Clark v. Beyrle

116 P. 739, 160 Cal. 306, 1911 Cal. LEXIS 515
CourtCalifornia Supreme Court
DecidedJune 29, 1911
DocketL.A. No. 2624.
StatusPublished
Cited by9 cases

This text of 116 P. 739 (Clark v. Beyrle) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark v. Beyrle, 116 P. 739, 160 Cal. 306, 1911 Cal. LEXIS 515 (Cal. 1911).

Opinions

The controversy in this action is over the right of the plaintiffs to receive payment of certain demands out of moneys due from the city of Santa Barbara to Robert Beyrle for work done in the construction of a tunnel.

The city of Santa Barbara undertook to construct a water conduit tunnel running in a northerly and southerly direction through the Santa Ynez Mountains for a length of some nineteen thousand feet. Contracts for the construction of the northerly 8,560 feet of the tunnel were entered into between the said city and Beyrle. For the purpose of doing the work this part of the tunnel was divided into nine sections numbered respectively 20, 19, 18, 17, 16, 15, 14, 13, and 12. Section 20 was the first section from the northerly mouth of the tunnel and the others ran successively southerly in the inverse order of their numbers. Section 20 was five hundred and sixty feet in length and each of the other sections one thousand feet. The respective contracts were similar in form, specific prices being agreed upon for each cubic yard of excavation and for each thousand feet of timbering, while *Page 308 the rate for hauling excavated matter out of the tunnel increased with the distance from the mouth in hundred feet lengths.

The complaint sets forth the making of a single contract and alleges that it was put in the form of nine several and separate agreements. It alleges further that Beyrle entered upon the performance of the contract and after completing section 20 made an agreement with T.A. McCullough whereby the latter was to complete the work as subcontractor. The plaintiffs Clark and Little became associated with McCullough in the work and ultimately succeeded to all of his interest under his contract with Beyrle. Said Clark and Little continued to perform the contract between Beyrle and the city of Santa Barbara until February 13, 1908, when by reason of the alleged failure of Beyrle to keep certain terms of the contract between himself and McCullough said Clark and Little were compelled to abandon the work. Thereupon Beyrle re-entered upon the performance of the contract between himself and the city of Santa Barbara and from February 13, 1908, to June 10, 1908, employed Warren W. Clark to superintend such performance. It is alleged that while the work of construction was being carried on by the firm of Clark and Little the plaintiff Norman W. Clark performed labor for said Clark and Little upon said tunnel and that a balance of $1,395.50 remains unpaid to him on account of said work; that during the same time the plaintiff John G. Sanborn performed work for Clark and Little upon said tunnel and that a balance of $757.17 remains due to him; that during the same period Minnie Chant performed labor on said tunnel "as cook for the laborers and others engaged in the construction thereof" and that a balance of $780.04 remains due to her.

On July 2, 1908, each of the claimants gave to the defendant city of Santa Barbara written notice that they had respectively performed said labor and notified the city to withhold from the defendant Beyrle sufficient money then due or to become due to him to answer the respective claims of said plaintiffs. The complaint alleges that there is due from the city for the unpaid portions of the completed work upon said tunnel the sum of $3,977.91, which the city is holding pursuant to said notices. Judgment is asked for *Page 309 the sums alleged to be due to the respective plaintiffs. The plaintiffs also seek to hold the defendant The Title Guaranty and Trust Company, which, as surety, signed a bond attached to the contract, and guaranteeing faithful performance by Beyrle.

The answers of the defendants contained a number of denials which need not be here detailed. Upon the issues so made the court made its decision. With reference to the contracts, the court found that nine separate agreements were made between the city of Santa Barbara and Beyrle for the construction of nine successive portions or sections of the tunnel, the terms of such agreements being as hereinbefore stated. It is found that the agreements were so severally executed for the purpose of enabling Beyrle to receive payments in full for the successive portions of said construction. The agreement with McCullough and the transfer of McCullough's rights to Clark and Little are found as alleged in the complaint. It is found that sections 20, 19, 18, and 17 of the proposed tunnel were completed and accepted by the city on January 5, 1905, November 23, 1905, February 25, 1907, and December 27, 1907, respectively, and all balances due to Beyrle from the city under the agreements providing for the construction of said sections were respectively paid to Beyrle by the city thirty-six days after the respective dates of completion and acceptance of the sections, and the defendant Title Guaranty and Trust Company was discharged by the city from all liability on account of said agreements. Between January 31, 1906, and February 13, 1908, the plaintiff Norman W. Clark performed labor upon the tunnel at the request of Clark and Little and a balance of $1,395.50 remains due and unpaid to him. It is further found, however, that only $152.90 of this amount accrued after the twenty-seventh day of December, 1907, (i.e., the date of the completion of section 17 of the tunnel) and the last-named amount is all that accrued for labor performed on section 16. There are similar findings with respect to the plaintiff John C. Sanborn that a balance of $757.17 is due, but only $129.25 of this amount is due for labor performed in the construction of section 16. Likewise, the court finds that Minnie Chant performed labor as alleged, but finds that only $76.45 of her claim accrued while the firm of Clark and Little was engaged *Page 310 in the construction of section 16. The court finds, further, that there is due from the city of Santa Barbara the sum of $3,977.91 on account of the construction of section 16 of the tunnel and that the said city is holding this sum to abide the event of this action. The conclusions of law are to the effect that none of the plaintiffs is entitled to any judgment for labor performed on the tunnel prior to the completion of section 17 and that plaintiffs Norman W. Clark and Sanborn are entitled to judgments that the city of Santa Barbara pay them the amounts found to be due for labor performed on section 16, — that is to say, $152.90 to the plaintiff Norman W. Clark and $129.25 to the plaintiff John G. Sanborn. As regards the plaintiff Minnie Chant the conclusion is that she is not entitled to any judgment.

There were also findings and conclusions of law in favor of a claim of Warren W. Clark, but as the disposition of this claim is not disputed we shall make no further reference to it.

On the foregoing findings and conclusions of law judgment was entered that the city of Santa Barbara pay plaintiffs Norman W. Clark and John G. Sanborn the amounts found to be due to them as aforesaid and that the plaintiff Minnie Chant take nothing by this action. There is a further declaration in the judgment that plaintiffs Norman W. Clark and John G. Sanborn "take nothing by this action except as hereinbefore adjudged."

The present appeal is taken by Norman W. Clark, John G. Sanborn, and Minnie Chant from those parts of the judgment which adjudge that said plaintiffs Clark and Sanborn take nothing by this action except as in said judgment adjudged, and that said plaintiff Minnie Chant take nothing.

A preliminary motion to dismiss the appeals of Clark and Sanborn is made by the respondents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Primo Team, Inc. v. Blake Construction Co.
3 Cal. App. 4th 801 (California Court of Appeal, 1992)
Pacific Employers Insurance v. State of California
477 P.2d 129 (California Supreme Court, 1970)
Theisen v. County of Los Angeles
352 P.2d 529 (California Supreme Court, 1960)
Holtzman v. Bennett
229 P. 1095 (Nevada Supreme Court, 1924)
Fuller v. Towne
193 P. 88 (California Supreme Court, 1920)
Sweeney v. Board of Trustees of Auburn School District
165 P.2d 42 (California Court of Appeal, 1917)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
Acme Lumber Co. v. Wessling
126 P. 167 (California Court of Appeal, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
116 P. 739, 160 Cal. 306, 1911 Cal. LEXIS 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-v-beyrle-cal-1911.