Kellogg v. Howes

22 P. 509, 81 Cal. 170, 1889 Cal. LEXIS 1007
CourtCalifornia Supreme Court
DecidedNovember 9, 1889
DocketNo. 13324
StatusPublished
Cited by37 cases

This text of 22 P. 509 (Kellogg v. Howes) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kellogg v. Howes, 22 P. 509, 81 Cal. 170, 1889 Cal. LEXIS 1007 (Cal. 1889).

Opinions

Works, J.

This action was brought by the respondents as material-men, laborers, and subcontractors against the appellants, to enforce a lien for material furnished and for labor done in the construction of a dwelling-house. The appellant Howes was the owner of the real estate, and contracted with his co-defendant to construct the building, and the latter contracted with the respondents for the labor and material done and furnished by them. The contract price for constructing the building was more than one thousand dollars, and the contract was not filed for record as required by section 1183 of the Code of Civil Procedure. The respondents had actual notice that there was a contract between the owner and his contractor, and gave no notice to the owner to withhold payments to such contractor. The owner paid the contractor the greater part of the contract price. The amounts for which the respondents claimed liens exceeded the amount- due the [172]*172contractor, and unpaid, assuming the contract to have been valid, but were less than the full contract price. The court below held the contract to be void, for the reason that it was not filed for record, and that the respondents were entitled to recover the value of the material furnished and labor done by them without any reference to the amount remaining unpaid to the original contractor by the owner. The only question presented and argued on this appeal is, whether or not a material-man or subcontractor can recover beyond the amount unpaid by the owner to the original contractor on the contract, where the same has not been recorded, and where no personal notice has been given by such material-man or subcontractor to the owner to withhold the payments due such contractor, the material-man and subcontractor having actual notice that there was such a contract.

Counsel for appellants contend, with much earnestness and ingenuity and with marked ability, that the right of the material-man and subcontractor to enforce his lien is liniited, where he lias given no personal notice to the owner, to the amount remaining unpaid by the owner to the original contractor. They contend, in substance, that, although the contract is void as between the parties to it, it is not void as to the owner and the material-men and subcontractors; that there is a distinction between an original contractor and a material-man or subcontractor, in that the former has a direct lien upon the real estate of the owner to the full extent of the amount due him, based upon the personal liability of the owner to him, while the latter have but a lien in the nature of an attachment against the money in the hands of the owners and due the contractor, and that the legislature had no power to make the owner or his property liable to any greater extent. There is, perhaps, not a single one of these propositions that- is not, to some extent, supported by some decision or dictum of this court.. [173]*173The question is, therefore, whether these decisions or dicta are applicable to the present provisions of the mechanic’s lien law, and, if so, whether they are such as should control us in the interpretation of such provisions.

The present code, so far as it affects this question, provides: “ In case” of a contract for the work, between the owner and his contractor, the lien shall extend to the entire contract price, and such contract shall operate as a lien in favor of all persons, except the contractor, to the extent of the whole contract price; and after all such liens are satisfied, then as a lien for any balance of the contract price in favor of the contractor. All such contracts shall be in writing when the amount agreed to be paid thereunder exceeds one thousand dollars, and shall be subscribed by the parties thereto, and shall, before the work is commenced, be filed in the office of the county recorder of the county, or city and county, where the property is situated, who shall receive one dollar for such filing; otherwise they shall be wholly void, and no recovery shall be had thereon by either party thereto; and in such case the labor done and materials furnished by all persons aforesaid, except the contractor, shall be deemed to have been done and furnished at the personal instance of the owner, and they shall have a lien for the value thereof.” (Code Civ. Proc., sec. 1183.)

