Pacific Manufacturing Co. v. Perry

181 P. 820, 40 Cal. App. 708, 1919 Cal. App. LEXIS 113
CourtCalifornia Court of Appeal
DecidedApril 18, 1919
DocketCiv. No. 2750.
StatusPublished

This text of 181 P. 820 (Pacific Manufacturing Co. v. Perry) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Manufacturing Co. v. Perry, 181 P. 820, 40 Cal. App. 708, 1919 Cal. App. LEXIS 113 (Cal. Ct. App. 1919).

Opinion

HAVEN, J.

This is the second appeal in consolidated actions to foreclose contractors’ and materialmen’s liens, the opinion on the first appeal being reported in 31 Cal. App. 274, [160 Pac. 246]. On June 10, 1910, the defendant R. A. Perry, acting on behalf of the defendant Winifred A. Perry, his wife, entered into a valid contract with defendant Magneson for the construction of a. residence and garage for the total contract price of $23,567, which contract was re *710 corded on June 13, 1910. The contractor commenced construction of the building thereunder and continued until February 11,1911, at which latter date he abandoned work under the contract. On March 22, 1911, the defendants R A. and Winifred A. Perry filed for record a notice of abandonment by the contractor of said contract. The details of the contract, so far as they may be material, are set forth in the opinion on the former, appeal and need not here be repeated. The present appeal is by the defendants from a decree adjudging plaintiffs entitled to .liens as set forth in their several complaints and decreeing the .foreclosure thereof. All the claims of lien here involved are. based upon work performed or materials furnished prior to the abandonment of the contract. The controversy is concerned mainly with the proper portion of the contract price applicable to the payment of such liens under section 1200 of the Code of Civil, Procedure, prior to its repeal in 1911; and particularly as to the correct method of computation to be adopted in arriving at that amount. The court found: “That the value of the work and materials already done and furnished at the time of the abandonment of said work and contract by the said defendant Magneson, as aforesaid, to wit, on the eleventh day of February, 1911, including materials then actually delivered and on the ground, estimated as near as may be by the standard of the whole contract price, exclusive of the extra work hereinafter mentioned and referred to, was and is the aggregate sum of $17,468.71, being 74.2 per cent of the amount of the contract price, to wit, $23,567, qn account of which there had been paid the contractor, the defendant Magneson, at the time of abandonment, the sum of ten thousand dollars.” The court also found that during the course of construction of the buildings, and prior to the abandonment of the contract, certain extra work was performed by the contractor, subcontractors, and materialmen, under authorization in writing from the defendants Perry and. in conformance with the provisions of the contract, the reasonable value of ’ which aggregated $4,016.36, on account of which there had been paid to the contractor the sum of $1,300, leaving a balance unpaid for said extras in the sum of $2,716.36.

[1] Appellants attack the finding above quoted as not being a sufficient finding of fact under the terms of section *711 1200 of the Code of Civil Procedure. It is couched, however, in the language of that section, and is sufficient Under the authority of Marshall v. Vallejo Commercial Bank, 163 Cal. 469, 474, [126 Pac. 146]. The ultimate fact is found as required by the section referred to. The real contention of appellants is that this finding is not supported by the evidence, for the reason that it does not appear that the cost of completion of the building was an element taken into consideration in arriving at the amount found to be applicable to the payment of liens at the time of abandonment. Appellants argue that the cost of completion after abandonment was much greater than it would have been if there had been no abandonment, and as the owners were obliged to pay this extra cost through no fault on their part, it should have been taken into consideration in arriving at the amount applicable to claims of lien which accrued prior to abandonment.

[2] It is admitted by appellants that this contention is contrary to the rule laid down in Ganahl Lumber Co. v. Weinsveig, 168 Cal. 664, 669, [124 Pac. 1025]. But it is claimed that the rule announced in the case last referred to is contrary to all the previous decisions of the supreme court, and to the law of these cases as announced upon the former appeal. Particular reliance is placed by appellants upon the cases of Roystone Co. v. Darling, 171 Cal. 526, 533, [154 Pac. 15], McDonald, v. Hayes, 132 Cal. 490, [64 Pac. 850] , Hoffman-Marks Co. v. Spires, 154 Cal. 111, 116, [97 Pac. 152], and Marshall v. Vallejo Commercial Bank, 163 Cal. 469, [126 Pac. 146], as announcing a rule which is inconsistent with that declared in the Ganahl case, as construed and applied on the former appeal, and by the trial court .in the instant eases. Upon a careful reading of the decisions referred to, we do not find the inconsistency claimed by appellants. In our opinion, the confusion of appellants arises from a failure fully to appreciate the fact, so clearly pointed out in the Ganahl case, that upon abandonment the performance of the contract has come to an end, and the rights of all parties thereunder must be adjusted as of that date. It is true that a contract legally made limits the liability of the owner to lien claimants to the amount of the contract price; but the liability thus referred to is to lien claimants whose claims have arisen under the contract. Section 1200 of the Code of Civil *712 Procedure, as it existed prior to its repeal, recognized that a building contract might be terminated by abandonment, and provided a method of arriving at the proportion of the contract price applicable to liens in that event. As stated in the Ganahl case, if the contract is half performed, it is equitable, and a protection of the constitutional rights of all parties, to decree that one-half of the price agreed to be paid for the performance of the entire contract,- less payments made, should be applied to the discharge of liens which had accrued prior to the abandonment. This is undoubtedly the rule established by the decision last above referred to, and even if it could be construed as inconsistent with former decisions, as claimed by appellants, we should consider ourselves bound thereby. We are of the opinion, however, that all the eases referred to are entirely harmonious.

[3] The testimony was conflicting as to the value of the work done and materials furnished at the time of abandonment, and as to the reasonable value of all the labor and materials necessary to construct and complete the buildings according to the contract, plans, and specifications. The findings of the court are sufficiently supported, however, by the evidence of experts offered on behalf of the plaintiffs. These witnesses testified that the reasonable value, at the time the buildings were constructed, of all the labor and materials necessary and required to construct and complete the buildings according to the contract, plans, and specifications was the aggregate sum of $26,255.08; and that the aggregate value of the labor and materials actually used in the construction of the buildings and upon the ground at the time of the abandonment was $19,454.34. They then computed that the latter sum was 74.2 per cent of the former, and, therefore, testified that the contract had been 74.2 per cent completed at the time of the abandonment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Manufacturing Co. v. Perry
160 P. 246 (California Court of Appeal, 1916)
Hoffman-Marks Co. v. Spires
97 P. 152 (California Supreme Court, 1908)
McDonald v. Hayes
64 P. 850 (California Supreme Court, 1901)
G. Ganahl Lumber Co. v. Weinsveig
143 P. 1025 (California Supreme Court, 1914)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
Marshall v. Vallejo Commercial Bank
126 P. 146 (California Supreme Court, 1912)
Goss v. Strelitz
54 Cal. 640 (California Supreme Court, 1880)

Cite This Page — Counsel Stack

Bluebook (online)
181 P. 820, 40 Cal. App. 708, 1919 Cal. App. LEXIS 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-manufacturing-co-v-perry-calctapp-1919.