Steiger Terra Cotta & Pottery Works v. City of Sonoma

100 P. 714, 9 Cal. App. 698, 1909 Cal. App. LEXIS 350
CourtCalifornia Court of Appeal
DecidedJanuary 27, 1909
DocketCiv. No. 509.
StatusPublished
Cited by5 cases

This text of 100 P. 714 (Steiger Terra Cotta & Pottery Works v. City of Sonoma) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steiger Terra Cotta & Pottery Works v. City of Sonoma, 100 P. 714, 9 Cal. App. 698, 1909 Cal. App. LEXIS 350 (Cal. Ct. App. 1909).

Opinion

CHIPMAN, P. J.

This is an action for the recovery of the possession of specific personal property or, if delivery cannot be had, for the value thereof.

■ The facts are not disputed so far as they concern the main question involved.

One MacQuiddy entered into a written contract with defendant, city of Sonoma, to erect a city hall. This contract was duly recorded and its validity is not questioned. MacQuiddy entered into a written contract with plaintiff whereby plaintiff agreed to “furnish and set on the roof of the New City Hall, ... as per plans and specifications by architect, A. C. Lutgens, all of the Spanish ‘S’ Tile and finishings required, said material and work to be satisfactory to said architect.” Plaintiff also agreed to “complete said work” within a time stated “after receipt of full sized detail drawings of said roof,” and guaranteed “said roof against leakage caused by defects of workmanship or material for period of two years from and after completion of roof, ...” and to “furnish said material and perform said work for the sum of $875.00.” It was also agreed that said MacQuiddy will pay said sum “upon completion of the work on the roof of said building in accordance with the terms of” their contract, “$650.00 and the balance $225.00 in thirty-five days after said completion. ’ ’ The material was manufactured by plaintiff and remained in its possession until it was shipped t'o MacQuiddy under the contract and all expenses of shipping and delivering the ma *700 terial to the plaza at Sonoma, the site of the proposed building, where it was stored to await use, were paid by plaintiff and the material was charged on plaintiff’s books to MacQuiddy. It appeared also that nothing had been paid for the material by MacQuiddy or by any person for or on his behalf. Before the completion of the building MacQuiddy defaulted' and abandoned the work, and defendant, the city of Sonoma, entered into a contract with defendant Newman to complete the building, took possession of the material in question, and caused its value to be appraised, proceeding under section 1200 of the Code of Civil Procedure, on the assumption that the material had become the property of defendant, city of Sonoma. Plaintiff demanded possession of the property, and, being refused, commenced this action, at which time no part of the material had been used in the construction of the building. Defendant, city of Sonoma, gave the statutory bond and the property was thereupon redelivered to said defendant. The cause was tried by the court without a jury and defendants had judgment, from which plaintiff appeals upon bill of exceptions.

Appellant relies upon the proposition that the contract between it and MacQuiddy is a contract for work and materials under which no title in the materials passed to MacQuiddy, and that this unmistakably appears from the terms of the contract itself. We think this is a sound interpretation of the instrument. Mr. Benjamin states the rule as follows: “Where a contract is made for furnishing a-machine or a movable thing of any kind and fixing it to the freehold, it is not a contract for the sale of goods. In such contract the intention is plainly not to make a sale of movables, but to make improvements on the real property, and the consideration to be paid to the workman is not for a transfer of chattels, but for work and labor done and materials furnished in adding something to the land.” (Benjamin on Sales, 7th ed., sec. 108.) The English rule on the subject is clearly stated in Tripp v. Armitage, 4 Mees. & W. 687. In this case the contract was to make certain sash frames and attach them to a building. Baron Parke said: "The contract is, that the bankrupt shall build a house; that he shall make, among other things, window-frames for the house, and fix them in the house, subject to the approbation of a surveyor; and it was never intended by this contract, that the articles so to be fixed should become the property of the defendants, until they were fixed to the freehold. It is said *701 that the approbation of the surveyor is sufficient to constitute an acceptance by the defendants; but that approbation is not given eo animo at all; it is only to ascertain that they are such materials as are suitable for the purpose; and notwithstanding that approval, it is only when they have been put up, and fixed to the house, in performance of the larger contract, that they are to be paid for.” Lord Chief Baron Abinger, in giving his opinion, said: “This is not a contract for the sale of goods as movable chattels; it is a contract to make up materials and to fix them; and until they are fixed, by the nature of the contract, the property will not pass.” It was suggested as illustrative of the principle, that had the sashes been destroyed by fire the loss would have fallen on the builder, for the owner of the building was not bound to pay for anything until put up and fixed. So here, plaintiff’s undertaking was not only to furnish certain materials, but plaintiff was itself to perform the labor of placing them on the roof to become a part of t'he building and freehold; and plaintiff was not to be paid for the materials alone, but was to receive an entire sum for the combined labor and materials and that only after completion of the work. It is not possible to distinguish the two cases.

The principle was applied in Chandler v. De Graff, 22 Minn. 471. In that case the question was as to the title to certain railroad ties. Among other things, the court said: "They (the ties) were furnished not on account of any agreement for the purchase or sale of ties, but in part execution of defendant’s promise to build and complete a certain line of railroad, and of such quality, and to such an extent only, as might be necessary to fulfill that specific obligation and complete the undertaking. The risk of loss was clearly defendant’s until the road was inspected and accepted as provided in the contract. . . . No property nor title in the ties vested in the railroad company until after they had been actually placed in the track.” The same principle was applied where certain contracts were entered into to furnish materials and construct a street railroad. (Cameron v. Orleans & J. Ry. Co., 108 La. 83, [32 South. 208]; Orleans & J. Ry. Co. v. International Construction Co., 108 La. 82, [32 South. 218].)

The learned judge who tried the case held that plaintiff’s rights were limited to such as are found in section 1200, Code of Civil Procedure; that the contractor having abandoned his *702 contract and the work before the completion of the building, the portion of the contract price to which plaintiff was entitled was to be fixed by that section as follows: “Prom the value of the work and materials already done and furnished at the time of such failure or abandonment, including materials then actually delivered or on the ground, which shall thereupon belong to the owner, . . . shall be deducted the payments then due and actually paid, according to the terms of the contract and the provisions of sections 1183 and 1184, and the remainder shall be deemed the portion of the contract price applicable to such liens.” (Code Civ. Proc., sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aced v. Hobbs-Sesack Plumbing Co.
360 P.2d 897 (California Supreme Court, 1961)
Rino v. Statewide Plumbing & Heating Co.
262 P.2d 1003 (Idaho Supreme Court, 1953)
Hogan Lumber Co. v. City of Oakland
142 P. 1084 (California Court of Appeal, 1914)
Quartaroli v. City of Sonoma
123 P. 533 (California Court of Appeal, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
100 P. 714, 9 Cal. App. 698, 1909 Cal. App. LEXIS 350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steiger-terra-cotta-pottery-works-v-city-of-sonoma-calctapp-1909.