Marshall v. Vallejo Commercial Bank

126 P. 146, 163 Cal. 469, 1912 Cal. LEXIS 431
California Supreme Court·Decided August 7, 1912·No. Sac. No. 1941.·Published·Cited by 8 cases

Opinion

SLOSS, J.

The plaintiff in his own right, and as assignee of the Coast Electric Company and of J. W. Mitchell, brought this action to foreclose three mechanics’ liens upon the property of defendant Vallejo Commercial Bank in the city of Vallejo.

*471 On the nineteenth day of August, 1907, the Vallejo Commerr cial Bank, as owner, entered into a written contract with Newton-Sandford Construction Company, as contractor, for the making of certain alterations and additions to a brick building owned by the bank. The contract price was $13,800. The validity of the contract, although questioned by the complaint, was declared by the findings, and is not now disputed.

The plaintiff and his assignors were subcontractors of the Newton-Sandford Company, and filed claims of lien ftir the following amounts: the plaintiff, $2,950; J. N. Mitchell, $393.77, and Coast Electric Company, $223.50. The propriety of these demands, as against the contractor, and the regularity of the steps to claim liens therefor, are not questioned. The only controversy is over the amount due from the owner, Vallejo Commercial Bank, and applicable to the satisfaction of these liens.

It appears that the contractor commenced performance of the contract, and continued until on or about January 28, 1908, when it ceased work. Notice of cessation of labor was duly filed by the owner, which proceeded to complete the work itself. The rule for ascertaining the amount available for liens of persons other than the contractor was, under this state of facts, to be fixed according to the provisions of section 1200 of the Code of Civil Procedure, which, though repealed in 1911 (Stats. 1911, p. 1319), was still in force at the time of the accrual of the rights asserted in this action.

The court found that at the time of the cessation of labor upon the building by the contractor, the value of the work done and materials furnished by the said contractor was the sum of $10,767.34, “estimated according to the standard of the said contract price,” and that at said time there had been paid by the Vallejo Commercial Bank on account of said contract the sum of $8,800.51. Of said amount $892.86 was paid before the dates fixed by the contract for payment and $67.03 of this was paid in excess of progress payments, but all of said $892.86 was paid to subcontractors, materialmen, and laborers having contracts with the Newton-Sandford Construction Company, “and for that reason should now be allowed as a credit to defendant the Vallejo Commercial Bank.” Deducting the sum of $8,800.51 from the sum of $10,767.34, the amount fixed as the value of the materials and labor furnished, *472 estimated according to the contract price, the court found the balance of $1,966.83 to be the amount owing from the bank. From this it deducted $560, the damage found to have been sustained by the bank through the failure of the contractor to complete the building within the agreed time. This left the sum of $1406.83 which the court, in its conclusions of law, found to be due from the bank, and applicable to the discharge of plaintiff’s liens. A decree of foreclosure was entered accordingly. Thereafter, upon motion of the plaintiff, the court amended its conclusions of law and entered a new judgment. The second judgment was based upon the view that, in ascertaining the amount due from the bank, the premature payments of $892.86, and the damages claimed for delay, amounting to $560, should not have been deducted from the value of the materials furnished and labor done at the time when work on the building ceased. The result was to make the balance due from the appellant and applicable to the payment of liens $2,859.69, and the conclusions of law and the decree so declare.

The bank moved for a new trial, which was denied. It appeals from the order denying its said motion, and from the parts of the decree adjudging that the sum of $2,859.69, with interest and costs, is a lien upon its property, and ordering a sale to realize such sum.

The first point urged by the appellant is that the evidence is insufficient to sustain the finding that at the time of the cessation of labor the value of the work done and materials furnished “was the sum of $10,767.34, estimated according to the standard of the said contract price.” This contention must be upheld. There is virtually no dispute in the evidence regarding the items which must be taken into account in computing the amount in question. The contract price was $13,800. The actual value of the labor done and materials furnished up to the time of cessation of labor was $10,767.34. The amount reasonably and necessarily expended in completing the building was $3,703.06. This made the total cost of the completed building $14,470.40. To this must be added the reasonable cost that would have been incurred in completing, according to the contract, two items of construction, one of which was altered by the substitution of a cheaper material and the other omitted from the building. Accordingly, the *473 value of the work done and materials furnished, “estimated as near as may be by the standard of the whole contract price,” as provided by section 1200, was to be fixed by taking such proportion of the actual value of the work and materials done and furnished at the time of abandonment as the total contract price bore to the actual total reasonable cost of the complete improvement, the last mentioned figure being reached by “adding to the actual value of the work done and materials furnished at the time of the abandonment the reasonable cost of completing the building.” (Hoffman-Marks Co. v. Spires, 154 Cal. 111, [97 Pac. 152].) Such computation would have resulted in the ascertainment of an amount considerably less than $10,767.34, which was the sum found by the court. This sum was the actual value of the labor and materials, and not the value estimated according to the standard of the contract price.

The alteration above referred to consisted in the substitution of metal for Spanish tile, reducing the actual cost by $225. A heating plant, called for by the contract, was not installed. The appellant claims that the reasonable value of installing this item would have been $375, but the respondent contends, and we think correctly, that there is no sufficient evidence to show this. But whether the cost of the heater be taken into account or not, the finding under discussion cannot stand. If we accept appellant’s view on this point, a calculation, under the rule above stated, shows the value of labor done and materials furnished, estimated according to the standard of the contract price, to be $9,859.45, or $907.89 less than the amount found by the court. Omitting any consideration of the heater, the value of the labor and materials, thus estimated, would be $10,110.53, or $656.81 less than the amount found. The error cannot be rectified by modifying the judgment, as suggested in respondent’s brief, for the reduction thus proposed is only $499.61, which is not sufficient to meet the requirements of the case. Upon a new trial there can be little difficulty in ascertaining the correct figure, and the court may then have before it sufficient data from which to determine and to take into account, the reasonable cost which would have been incurred in installing the heating plant according to the plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Marshall v. Vallejo Commercial Bank, 126 P. 146, 163 Cal. 469, 1912 Cal. LEXIS 431 (Cal. 1912).

126 P. 146 (Marshall v. Vallejo Commercial Bank) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Palmer v. Brown
273 P.2d 306 (California Court of Appeal, 1954)
Passaic-Bergen Lumber Co. v. Peterson
147 A. 198 (Supreme Court of New Jersey, 1929)
Pacific Manufacturing Co. v. Perry
181 P. 820 (California Court of Appeal, 1919)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
Hubbell, Hall & Randall Co. v. Pentecost
93 A. 672 (Supreme Court of Connecticut, 1915)
G. Ganahl Lumber Co. v. Weinsveig
143 P. 1025 (California Supreme Court, 1914)
Growall v. Pacific Surety Co.
131 P. 73 (California Court of Appeal, 1913)