Goldtree v. City of San Diego

97 P. 216, 8 Cal. App. 505, 1908 Cal. App. LEXIS 156
California Court of Appeal·Decided July 9, 1908·No. Civ. No. 445.·Published·Cited by 8 cases

Opinion

ON BEHEARING.

TAGGART, J.

It being assumed upon the former decision of this appeal that the errors relied upon on the appeal from the judgment were the same as those presented on appeal No. 472, which was considered with it, the error of the trial court in awarding a personal judgment against the defendants Howard and Long escaped attention.

We are satisfied that while the laborers working for the subcontractor, Stabler, were entitled to have that portion of the sewer fund earned by their labor applied to the payment of their claims, they were not entitled to a personal judgment against the contractors.

In other respects we are satisfied with the opinion of this court filed in appeals Nos. 472 and 445 on the tenth day of January, 1908, which opinion is as follows:

*507 “Both of these appeals relate to a consolidated action to enforce an equitable lien upon a sewer improvement fund in the treasury of the city of San Diego claimed by plaintiff as the assignee of forty-eight laborers who worked upon the sewer system for which said fund was provided.
“Judgment was for plaintiff. Appeal No. 445 is by all the defendants, other than the city of San Diego, and is from the judgment and from an order denying their motion for a new trial. No. 472 is an appeal by the city of San Diego from a part of the judgment. These two appeals are brought up on separate records, but were submitted together by consent of the respective parties, and the briefs in each case are considered as if filed in both.
“Upon the oral presentation of Appeal No. 445 it was stated by the presiding justice of this court that if the papers claimed to have been omitted from the transcript were deemed necessary for a full consideration of the cause upon its merits, counsel for appellants would be notified and permitted to supply the same. Since these papers are all before us in the record in No. 472, the causes will be heard as if upon a consolidated record embracing both transcripts, and the objections to the transcript in No. 445 will not be considered.
“Plaintiff’s assignors performed labor to the value of various sums ranging from $3.96 to $53.46, and amounting in the aggregate to $1,231.96, upon a sewer system constructed by the city of San Diego. This labor was done under an employment by the defendant Stabler, who was a subcontractor under the defendants Howard & Long,- who were contractors with the city to construct such sewer system. Stabler defaulted in his subcontract and discontinued and abandoned work upon the portion of the sewer which he was to construct, and it was completed by said Howard & Long. At the time of the abandonment there was in the hands of the city of San Diego, then due from it to the contractors, from the fund in its treasury applicable to such sewer construction, the sum of $5,000, and of this sum more than $1,000 was earned by the work done on the portion of the sewer constructed by Stabler. Stabler failed to pay the said forty-eight laborers for their labor on the sewer, and immediately upon his abandoning the work, and while said *508 sum was still in the city treasury, they each served notice in writing on the city of their several claims upon said fund, as provided by section 1184 of the Code of Civil Procedure. Thereafter the forty-eight claims were assigned to plaintiff, who brought a single action upon the combined claims, and also separate actions upon each of them, which actions were by order of the trial court consolidated as provided by section 1048 of the Code of Civil Procedure.
“The first point made by appellants we do not think it necessary for us to consider at length. The validity of the bond given by the contractors is not in question here, as no recovery on the bond is sought by plaintiff. The reference to it in the complaint is to a step in the proceedings taken and had in the making of a valid contract between the city and Howard & Long. The order overruling defendants’ demurrers to the complaint on the ground of want of jurisdiction of the court must be considered then, in connection with the objections, (1) that the amount sued upon in each of the actions is less than $300, and. (2) that service of the notice provided to be given by section 1184 does not create an equitable lien upon that part of the sewer improvement fund in the city treasury which is due and owing under the contract with Howard & Long for work done upon that portion of the sewer system constructed by the labor of plaintiff’s assignors.
“The state constitution (sec. 15, art. XX), declares that laborers of every class shall have a lien upon the property upon which they have bestowed labor, for the value of the labor done. No exception as to public or municipal property is made by the section. Only because of other constitutional provisions, or by reason of public policy, can the laborer be deprived of the right so created by the people. Without constitutional authority the right to the lien cannot be taken away by the legislature, either by legislation or lack of legislation. The last clause of section 15 requires the legislature to provide, by law, for the speedy and efficient enforcement of the liens the right to which are thereby created. The question of whether or not section 15 is self-executing is not material, since the legislature in obedience thereto has already provided a good and sufficient procedure whereby the lien may be declared and enforced.
*509 “Authorities based upon the theory that the Lien Law is a creation of the statute, in the strict sense of that term, are misleading when the right to the lien is under consideration in this state. Only as the terms statute or statutory law are intended to include the constitution as well as the enactments of the legislature can they be said to create the right to a mechanic’s lien. (Spinney v. Griffith, 98 Cal. 149, [32 Pac. 974].) The more recent decisions of the supreme court recognize the force of the constitutional declaration of the right. (Hampton v. Christensen, 148 Cal. 737, [84 Pac. 200] ; Hughes Bros. v. Hoover, 3 Cal. App. 150, [84 Pac. 681].)
“The mechanic’s lien law of the code is the statutory provision made by the legislature in obedience to the constitutional mandate of section 15 and prescribes the manner in which the right to the lien in each particular case may be declared and rendered effective. Two methods, are provided for giving notice of claim of lien; one by recording against the property (sec. 1183), and the other by notice to the holder of the fund which has been earned by the claimant’s labor. (Sec. 1184.) The former, for reasons of public policy, cannot be enforced against a public building or improvement, but no such objection exists as to the latter. It is contended by appellants that both of these methods were intended by the legislature to apply only to private owners. To so construe the enactment would be to hold that the legislature has failed to carry out the command to provide means to render effectual the right created by the constitution; that it has only partially complied with the requirement of the section. The Bond Act of 1897 (Stats. 1897, p.

Free access — add to your briefcase to read the full text and ask questions with AI

Goldtree v. City of San Diego, 97 P. 216, 8 Cal. App. 505, 1908 Cal. App. LEXIS 156 (Cal. Ct. App. 1908).

97 P. 216 (Goldtree v. City of San Diego) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Robinson Township School District's Petition
58 Pa. D. & C. 217 (Alleghany County Court of Common Pleas, 1946)
Commander v. Board of Com'rs
11 So. 2d 605 (Supreme Court of Louisiana, 1942)
Hughes v. Baker
1934 OK 446 (Supreme Court of Oklahoma, 1934)
Stansbury v. Frazer
189 P. 495 (California Court of Appeal, 1920)
Sweeney v. Board of Trustees of Auburn School District
165 P.2d 42 (California Court of Appeal, 1917)
Emigh-Winchell Hdw. Co. v. Pylman
31 Cal. App. 46 (California Court of Appeal, 1916)
Emigh-Winchell Hardware Co. v. Pylman
31 Cal. App. 46 (California Court of Appeal, 1916)
D. I. Nofziger Lumber Co. v. Solomon
110 P. 474 (California Court of Appeal, 1910)