Hughes Brothers v. Hoover

84 P. 681, 3 Cal. App. 145, 1906 Cal. App. LEXIS 194
CourtCalifornia Court of Appeal
DecidedFebruary 23, 1906
DocketCiv. No. 126.
StatusPublished
Cited by19 cases

This text of 84 P. 681 (Hughes Brothers v. Hoover) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hughes Brothers v. Hoover, 84 P. 681, 3 Cal. App. 145, 1906 Cal. App. LEXIS 194 (Cal. Ct. App. 1906).

Opinion

GRAY, P. J.

Appeal by the E. K. Wood Lumber Company from a judgment and an order denying a new trial in an action to foreclose a mechanic’s lien.

It appears from the record that the contract between the owner and contractor was valid; that one of its provisions gave to the owner the right, should the contractor neglect to supply a sufficient number of skilled workmen, or materials of the proper quality, or to prosecute the work with promptness and diligence, after three days’ notice, to terminate the employment and complete the work; that the contractor *147 making default, the owner gave the notice, and three.days after its service took possession of the building and completed the same; that deducting from the contract price the sum necessarily expended in the completion, and a certain payment made by stipulation, there remained in the owner’s hands on February 1, 1903, the date of completion, $5,953.86. That all of the claims of lien in controversy were filed in time, and actions, either original or by way of cross-complaint to other actions, were commenced within ninety days of the filing thereof, except the claim of appellant, which was commenced ninety-two days after its filing. Appellant’s claim of lien, however, which is stipulated to be true in every respect, disclosed that the materials furnished by appellant were payable in installments during the progress of the work, the last payment to be made within or before thirty-five days from the completion of the building. In one of the original actions brought to foreclose the liens, being case No. 41,412, appellant was not named as a party defendant, but in said action one E. K. Wood, John Doe, and others were named. Appellant answered, alleging that E. K. Wood had no interest in the controversy, but that it had, and set up in proper way its claim of lien. This pleading, denominated a cross-complaint, was served upon plaintiff, service acknowledged, and plaintiff entered an appearance thereto; the same was filed in the action, and subsequently all parties stipulated that they should be deemed as having answered thereto. Subsequently, appellant filed an original action, setting up that it had served the statutory notice upon the owner to withhold money under the contract, and upon this it claimed the right to a personal judgment against the owner and contractor. This case, and all of the other cases involving the question of the rights of the various parties to the unpaid balance on the contract, were consolidated and heard together. Upon the hearing the court found that appellant had never commenced any action upon its claim of lien, and apportioned all of the unpaid balance in the hands of the owner among the lien claimants other than appellant; but rendered a personal judgment in favor of appellant against the contractor.

This appeal presents two primary and controlling questions: 1. Was an action commenced by appellant upon its claim of lien when it filed the cross-complaint? 2. Was the same filed in time to avoid the force of the limitation provided in section *148 1190 of the Code of Civil Procedure ? The trial court, apparently with the acquiescence of all parties, proceeded upon the theory that all parties plaintiff and defendant in an action of this character who are served with process and appear thereto and answer are actors; and this seems to find support in Grant v. Murphy, 116 Cal. 431, [58 Am. St. Rep. 188, 48 Pac. 481], wherein it assigned the reasons why in proceedings in partition all parties thereto are actors, such reasons therein applying with equal force to a case of the character under consideration. It is apparent in this case, from the fact that the contract was a valid one and that a fixed balance unexpended of the contract price was the fund from which alone the parties were entitled to base their claims, that all lienholders were entitled to share therein. The cross-complaint of E. K. Wood Lumber Company, appellant herein, was filed, and all parties stipulated, in effect, that its allegations should be deemed to be.denied by each of the several parties. To be sure, the cross-complaint was once stricken out by the court on motion, but it was afterward restored by consent, and was left in the case as if no motion to strike out had ever been made. It was also stipulated that the defense that the ninety-day period for bringing action to foreclose the lien should be deemed to be pleaded to the said cross-complaint. It seems clear from the record, therefore, that no question was made in the court below about appellant’s lien not being properly before the court; but on the contrary, by express stipulations, issues were made up fully involving that lien and every defense that could be urged thereto. The trial court was thus, by the consent of all parties, given jurisdiction of the subject matter of all those issues and of the person of all the parties interested therein. It is too late to urge here for the first time that the appellant and its rights had no place in the trial court. No objection to that effect having been made, or, rather, the objection which was made having been withdrawn and no similar objection thereafter made in the court below, no such objection will be heard here. From these facts we say we must assume for the purposes of this appeal, that an action was commenced upon appellant’s claim of lien when it filed its cross-complaint, and that thereafter the said cross-complainant and its rights of lien and the defenses thereto were properly treated as before the trial court for its adjudication.

