Los Angeles Pressed Brick Co. v. Higgins

97 P. 414, 8 Cal. App. 514, 1908 Cal. App. LEXIS 154
CourtCalifornia Court of Appeal
DecidedJuly 9, 1908
DocketCiv. No. 506.
StatusPublished
Cited by10 cases

This text of 97 P. 414 (Los Angeles Pressed Brick Co. v. Higgins) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Los Angeles Pressed Brick Co. v. Higgins, 97 P. 414, 8 Cal. App. 514, 1908 Cal. App. LEXIS 154 (Cal. Ct. App. 1908).

Opinion

TAGGART, J.

Consolidated action on mechanics’ liens. Appellant Higgins is the owner of a six-story brick building erected for him in the city of Los Angeles by respondents Alpeter, Hall & Alpeter as contractors, in accordance with three separate contracts in writing, to wit: (1) One to construct a four-story building for the sum of $40,500; (2) another to furnish labor and materials for walls, roof and interior bearing partitions of two additional stories, for the sum of $4,700; and (3) the third to complete the fifth and sixth stories of the building according to the plans and specifications therefor, for the sum of $9,200. As found by the court, Alpeter, Hall & Alpeter completed all work and furnished all materials required by said contracts, except as modified by agreement of the parties, which modification entitled the owner to a credit of $220 for bath tubs not furnished; and except as to painting and polishing the floors, upon which the owner ■ expended the sum of $2,354.75 for work not done by the contractors. The contractors also furnished extra labor and material to the value of $2,857. The aggregate value of all labor performed and material furnished was found by the court in the following words and figures: “That the total amount of all of said materials and labors agreed to be furnished in the construction of said building and appurtenances thereto, including the contract prices in said contract and the contract price and reasonable value of such additional labor and material, and less the credit for said bath tubs of $220, is the sum of $57,037.”

In addition to the $2,354.75 paid for painting and polishing the floors the owner, prior to the filing of the liens of plaintiffs against the property, had also paid to the contractors the sum of $38,689.01, and was entitled to a total credit on contracts and extras of $41,043.76, leaving a balance unpaid from the owner to the contractors of $15,993.24.

*517 The contractors filed a lien against the building for an alleged unpaid balance of $18,617.99, and thirteen other persons claiming to have furnished labor and material in the construction of the said building filed liens aggregating an amount in excess of that sum. The several actions brought to foreclose these liens were consolidated for the purpose of trial. The defendant-owner, Higgins, deposited in court the amount of the balance alleged by said contractors to be due to them, to wit, $18,617.99, to abide the order and judgment of the court.

The court finds that contract No. 1 was never filed for record, but that contracts 2 and 3 were regularly filed; that notice of completion of the work under the second contract was filed February 27, 1905, and under the first and third July 10, 1905. The claim of lien of the contractors is declared invalid because the amoupt due under each contract is not segregated and separately -stated, and the same finding is made as to all the lien claimants, except Howe Brothers, the Consolidated Lumber Company and Harry C. Bowers; and as to the latter it is found that his assignor, whose lien he is seeking to foreclose, is not entitled to recover because of failure to comply with his contract. The liens of Howe Brothers and the Consolidated Lumber Company are declared valid and entitled to be enforced, and an allowance of attorney’s fees made in each of said cases for foreclosure.

As conclusions of law, the court finds that Alpeter, Hall & Alpeter are entitled to judgment against Higgins for the sum of $15,993.24, with interest; and that each of the other lien claimants, except Harry C. Bowers, is entitled to a judgment against said contractors for a certain sum stated. Judgment was given in accordance with these conclusions, and it was directed by the judgment that the attorney’s fees allowed be paid out of the $18,617.99 deposited in court by the owner; and that the $15,993.24 found due from the owner to the contractors be applied, first, to the payment of the two valid liens, with costs, and the residue applied pro rata in payment of the personal judgments in favor of the other claimants against the contractors.

Appellant moved to vacate the judgment and to amend the conclusions of law because not supported by the findings of fact; and also -moved the court to permit him to withdraw the deposit made by him and to substitute an undertaking to *518 stay execution in lieu thereof, both of which motions were denied. He appeals from the judgment and the order of the court denying these motions.

His principal contentions on appeal are, that the first contract being void for failure to record it, the contractors must recover from the owner, if they recover at all, for the-reasonable value of the materials furnished and labor performed; and that there is neither allegation in the complaint nor finding by the court to support such a recovery; that the claimants who failed to establish valid liens are not entitled to have their personal judgments against the contractor paid in whole or in part out of the fund deposited in court by appellant; and that the allowance of attorney’s fees to the two valid lien claimants is void.

The clause in section 1183 of the Code of Civil Procedure providing that the failure to, file a building contract in the county recorder’s office shall render it “wholly void” is penal in its nature. It is to be construed in connection with the rest of the section in which it is found, as well as with- regard to the section of the constitution creating the mechanic’s lien, for the enforcement of which the lien law was provided. (Art. XX, sec. 15.) It is an arbitrary provision and is not to be extended to any contract not falling strictly within its letter. • (Kiessig v. Allspaugh, 99 Cal. 454, [34 Pac. 106].) No (merely technical) construction can be indulged for the purpose of visiting a penalty upon the owner, unless there has been a substantial failure to comply with the law, which (such as) if continued would defeat the remedial purposes of the statute; but if there be a reasonable doubt as to the construction of the statute, or as to whether the defendants complied with it, theyshould have the benefit of it. (Joost v. Sullivan, 111 Cal. 296, [43 Pac. 896].)

Appellant’s position that the contract is void, even as between the owner and contractors, is sustained by some of the earlier cases in this state, but in the later cases it has been demonstrated that such a construction of the lien law is not essential to the purpose of the constitutional provisions creating the right of lien. (Laidlaw v. Marye, 133 Cal. 176, [65 Pac. 391].) Certain provisions of the statute, formerly considered as effective, have been declared to interfere with the constitutional rights of an owner of property to make con *519 tracts relating to its use and enjoyment (Stimson Mill Co. v. Braun, 136 Cal. 122, [89 Am. St. Rep. 116, 68 Pac. 481] ; Snell v. Bradbury, 139 Cal. 379, [73 Pac. 150]), while others have been said' to be not necessary to carry out the constitutional requirements as to liens for labor bestowed upon and material furnished to construct or improve property, and have been held to exceed the legislative power. {Hughes Bros. v. Hoover,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re of Lightner
184 F. Supp. 825 (S.D. California, 1960)
Navarro v. Lippold
195 P.2d 543 (California Court of Appeal, 1948)
Los Angeles Gas & Electric Corp. v. Superior Court
200 P. 811 (California Court of Appeal, 1921)
Condon v. Donohue
118 P. 113 (California Supreme Court, 1911)
Mills v. Olsen
115 P. 33 (Montana Supreme Court, 1911)
D. I. Nofziger Lumber Co. v. Solomon
110 P. 474 (California Court of Appeal, 1910)
Lacy Manufacturing Co. v. Los Angeles Gas & Electric Co.
106 P. 413 (California Court of Appeal, 1909)
Steiger Terra Cotta & Pottery Works v. City of Sonoma
100 P. 714 (California Court of Appeal, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
97 P. 414, 8 Cal. App. 514, 1908 Cal. App. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/los-angeles-pressed-brick-co-v-higgins-calctapp-1908.