Midland Railway Co. v. Wilcox

23 N.E. 506, 122 Ind. 84, 1890 Ind. LEXIS 52
CourtIndiana Supreme Court
DecidedJanuary 16, 1890
DocketNo. 13,686
StatusPublished
Cited by25 cases

This text of 23 N.E. 506 (Midland Railway Co. v. Wilcox) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midland Railway Co. v. Wilcox, 23 N.E. 506, 122 Ind. 84, 1890 Ind. LEXIS 52 (Ind. 1890).

Opinion

Elliott, J.

Wilcox seeks by his complaint' to foreclose a lien which he asserts he holds by the assignment of part of an estimate, certified to him by the appellant’s engineer, against an unfinished railroad of which the appellant is the owner. Holleran and Ingerman filed a cross-complaint, asserting a lien, and claiming the right to enforce it as the assignees of the persons with whom the construction contract was entered into by the railroad company.

We do not deem it necessary to give a synopsis of the pleadings, for the reason that the special finding contains the material facts, and we can, without a repetition, determine all the material questions of law arising in the case upon the facts contained in the special finding.

The facts, as they appear in the special finding, may be [86]*86thus summarized : On the 4th day of June, 1885, the Cleveland, Indiana and St. Louis Railroad Company was the owner of a line of railroad extending from the city of Anderson to the city of Lebanon; that part of the road lying between Noblesville and Anderson was completed and in operation, but that part between Noblesville and Lebanon was not completed or in operation. On the day named the company entered into a contract with Parker & Co. for the construction of its unfinished railroad; before any work was done under this construction contract the Midland Railway Company became the successor of the Cleveland, Indianapolis and St. Louis company, and accepted the contract which the latter had made with Parker & Co. Under the direction of the Midland company, and in accordance with the terms of the contract, the original contractors and their assignees performed labor and furnished materials to the Midland company, estimates were certified by its engineer for the principal part of the sum owing the contractors for the labor done and materials furnished. The aggregate sum was evidenced by eleven estimates certified by the company’s chief engineer. On the 15th day of July, 1885, Parker & Co., assigned twelve hundred dollars of the estimate for June, 1885, to the plaintiff, Wilcox, as collateral security for a loan of that amount. On the 15th day of August, 1885, Parker assigued his interest in the construction contract to his partners, Prisco and Fiorella, and they subsequently assigned to Holleran, Ingerman and Haverstick, but the latter afterwards assigned his interest to his associates, Holleran and Ingerman. In the contract of assignment to Holleran, Ingerman and Haverstick, it was stipulated that they should have all the rights and claims of every description of the assignors. On the 2d day of October, 1885, Holleran and Ingerman filed a notice of their intention to hold a lien on the railroad for work done and materials furnished under the construction contract, and stated therein the amount owing them, and stating, also, what was included in the estimates, and what had not been [87]*87estimated. This notice describes the entire line of uncompleted road and appurtenances, and recites the assignment to Wilcox of twelve hundred dollars of the -June estimate. On the 23d day of November, a similar notice of an intention to hold a lien on the road and appurtenances was filed in the recorder’s office of Hamilton county, and notice was also filed in Boone county, and it was recorded on the 28th day of that month. The labor and materials, included in the estimates and mentioned in the notices, was performed upon and were furnished for that part of the road between Noblesville and Lebanon, the part between Noblesville and Anderson having been completed and in operation at the date of the construction contract. The estimates prepared by the engineer do not divide the work so as to show what part of the materials were furnished for the separate parts of the road, nor do they show what part of the work was done in Hamilton county and what part in Boone, but in performing the work and furnishing the materials the contractors and the engineer treated the work as a continuous line extending from Noblesville to Lebanon, and as not separated by any divisions. The value of the work done upon the road and materials furnished therefor in the county of Hamilton as estimated by the engineer is $8,160.06, and the value of the work done upon and materials furnished for the road in Boone county is $3,400. The contractors have been paid at different times sums amounting in the aggregate to $4,-132.49. The payments were made generally and without regard to the county in which the work was done. In addition to the payments referred to Holleran and Ingerman were paid $1,760 on the 15th day of February, 1886, on general account. Actions were brought by divers sub-contractors in which judgments were rendered, amounting in the aggregate to $1,088.17 principal, $141.70 attorney’s fees, and costs $243.20, making a total of $1,473.07. Holleran and Ingerman were not parties to any of these actions, but they testified as witnesses in them. All of the judgments ex[88]*88cept two, one in favor of Presser and Downing for $508.54, and one in favor of Reuben Grebler for $64.50 were paid by the company. The judgment in favor of Presser and Downing was for timber, and it was for $311.54 more than the value of timber furnished by them. The actions in which judgments were rendered were brought after the 5th day of November, 1886, and after the railway company had made default in payment. The assignors, Prisco and Fiorella, under the terms of their contract with their assignees, Holleran and Ingerman, are indebted to the latter in the sum of $4,358.56. The amount due Wilcox is $758.50.

