Pacific Rolling Mill Co. v. Bear Valley Irrigation Co.

52 P. 136, 120 Cal. 94, 1898 Cal. LEXIS 718
California Supreme Court·Decided February 12, 1898·No. L. A. No. 264·Published·Cited by 6 cases

Opinion

CHIPMAN, C.

The defendant, Bear Valley Irrigation Company, was incorporated under the laws of this state for the purpose of engaging in very many kinds of business. Among other of its undertakings was that of constructing a canal or aqueduct, [95]*95called “Santa Ana canal,” from a point on the Santa Ana river, known as the company’s head works, through what is called Blair’s Pass, to the Alessandro & Perris Irrigation districts, in Biverside county. The entire proposed line of canal comprised what are termed in the transcript divisions 1, 2, 3, and 4. The work of construction began about December, 1892; divisions 1 and 2 were completed September 16, 1893, when construction work ceased; division 3 was partly graded; division 4 was only surveyed. The route of the canal was down the Santa Ana river for about three miles, where it left that stream and crossed the dividing water shed to Mill creek, where at the head of what is called the Alessandro pipe line of the company, previously constructed and in operation, divisions 1 and 2 ended. Division 3 vras to follow substantially the route already taken by the Alessandro pipe line to Blair’s Pass. Below this point the line was called division 4. Plaintiff and plaintiff’s assignors furnished materials used in the construction of divisions 1 and 2. This action was brought to foreclose plaintiff’s liens. The complaint and liens were so drawn as to claim a lien on divisions 1, 2, and 3, or on 1 and 2, as the facts might warrant, but did not include the Alessandro pipe line or other of the company’s works. Plaintiff had judgment foreclosing its liens on divisions 1 and 2. After the action was brought, J. A. Graves and A. P. Maginnis, who had been appointed receivers of defendant company by order of the United States circuit court, and to whom, as such receivers, the defendant company had transferred all its property, answered the complaint and now prosecute this appeal, by bill of exceptions, from the judgment and from the order denying motion for new trial.

1. Appellants challenge the sufficiency of the evidence to justify findings 5, 10, 13, and 15, which are to the effect, briefly stated, that divisions 1 and 2 of the “Santa Ana Canal” form a complete structure within the meaning of section 1183 of the Code of Civil Procedure, and do not and never did form a part of an entire and continuous line or system of canals, and that the said canal does not extend beyond the head of the Alessandro pipe line.

As I understand the position of appellants, it is that the lien [96]*96should have been claimed upon the entire system of defendant company, or should at least have included division 3 .and the Alessandro pipe line: that “the word ‘structure/ as used in section 1183 of the statute, means an entire thing; that the statute makes no distinction between buildings, railroads, ditches, flumes, aqueducts, mining claims, or other structures; therefore, a ditch or flume which forms a part of a continuous line of canal, owned and operated by one person or company, is as much an entirety as a railroad, and the law with reference to mechanics’ liens on railroads is clearly applicable to such cases.” Cox v. Western Pac. R. R. Co., 44 Cal. 28, where a lien was filed on a portion of a railroad, and Williams v. Mountaineer etc. Co., 102 Cal. 134, where the lien was claimed on a portion of the property comprising a mill, tramway, boarding-house, and other buildings, belonging to a mining claim, are relied upon by appellants. Appellants also cite Brooks v. B. & S. Railway Co., 101 U. S. 443; Farmer’s etc. Co. v. Candler, 87 Ga. 241; National etc. Works v. Oconto etc. Co., 52 Fed. Rep. 43; affirmed, 59 Fed. Rep. 19; Midland Ry. Co. v. Wilcox, 122 Ind. 84; Helm v. Chapman, 66 Cal. 291; Willamelte etc. Co. v. Kremer, 94 Cal. 205; Wright v. Cowie, 5 Wash. 341; Knapp v. St. Louis etc. Ry. Co., 74 Mo. 374. Ho intelligent application of the cases cited can be made without a clear understanding of the facts. William Ham Hall testified: “I planned the Santa Ana canal; the objective point of that canal was the Alessandro tunnel, which is from twelve to twenty miles from the head, of the Alessandro pipe line, depending on the route which might be followed. Divisions 1 and 2 were planned so as to go to Mill creek, near the head of the pipe line. Division 3 ran thence to Blair’s Pass, almost parallel to the pipe line.” Again he testified: “It was realized from the beginning that water would have to be turned into that pipe as a temporary expedient; the canal was not regarded as a mere feeder to the pipe, but the canal was projected to be built through to the tunnel. -If the canal had been constructed through to the tunnel the pipe Ene had no utility.” Again: “The intention was to take up the Alessandro pipe line from its head to Blair’s Pass, seeing that it ran parallel to the canal for that length and would be of no use; .... or perhaps use a small piece of it in the neighborhood of Blair’s Pass by con[97]*97necting with the canal there.” On cross-examination, he was asked: “Q. Wasn’t it the intention from the beginning that when the Santa- Ana canal was constructed, to the Alessandro pipe line to connect the two together? A. Mo, sir, it was not. From the beginning it was' not intended to put the Santa Ana canal there at all.” It appeared that the canal had a capacity of six thousand miner’s inches, while the pipe could carry only nine hundred to one thousand miner’s inches. A witness for appellants testified that this pipe line was finished about May or June, 1891, and took water from Mill creek from that time until September, 1893. Appellants introduced certain proceedings of defendant company in relation to acquiring temporarily, from certain persons, the right to take water from Mill creek to run in this pipe, but there is nothing in this evidence inconsistent with the testimony of Mr. Hall that the pipe line was used only as “a temporary expedient,” and in fact formed no part of the system of which the Santa Ana canal was, what this witness termed, “the main artery.”

The defendant company owned what is known as Bear Valley reservoir for the storage of water, several miles above the “head works.” Bear creek empties into Santa Ana river about four miles above the head of the canal. Water is taken directfy from Santa Ana river into the canal, and at some seasons of the year part of the water comes from this storage reservoir. The company also takes water from Santa Ana river for ditches and flumes other than and wholly independent of the canal,

Division 3 was never completed. Mr. Hall testified: “It has never been a completed canal. It has never been in condition to be used as a canal. It has nevér been graded for its entire length. The reason why it was not graded was that the company did not have the right of way; at places there are flumes yet to be built; from half a dozen to eight pieces of flume to be built, aggregating between three and four thousand feet. There were tunnels yet to be constructed—at least six—I don’t remember the exact number.” On cross-examination he said: “One place that I know of my own knowledge where the company did not have a right of way was through a tract owned by a man named McIntosh, and the distance was nearly three-quarters [98]

Free access — add to your briefcase to read the full text and ask questions with AI

Pacific Rolling Mill Co. v. Bear Valley Irrigation Co., 52 P. 136, 120 Cal. 94, 1898 Cal. LEXIS 718 (Cal. 1898).

52 P. 136 (Pacific Rolling Mill Co. v. Bear Valley Irrigation Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Deiner v. Sutermeister
178 S.W. 757 (Supreme Court of Missouri, 1915)
Kosidowski v. City of Milwaukee
139 N.W. 187 (Wisconsin Supreme Court, 1913)
Clark v. Beyrle
116 P. 739 (California Supreme Court, 1911)
Granquist v. Western Tube Co.
88 N.E. 468 (Illinois Supreme Court, 1909)
Bank of Woodland v. Heron
54 P. 537 (California Supreme Court, 1898)