Quartaroli v. City of Sonoma

123 P. 533, 18 Cal. App. 400, 1912 Cal. App. LEXIS 313
CourtCalifornia Court of Appeal
DecidedFebruary 29, 1912
DocketCiv. No. 889.
StatusPublished

This text of 123 P. 533 (Quartaroli v. City of Sonoma) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quartaroli v. City of Sonoma, 123 P. 533, 18 Cal. App. 400, 1912 Cal. App. LEXIS 313 (Cal. Ct. App. 1912).

Opinion

*401 CHIPMAN, P. J.

Plaintiffs bring the action to recover the possession of certain personal property or the value thereof, in case delivery cannot be had, alleged to be $3,590.85. They claim ownership by virtue of a bill of sale from one John T. MacQuiddy, of date September 13,1906. MacQuiddy had entered into a written contract with defendant, the city of Sonoma, to construct a municipal building for that city, agreeing to furnish all materials and labor therefor at the agreed price of $15,475. This contract was duly authorized and legally entered into and was duly recorded. No question arises as to full compliance with the provisions of the statute relating to the making and recording of such contracts. At the same time MacQuiddy executed a bond with said city, “in the sum of $4,000”; on which plaintiffs, including defendant Heggie’s intestate, were sureties, which recited the making of said contract and was, conditional upon its faithful performance by MacQuiddy, and that he “shall make full payment to all persons supplying him labor or materials in the prosecution of the work provided for in said contract. ’ ’ This bond was also recorded at the same time and with the contract. MacQuiddy entered upon the work and prosecuted it up to September 8,1906, on which day, as found by the court, “work ceased upon said building or the construction thereof and was wholly abandoned, and the said John T. MacQuiddy ceased to do any work upon said building from the eighth day of September, 1906, and said cessation from work and the finishing of said construction and the abandonment of said work and said contract by said MacQuiddy on said unfinished building continued for more than forty days after said cessation of work by said contractor MacQuiddy, and that at the time of the abandonment of said contract by said contractor MacQuiddy the articles of personal property and the materials mentioned in the answer of said city of Sonoma, which were materials necessary for the construction of said building, were then actually delivered and on the ground where said building was to be constructed, and that the same and all thereof were necessary materials for the construction of said building, and were actually delivered and on the ground where the same were to be used in the construction of said building, and that all of the aforesaid personal property was used and placed in the said building by defendant Newman at the instance of the *402 said city of Sonoma long prior to the commencement of this action.”

It appeared, and was so found by the court, that after MacQuiddy ceased work the city called upon him to resume work, which he neglected and refused to do, and on September 13, 1906, he made the bill of sale to plaintiffs, on which they rely. The court found further as follows: “That said John T. MacQuiddy entirely failed to complete said contract or to perform the conditions and covenants and agreements therein set forth, and that by reason of said default and.failure to carry out said contract, said defendant city of Sonoma was compelled to and did, after proceedings had to that end, let to the highest bidder, to wit, to defendant, James B. Newman, and entered into a written contract with him for the completion of said building in all respects as it was to be completed under the original contract to' and with the said MacQuiddy and the said James B. Newman and the said city of Sonoma entered into a contract for the completion of said building in and at the price of $14,200 . . . ; and that prior to the entering into said contract with said Newman and subsequent to the failure and abandonment of the said MacQúiddy to perform his said contract, the said materials and articles of personal property, being then and there actually delivered and' were upon the ground where said building was to be.constructed, the said city of Sonoma caused to be estimated, inventoried and listed, the said articles of personal property as nearly as possible by the standard of the whole contract price entered into by the said MacQuiddy with said city, and that the said materials and all thereof were delivered to the said James B. Newman by the said city of Sonoma for the completion and construction of said building and the carrying out of the said contract with the said Newman, and that said James B. Newman was furnished the said materials set forth in the' separate answer of the said city of Sonoma by the said city, and that 'the same were placed in and used by him in the' construction and completion of sáid municipal building.” The court also found: “That the sáid city of Sonoma'has paid out and expended the sum of $15,200 in cash for the carrying out'the completion of the building' entered into by the said MacQuiddy and abandoned by him,, and for the carrying out. and completion of the contract as entered into'by the *403 said defendant James B. Newman for the completion of the building, which was completed in all respects in accordance with the original contract, and that all of the materials and articles of personal property in controversy herein and herein sued for was actually used and necessarily used in the completion of the said municipal building, and that its value is hereby fixed at the sum of $3,590.85, and that if the city of Sonoma is or should be compelled to pay therefor the said sum of $3,590.85 to the plaintiffs, then and in that case the said city of Sonoma would lose and be damaged in the sum of the value thereof, to wit, $3,590.85, and that no part of the said sum has been paid to the said city of Sonoma, and that the bondsmen who executed the bond herein referred to and who are the plaintiffs in this action (with the exception of the said C. Aguillon, whose administrator is a plaintiff herein), would be liable to the said city for the said sum. That the-said bond is a valid and legal bond, and indemnified, to the extent of $4,000, the said city of Sonoma from all damages which the defendant city of Sonoma should sustain by reason of the failure or abandonment of the said MacQuiddy to perform his said contract. That there is in the treasury in the city of Sonoma thé sum of $275 properly applicable to the-payment of the plaintiffs’ claim for damages or from any cause arising out of the use of the said property by the said city and the said materials and articles of personal property which were used in the construction and completion of said-building, and that there is no other money or funds applicable to the payment of the claim or demand of the plaintiffs herein sued upon, and that there will not be in the treasury of the said city any greater or other amount than the said sum of $275 in the general fund of the said city properly- applicable to the payment of the said claim. That the- plaintiffs are bound by their bond for any loss occasioned to the city of Sonoma by reason of the said abandonment of the said contract and the said contract entered into by the said city wdth the said MacQuiddy. to--the extent of $4,000, and that the building was only completed at and for the sum of $15,200 after using all of the said materials and personal property involved in this action in. the construction and completion" .of said building, and that the plaintiffs are estopped from re *404 covering any other or further amount than the said sum of $275.”

It appears that defendant Newman’s contract gave him the right to use the materials in question “free of.cost to him and to be used in the construction of said building.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCue v. Jackman
95 P. 673 (California Court of Appeal, 1908)
Duffy Lumber Co. v. Stanton
98 P. 38 (California Court of Appeal, 1908)
Steiger Terra Cotta & Pottery Works v. City of Sonoma
100 P. 714 (California Court of Appeal, 1909)
Hoffman-Marks Co. v. Spires
97 P. 152 (California Supreme Court, 1908)
W. W. Montague & Co. v. Furness
78 P. 640 (California Supreme Court, 1904)
McDonald v. Hayes
64 P. 850 (California Supreme Court, 1901)
Shaughnessy v. American Surety Co.
69 P. 250 (California Supreme Court, 1903)
Union Sheet Metal Works v. Dodge
62 P. 41 (California Supreme Court, 1900)
People v. Matuszewski
71 P. 701 (California Supreme Court, 1903)
Mayrhofer v. Board of Education of San Diego
26 P. 646 (California Supreme Court, 1891)
White v. Miller
18 Pa. 52 (Supreme Court of Pennsylvania, 1851)
Union Pacific Railway Co. v. Hammerlund
79 P. 152 (Supreme Court of Kansas, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
123 P. 533, 18 Cal. App. 400, 1912 Cal. App. LEXIS 313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quartaroli-v-city-of-sonoma-calctapp-1912.