Hammond Lumber Co. v. Barth Investment Corp.

262 P. 31, 202 Cal. 606, 1927 Cal. LEXIS 390
CourtCalifornia Supreme Court
DecidedDecember 13, 1927
DocketDocket No. L.A. 8926.
StatusPublished
Cited by19 cases

This text of 262 P. 31 (Hammond Lumber Co. v. Barth Investment Corp.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammond Lumber Co. v. Barth Investment Corp., 262 P. 31, 202 Cal. 606, 1927 Cal. LEXIS 390 (Cal. 1927).

Opinion

SEAWELL, J.

This appeal, which is from the judgment-roll, involves some questions of law similar to those decided in Hammond Lumber Co. v. Barth Investment Corp., ante, p. 601 [262 Pac. 29], and as to such questions that case is decisive. Carl Heilman and Anna Heilman were owners of a lot situated in the city of Los Angeles. C. A. Barth and Barth Investment Corporation contracted with said owners to erect upon said lot a flat at the cost of $13,500 to said owners. The action was commenced to foreclose a materialman’s lien and for a personal judgment against said contractors in the sum of $3,000.17. Judgment went by default against said contractors, but in favor of respondents Heilman for costs of suit. This appeal is taken from that portion of the judgment entered in favor of said respondents.

The questions presented are whether or not the asserted lien of appellant, the materialman, was filed' within the statutory time prescribed by section 1187 of the Code of Civil Procedure, and also as to the eonclusiveness of certain ultimate findings which are in conflict with certain findings of probative facts. That question is dependent upon the time the building was completed, inasmuch as the owner neglected to file for record notice of the completion of said *608 improvement contract or.a cessation of labor thereon as provided by said section 1187, supra. The building contract provided for certain electrical construction or equipment as a part of the building. The electrical work was subcontracted, but the subcontractor, soon after entering upon the performance of his contract, abandoned work thereunder and left it, as found by the court, in “a partially incomplete and unfinished condition.” Thereafter the original contractors employed an electrical contractor, one Ingraham, to complete said work. The court further found, as set forth in finding Vila, that “The said Ingraham, while said owners were in the use,, occupation and possession of said structure, did 95 hours’ work upon said Heilman flats to correct and complete said electrical work in accord with the plans and specifications and the requirements of the city ordinances of the city of Los Angeles at a reasonable cost of $260.61; that said work was done partially in July, 1922, and was necessary to correct and complete the work in accordance with the plans and specifications; that said work consisted generally of putting in more and heavier wires, and drawing out wires not heavy enough to carry the load; and putting in necessary materials to correct and complete said work; that said work done by the said Ingraham was finished on the eleventh day of July, 1922, except six hours’ work that was done on August 16, 1922, and five hours’work on August 17, 1922. That without the work done by said Ingraham, the city electrician’s office of the city of Los Angeles refused to accept said work and furnish a final inspector's certificate; that said acceptance by the city and the final certificate of acceptance was not issued by the city until after the 7th day of August, 1922. The original contract for the construction of said building contained the following: ‘All work to be installed in accordance with city ordinances furnishing electrical inspector’s certificate before work will be accepted.’ The court finds that the above work constituted a trivial imperfection; that the contract cost of construction of said flat was $13,500 and that the original contract cost for the installation of the electrical work was $357.00. The city permit granted to said Ingraham to do his work was dated and issued June 5, 1922.”

