Hoffman-Marks Co. v. Spires

97 P. 152, 154 Cal. 111, 1908 Cal. LEXIS 308
CourtCalifornia Supreme Court
DecidedAugust 8, 1908
DocketL.A. No. 1990.
StatusPublished
Cited by15 cases

This text of 97 P. 152 (Hoffman-Marks Co. v. Spires) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoffman-Marks Co. v. Spires, 97 P. 152, 154 Cal. 111, 1908 Cal. LEXIS 308 (Cal. 1908).

Opinion

SLOSS, J.

Three of the four actions involved in these appeals were commenced to foreclose mechanics’ liens upon a lot and building in the city of Los Angeles. Mary H. Spires, the owner of the property, answered the complaints in said actions, and commenced, as plaintiff, a separate action against all of the lien claimants and the original contractors. In this action she prayed for a decree adjudging that none of the claimants was entitled to any lien against her property, and that there was no fund in her hands for the payment of the laborers or materialmen. The four actions were consolidated and tried together.

*113 The findings, so far as it is necessary to state them, were as follows: On September 6, 1904, L. MeKown, IT. M. Baird, H. Stone, and H. J. Hoover, copartners under the firm name of L. MeKown & Co., entered into a contract with Mary H. Spires to build for her a house on the lot in question for the sum of $8183. The contract was in writing and was, before the work was commenced thereunder, filed in the office of the county recorder. With said contract and as part thereof there were filed plans and, specifications, referred to in the contract and signed by the parties. The contract price was, by the terms of the contract, made payable as follows: First payment, the sum of $1227.45, when the second floor joists are in place. Second payment, the sum of $1227.45, when the roof is ready for metal covering and chimney built. Third payment, the sum of $1227.45, when the building is inclosed, brown coated and rough plumbed. Fourth payment, the sum of $1227.45, when the last coat of mortar is on, and sash and glass and cement steps are in place. Fifth payment, the sum of $1227.45, when building is accepted by architect and owner. Sixth payment, the sum of $2045.75, when thirty-five days have expired after acceptance by architect and owner, etc. MeKown & Co. commenced to build said house and progressed to the point when said building was inclosed, brown coated, and rough plumbed. The first, second, and third payments provided for in the contract, amounting in all to $3632.35, were made by Mrs. Spires to MeKown & Co. Thereafter MeKown & Co., having failed to proceed under their contract with proper dispatch, received from Mrs. Spires, on December 21, 1904, notice that unless they- so proceeded she would within three days proceed to complete the work, as she was by the contract authorized to do. They (MeKown & Co.) failed to proceed, and abandoned the contract, whereupon Mrs. Spires proceeded with the work and completed the building according to the provisions of the contract. At the time of the abandonment by MeKown & Co. the value of the work and materials already done and furnished, including materials then actually delivered on the ground, estimated by the standard of the whole contract price, was $3105. The fair and reasonable expense and cost of completion Pf the house was $7581.79, and Mary H. Spires paid that sum in completing the work. It was also found that certain sums, which it is not *114 necessary to specify, were due to respective lien claimants (appellants here) by McKown & Co. for materials and labor furnished to be used and used in said building.

From these facts the court drew the conclusions of law that the lien claimants were not entitled to liens upon the premises nor to any judgments against Mary H. Spires, but that they were entitled to judgments against the copartners constituting the firm of L. McKown & Co. for the sums found to be due to them respectively. Mary H. Spires was declared to be entitled to a judgment that the various claimants be decreed to have no lien or liens against her premises. A judgment followed in accordance with these conclusions.

Some of the lien claimants moved for a new trial and, their motion having been denied, they now appeal from the judgment and from the order denying their motion for a new trial.

