McDonald v. Hayes

64 P. 850, 132 Cal. 490, 1901 Cal. LEXIS 1094
CourtCalifornia Supreme Court
DecidedApril 27, 1901
DocketS.F. No. 1822.
StatusPublished
Cited by10 cases

This text of 64 P. 850 (McDonald v. Hayes) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonald v. Hayes, 64 P. 850, 132 Cal. 490, 1901 Cal. LEXIS 1094 (Cal. 1901).

Opinion

HAYNES,C.

—Action to foreclose mechanic’s liens in favor of the several plaintiffs, who had judgment foreclosing each of their several hens, and defendants.Esther Attell and Seymour Attell appeal from the judgment and from an order denying a new trial. Hayes did not answer.

Esther Attell is, and was, the owner of a house and lot in the city of San Francisco, and on November 21, 1896, entered into a written contract with defendant Hayes to make certain alterations and repairs upon the building upon said lot. This contract was duly' recorded before the work was commenced, and no question is made as to its validity. Hayes was to receive for the work and materials $2,200, to be paid in install *492 ments,—the first two of $415 each; the third, $400; the fourth, $420; and the last, $550, to be paid thirty days after completion,—the time for the payment of the first four installments being fixed by specified conditions of the work. Hayes entered upon and pursued the work in accordance with the contract until he had earned and received the first and second installments, amounting to $830, and on January 27, 1897, in the language of the finding, “he entirely ceased labor thereon without completing said building”; and the court further found that from and after that date no work of any kind was done thereon until March 27, 1897. Plaintiffs regarded the cessation of work for thirty days “as a completion of the building,” and thereupon filed their several claims of lien, for the foreclosure of which this action is prosecuted.

The answer of Mr. and Mrs. Attell affirmatively alleged the contract with Hayes, the work done under it, the payments made; that he failed and neglected to proceed further with the work; that on January 18th he was notified, in writing, to supply material and workmen sufficient to complete the contract within the time limited therefor, or the owner would furnish them and proceed to finish the work, and deduct the reasonable cost thereof from the contract price; that he failed and refused to proceed further with the performance of his said contract, and that all labor ceased on said building and under said contract until the 27th of March, 1897, when, a contract was made with D. R. Perry to furnish the necessary material and labor to complete the building according to the plans, specifications, and drawings set forth in the contract made with Hayes; that Mrs. Attell paid Perry for such completion of the building, $1,500, which was the reasonable value thereof; that she had paid Hayes the first and second installments under his contract, amounting to $830; that the value of the labor and materials done and furnished by Hayes, including materials then actually delivered, estimated by the standard of the whole contract price, was the sum of $1,150, and that no more than $120, if any sum at all, is applicable to the payment of the lien claimants,—and offered to deposit said sum in court for distribution by the court to them.

Upon the trial, defendants called as a witness Thomas A. Peters, who testified that he was a contractor and builder; that he knew the building in question, and examined it after Hayes ceased work; that he also examined the contract, and *493 was familiar with its terms and conditions, and the plans and specifications. No question was made as to his competency. He was then asked the following question:—

“ Taking the building in the condition it was left by Hayes when all work thereon by or under him ceased, and including all materials then delivered or on the ground, at what figure did you estimate the cost of completing said building according to the plans and specifications set forth in said contract with Hayes ? ”
“Mr. Jordan.—I object to the question, that it is immaterial and irrelevant, unless it appears that there was no cessation of work on said building for a period of thirty days after Hayes had ceased work thereon.”

The objection was overruled provisionally, and the witness answered: “Fifteen hundred dollars. Hayes had not completed half of the building when he ceased work.” And in reply to another question, to which the same objection and same ruling were made, he answered that fifteen hundred dollars was the reasonable cost. Mr. Jordan then moved to strike out both answers, “ on the ground that it did not appear that there was not a cessation of work on said building for a period of thirty days after January 27,1897.” This motion was granted, and defendants excepted.

Other witnesses were called by defendants, and apt questions put to ascertain the value of the work and materials done and furnished by Hayes, including material upon the ground not used, estimated by the standard of the whole contract price of two thousand two hundred dollars, and what would be the reasonable cost of completing the building according to the plans and specifications of the Hayes contract; to all of which the objection was made, “that it is immaterial and irrelevant what the value of such work and materials is, unless work on said building did not cease for a period of thirty days after January 27, 1897”; and these objections were all sustained by the court, and defendants excepted to each ruling.

The same question is also made and clearly presented by an amendment made to the complaint, by striking out the allegation that the contractor “abandoned” the work on January 27,1897; that the value of all the work done and materials furnished and used or on hand at the time of the abandonment was about $1,800; that the first and second *494 payments, amounting to $830, had been paid, leaving due and unpaid from defendants to Hayes, at the date of abandonment, $970, — and inserting in lieu thereof the following: “That all work ceased upon said building, as plaintiffs are informed and believe, upon the twenty-seventh day of January, 1897, and that no labor was done upon said building whatsoever subsequent to said' twenty-seventh day of January, 1897, for a period of more than thirty days, and until after the twenty-sixth day of February, 1897.”

The objections to the testimony offered by defendants, and the above amendment to the plaintiff’s complaint, are based upon the last clause of section 1187 of the Code of Civil Procedure, which is as follows: “Cessation from labor for thirty days upon any contract, or upon any building, improvement, or structure, or the alteration, addition to, or repair thereof, shall be deemed equivalent to a completion thereof for all the purposes of this chapter.”

It is not alleged nor in any manner contended that the contractor ceased work or abandoned the contract because of any fault of appellants, or of any violation of the contract by them, and therefore there was not, at the date of his cessation from the work,.or at any time afterward, any indebtedness or liability on the part of appellants to the contractor; but it is contended, that because appellants did not resume work within thirty days after the contractor ceased, they are liable to respondents, who furnished materials to the contractor, to the full amount of the contract price remaining unpaid, notwithstanding appellants were compelled to finish the work at an expense which, added to the payments made to the original contractor in accordance with the contract, exceeded the contract price. This contention cannot he sustained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Santa Cruz Portland Cement Co. v. Snow Mountain Water & Power Co.
274 P. 617 (California Court of Appeal, 1929)
Pacific Manufacturing Co. v. Perry
181 P. 820 (California Court of Appeal, 1919)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
Olson-Mahoney Lumber Co. v. Maxwell
124 P. 100 (California Court of Appeal, 1912)
Quartaroli v. City of Sonoma
123 P. 533 (California Court of Appeal, 1912)
Clark v. Beyrle
116 P. 739 (California Supreme Court, 1911)
Steiger Terra Cotta & Pottery Works v. City of Sonoma
100 P. 714 (California Court of Appeal, 1909)
Hoffman-Marks Co. v. Spires
97 P. 152 (California Supreme Court, 1908)
People v. Crane
87 P. 239 (California Court of Appeal, 1906)
Hampton v. Christensen
84 P. 200 (California Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
64 P. 850, 132 Cal. 490, 1901 Cal. LEXIS 1094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonald-v-hayes-cal-1901.