*149 We are also of opinion that the cross-complaint was filed in time. It appears from such cross-complaint that credit was extended and the filing thereof was within ninety days after the expiration of such credit. The proposition that this credit should be construed as expiring thirty-five days after abandonment of work by the contractor cannot be maintained; for it affirmatively appears that there was no actual abandonment of work in the sense contemplated by the statute, wherein abandonment is held to be the equivalent of completion. In eases of actual abandonment the right of the owner to complete, after awaiting the thirty-day suspension, is derived from the statute. In this case the right of completion was given by the contract itself, and no cessation of labor for any number of days was a condition precedent to the owner’s right of completion. Whatever, therefore, the owner did in the way of completing the building was as much performance under the contract as were similar acts performed by the contractor, and the completion, therefore, by the owner was a completion under the contract. Section 1190 of the Code of Civil Procedure provides: “No lien provided for in this chapter binds any building, mining claim, improvement, or structure, for a longer period than ninety days after the same has been filed, unless proceedings be commenced in a proper court within that time to enforce the same; or, if a credit be given, then ninety days after the expiration of such credit; but no lien continues in force for a longer time than two years from the time the work is completed, by any agreement to give credit. ’ ’ There is nothing in this section indicating that the credit therein mentioned refers to liens based upon direct contract with the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mutual Building & Loan Ass'n of Santa Fe v. Fidel
437 P.2d 134 (New Mexico Supreme Court, 1968)
Robinson v. S & S Development
256 Cal. App. 2d 13 (California Court of Appeal, 1967)
States Shingle Co. v. Kaufman
227 Cal. App. 2d 830 (California Court of Appeal, 1964)
Richards v. Hillside Development Co.
177 Cal. App. 2d 776 (California Court of Appeal, 1960)
Rutherford v. Maki
9 Alaska 350 (D. Alaska, 1938)
Fleshman v. Whiteside
34 P.2d 648 (Oregon Supreme Court, 1934)
Union Tank & Pipe Co. v. Mammoth Oil Co.
25 P.2d 262 (California Court of Appeal, 1933)
Hill v. Hesse
14 P.2d 338 (California Court of Appeal, 1932)
Monson v. Fischer
5 P.2d 628 (California Court of Appeal, 1931)
Leibowitz v. Berry
299 P. 779 (California Court of Appeal, 1931)
Mox, Inc. v. Leventhal
264 P. 562 (California Court of Appeal, 1928)
Hammond Lumber Co. v. Barth Investment Corp.
262 P. 31 (California Supreme Court, 1927)
Boise Payette Lumber Co. v. Weaver
234 P. 150 (Idaho Supreme Court, 1925)
Fuller v. Towne
193 P. 88 (California Supreme Court, 1920)
Hubbard v. Jurian
190 P. 1052 (California Court of Appeal, 1920)
People v. Moxley
120 P. 43 (California Court of Appeal, 1911)
Los Angeles Pressed Brick Co. v. Higgins
97 P. 414 (California Court of Appeal, 1908)
Goldtree v. City of San Diego
97 P. 216 (California Court of Appeal, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
84 P. 681, 3 Cal. App. 145, 1906 Cal. App. LEXIS 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hughes-brothers-v-hoover-calctapp-1906.