In so far as the conclusions of law are material to the controversy waged in this court they are, in substance, these:

1st. The plaintiff has a lien for $798.50 upon that part of defendant’s road in Hamilton county and west of Nobles-ville.

2d. The cross-complainants, Holleran and Ingerman, have a lien upon the road between Noblesville and Lebanon for $3,950.50.

The question which comes first in logical order, is whether the lien asserted under the construction contract exists and is enforceable. In 1883 a statute was enacted giving a lien to all persons who do work upon a railroad not in operation, or furnish materials for it, and in 1885 this statute was amended. Elliott’s Supp., sections 1699 and 1704. There is, therefore, a statutory lien created by law, and the question is as to the extent and nature of the lien, and whether the plaintiff and the cross-complainants are within the law.

The act of 1883 was in force when the construction contract was made, for it was not supplanted by the act of 1885, since that act, although it was passed some months before the contract was entered into, did not take effect until July 18th, 1885, but we do not regard the later act as in any respect impairing the lien created by the earlier statute. The later law, so far from impairing the lien, really enlarged it, by making the provisions of the act of 1883 explicit and [89]*89clear. The amendatory act did not profess to sweep away any rights existing under the former act, nor to create an entirely new. and different lien. What it professes to do, and what it does accomplish, is to clear away obscurities in the former act, and in some degree change the mode of securing and enforcing the lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cline v. Indianapolis Mortar & Fuel Co.
117 N.E. 509 (Indiana Court of Appeals, 1917)
Fleming v. Greener
90 N.E. 73 (Indiana Supreme Court, 1909)
Fleming v. Greener
83 N.E. 354 (Indiana Court of Appeals, 1908)
Pere Marquette Railroad v. Baertz
74 N.E. 51 (Indiana Court of Appeals, 1905)
Mulky v. Karsell
68 N.E. 689 (Indiana Court of Appeals, 1903)
Smith v. Tate
66 N.E. 88 (Indiana Court of Appeals, 1903)
Midland Railway Co. v. Trissal
65 N.E. 543 (Indiana Court of Appeals, 1902)
Ban v. Columbia Southern Ry. Co.
117 F. 21 (Ninth Circuit, 1902)
Wiley v. Connelly
60 N.E. 784 (Massachusetts Supreme Judicial Court, 1901)
Connor v. Tennessee Cent. Ry. Co.
109 F. 931 (Sixth Circuit, 1901)
Sprague Investment Co. v. Mouat Lumber & Investment Co.
14 Colo. App. 107 (Colorado Court of Appeals, 1899)
Citizens State Bank v. Julian
55 N.E. 1007 (Indiana Supreme Court, 1899)
Teague v. Whaley
50 N.E. 41 (Indiana Court of Appeals, 1898)
Wabash Railroad v. Achemire
49 N.E. 835 (Indiana Court of Appeals, 1898)
Pacific Rolling Mill Co. v. Bear Valley Irrigation Co.
52 P. 136 (California Supreme Court, 1898)
Trueblood v. Shellhouse
49 N.E. 47 (Indiana Court of Appeals, 1898)
Adams v. Grand Island & W. C. R.
72 N.W. 577 (South Dakota Supreme Court, 1897)
Upland Land Co. v. Ginn
43 N.E. 443 (Indiana Supreme Court, 1896)
Bratton v. Ralph
42 N.E. 644 (Indiana Court of Appeals, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
23 N.E. 506, 122 Ind. 84, 1890 Ind. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midland-railway-co-v-wilcox-ind-1890.