court of Appeal, 1914)
In re Cotton
209 F. 124 (N.D. California, 1913)
Diamond Match Co. v. Silberstein
131 P. 874 (California Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
117 P. 512, 160 Cal. 435, 1911 Cal. LEXIS 531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butler-v-ng-chung-cal-1911.