By preceding ultimate findings the court found that said owners did not file for record a notice of the completion of *609 said building, and that said building contract was completed on June 8, 1922. If the ultimate finding as to the completion should not be permitted to prevail over the conclusion which must be drawn from the probative facts specifically found by the court, and which lead in a contrary direction, the lien of appellant must be held to be a valid and subsisting lien and a reversal of the case must be ordered. The question, therefore, is whether the electrical work performed within the period of ninety days immediately preceding the day on which appellant’s lien was filed, to wit, September 15, 1922, constituted the correction of trivial imperfections merely, as found by the court (see. 1187, Code Civ. Proc.), or whether, as contended by appellant, said work was a material part of the contract which must be performed before it may be claimed that the contract was completed in the sense that the lien claimant is deprived of its lien. “As a general rule findings of ultimate facts may not be impeached, controlled, limited or modified by findings of probative facts, but will control in case of any conflict between them. Findings of probative facts invalidate a finding of an ultimate fact only when the latter is based on the former and is entirely overcome thereby and when the findings of probative facts dispose of all the facts involved in the pleadings.” (24 Cal. Jur. 972; Lee v. Hibernia, Savings & Loan Soc., 177 Cal. 656 [171 Pac. 677]; Steele v. Scott, 192 Cal. 521 [221 Pac. 342].) So, too,'it is the rule that “where the court, in addition to general findings, makes specific findings as to particular averments of the pleadings the latter control in the case of inconsistency.” (24 Cal. Jur. 974.) A general finding which is in effect but a conclusion of law is insufficient. (See footnote 16, 24 Cal. Jur. 974.) The findings in the instant case present and dispose of all the facts in the case and the ultimate fact is uneontrovertibly based upon probative facts as specifically set out by the court. If, then, the probative facts, as found by the court, are repugnant to the ultimate fact, that said building was completed prior to the months of July or August, 1922, the latter is invalidated by the former. The question squarely presented is whether, as a matter of law, the greater part of labor done and materials furnished for the completion of the electrical work according to the plans and specifications of the contract, and performed *610 in July and August, was of the kind and character and of sufficient contractual importance to warrant a finding that the building contract, so far as the materialman’s lien was affected thereby, was not completed without the additional labor and material which it was necessary to employ and furnish at a cost of $260 in order to comply with the plans and specifications of the original contract. We are of the view that the work necessary to be done to complete the electrical construction was in no sense a “trivial imperfection.” The portion of section 1187 of the Code of Civil Procedure, which the trial court held to be determinative of appellant’s rights, provides: “Any trivial imperfection in the said work, or in the completion of any contract by any lien claimant, or in the construction of any building, improvement or structure, . . . shall not be deemed such a lack of completion as to prevent the filing of any lien. ...”

This provision of the act was added to the earlier act for the benefit of the lien claimant,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Asphalt, Inc. v. Garrett Corp.
180 Cal. App. 3d 1001 (California Court of Appeal, 1986)
Green v. Smith
261 Cal. App. 2d 392 (California Court of Appeal, 1968)
Fredericksen v. Harney
199 Cal. App. 2d 189 (California Court of Appeal, 1962)
In re of Lightner
184 F. Supp. 825 (S.D. California, 1960)
Lewis v. Hopper
295 P.2d 93 (California Court of Appeal, 1956)
Munger & Munger v. McBratney
280 P.2d 232 (California Court of Appeal, 1955)
Estate of Kerr
274 P.2d 234 (California Court of Appeal, 1954)
Lámar v. Lámar
30 Cal. 2d 898 (California Supreme Court, 1947)
Garrison v. Edward Brown & Sons
154 P.2d 377 (California Supreme Court, 1944)
Sayles v. County of Los Angeles
138 P.2d 768 (California Court of Appeal, 1943)
Fitzpatrick v. Underwood
112 P.2d 3 (California Supreme Court, 1941)
Central Heights Improvement Co. v. Memorial Parks, Inc.
105 P.2d 596 (California Court of Appeal, 1940)
Quinn v. Rosenfeld
102 P.2d 317 (California Supreme Court, 1940)
Wilcox v. Cloward
56 P.2d 1 (Utah Supreme Court, 1936)
Hendrickson v. Bertelson
35 P.2d 318 (California Supreme Court, 1934)
Boise-Payette Lumber Co. v. Longwedel
295 P. 791 (Supreme Court of Colorado, 1930)
Winship v. Holden
265 P. 572 (California Court of Appeal, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
262 P. 31, 202 Cal. 606, 1927 Cal. LEXIS 390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammond-lumber-co-v-barth-investment-corp-cal-1927.