On the facts as declared in the findings the court properly concluded that the claimants were not entitled to liens or to judgments against Mary H. Spires. It is found that a valid contract in writing had been executed and filed; that work under this contract had been abandoned by the contractor before completion and that the payments made by the owner pursuant to the contract amounted, at the time of the abandonment, to more than the value of the work and materials then done and furnished, estimated by the standard of the whole contract price. Under the rule declared in section 1200 of the Code of Civil Procedure there was therefore no part of the contract price applicable to the payments of liens. That section reads as follows: “In case the contractor shall fail to perform his contract in full, or shall abandon the same before completion, the portion of the contract price applicable to the liens of other persons than the contractor, shall be fixed as follows: From the value of the work and materials already done and furnished at the time of such failure or abandonment, including materials then actually delivered or on the ground, which shall thereupon belong to the owner, estimated as near as may be by the standard of the whole contract price, shall be deducted the payments then due and actually paid, according to the terms "of the contract and the provisions of sections 1183 and 1184, and the remainder shall be deemed the portion of the contract price applicable to such liens.”

*115 In McDonald v. Hayes, 132 Cal. 490, 495, [64 Pac. 850], this court said: “Where there is a valid contract between the owner and contractor, it is the measure of the owner’s liability. (Greig v. Riordan, 99 Cal. 319, [33 Pac. 913]; Kellogg v. Howes, 81 Cal. 175, 177, [22 Pac. 509]; Walsh v. McMenomy, 74 Cal. 359, [16 Pac. 17] and cases cited.) But in cases where, as here, the contractor fails to perform his contract, section 1200 of the Code of Civil Procedure provides the mode of determining the owner’s liability . . ,” If, upon making the computation directed by section 1200, no balance remains, there is nothing available for lien claimants, and they must look to their personal claims against the contractor.

It is argued by appellants that the final payment of at least twenty-five per cent which, under section 1184 of the Code of Civil Procedure, must be made payable not less than thirty-five days after the final completion of the contract, constitutes in all cases a fund specially set apart for the satisfaction of liens, and that this fund cannot be impaired in any way. Accordingly, it is contended that the amount of $2045.75, the sixth and last payment provided for in the contract here involved, must be applied to the satisfaction of appellants’ liens, notwithstanding the fact that the contractor abandoned his contract, and the owner in completing it was compelled to expend a sum which, added to the payments already made, exceeded the whole contract price. We think the statute affords no foundation for this contention. It may, no doubt, be said in general terms that the Mechanics’ Lien Law has set apart the thirty-five-day payment as a fund for lien claimants, and that this fund must remain intact for them, unaffected by any offsets or claims on the part of the owner. (Hampton v. Christensen, 148 Cal. 729, [84 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Santa Cruz Portland Cement Co. v. Snow Mountain Water & Power Co.
274 P. 617 (California Court of Appeal, 1929)
Pacific Portland Cement Co. v. Hopkins
162 P. 1016 (California Supreme Court, 1917)
Pacific Manufacturing Co. v. Perry
160 P. 246 (California Court of Appeal, 1916)
Olson-Mahoney Lumber Co. v. Dunne Investment Co.
159 P. 178 (California Court of Appeal, 1916)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
G. Ganahl Lumber Co. v. Weinsveig
143 P. 1025 (California Supreme Court, 1914)
Growall v. Pacific Surety Co.
131 P. 73 (California Court of Appeal, 1913)
Marshall v. Vallejo Commercial Bank
126 P. 146 (California Supreme Court, 1912)
Olson-Mahoney Lumber Co. v. Maxwell
124 P. 100 (California Court of Appeal, 1912)
Quartaroli v. City of Sonoma
123 P. 533 (California Court of Appeal, 1912)
Butler v. Ng Chung
117 P. 512 (California Supreme Court, 1911)
Duffy Lumber Co. v. Stanton
98 P. 38 (California Court of Appeal, 1908)
H. Raphael Co. v. Grote
97 P. 155 (California Supreme Court, 1908)
Scheerer Co. Inc. v. Deming
97 P. 155 (California Supreme Court, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
97 P. 152, 154 Cal. 111, 1908 Cal. LEXIS 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoffman-marks-co-v-spires-cal-1908.