Again; “No payment made prior to the time when the same is due under the terms and conditions of the contract shall be valid for the purpose of defeating, diminishing, or discharging any lien in favor of any person, except the contractor, but as to such liens such payment shall' be deemed as if not made, and shall be applicable to such liens notwithstanding the contractor to whom it was paid may thereafter abandon his contract, or be or become indebted to the owner in any amount, for damages or otherwise, for non-performance of his contract or otherwise. .... All such contracts [174]*174and alterations thereof as do not conform substantially to the provisions of this section shall be wholly void, and no recovery shall be had thereon by either party thereto; and in such case the labor done and materials furnished by all persons, except the contractor, shall be deemed to have been done and furnished at the personal instance of the owner, and they shall have a lien for the Value thereof. Any of the persons mentioned in section 1183, except the contractor, may, at any time, give to the owner a written notice that they have performed, labor or furnished materials, or both, to the contractor, or other person acting by authority of the owner, or that they have agreed to do so, stating in general terms the kind of labor and materials, and the name of the person to or for whom the same was done or furnished, or both, and the amount in value, as near as may be, of that already done or furnished, or both, and of the whole agreed to be done or furnished, or both.....Upon such notice being given, it shall be the duty of the owner to,, and he shall, withhold from his contractor, or from any other person acting under such owner, and to whom by said notice the said labor or materials, or both, have been furnished or agreed to be furnished, all money due, or that may become due, to such contractor, or other person, or sufficient of such money to answer such claim and any lien that may be filed therefor, for record, under this chapter, including costs and counsel fees provided for in this chapter, until such notice is by writing withdrawn; and all money paid thereafter by the owner to the contractor, or such other person, while such notice is in force, shall, for the purposes of all liens of all persons, except that of the contractor, be deemed a payment prior to the time the same was due within the meaning of and subject to the provisions of this section.” (Code Civ. Proc., sec. 1184.)

It has been held in a number of cases under earlier ■ statutes that a subcontractor or material-man could en[175]*175force his lien only to the extent of the contract price remaining unpaid, and that, too, under statutes providing that subcontractors should have a lien “ regardless of the claim of the contractor against the owner,” or that the lien should inure “to the extent of the contract price,” and “ whether done or furnished at the instance of the owner or his agent,” and “that the contractor should be deemed such agent, and that the lien should not be affected by the fact that no money was due the contractor.”

Counsel for appellants have industriously gathered up and cited these earlier statutes and the .cases decided Under them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Himrich v. Carpenter
1997 SD 116 (South Dakota Supreme Court, 1997)
Drake v. Martin
30 Cal. App. 4th 984 (California Court of Appeal, 1994)
Johnson v. City of San Pablo
283 P.2d 57 (California Court of Appeal, 1955)
Reeves v. Nichols
216 P.2d 555 (California Court of Appeal, 1950)
Booth-Kelly Lumber Co. v. Oregon & California R.
193 P. 463 (Oregon Supreme Court, 1920)
Server v. Lang
92 Vt. 501 (Supreme Court of Vermont, 1918)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
Prince v. Hill
149 P. 578 (California Supreme Court, 1915)
G. Ganahl Lumber Co. v. Weinsveig
143 P. 1025 (California Supreme Court, 1914)
Curtis v. Nunns
54 Colo. 554 (Supreme Court of Colorado, 1913)
Butler v. Ng Chung
117 P. 512 (California Supreme Court, 1911)
Clark v. Beyrle
116 P. 739 (California Supreme Court, 1911)
Coghlan v. Quartararo
115 P. 664 (California Court of Appeal, 1911)
Stockton Lumber Co. v. Schuler
101 P. 307 (California Supreme Court, 1909)
Hoffman-Marks Co. v. Spires
97 P. 152 (California Supreme Court, 1908)
Baker v. Lake Land Canal & Irrigation Co.
94 P. 773 (California Court of Appeal, 1908)
Merced Lumber Co. v. Bruschi
92 P. 844 (California Supreme Court, 1907)
Hampton v. Christensen
84 P. 200 (California Supreme Court, 1906)
Chicago Lumber Co. v. Newcomb
19 Colo. App. 265 (Colorado Court of Appeals, 1903)
State v. Gregory
71 S.W. 170 (Supreme Court of Missouri, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
22 P. 509, 81 Cal. 170, 1889 Cal. LEXIS 1007, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kellogg-v-howes-cal-1889.