Joost v. Sullivan

43 P. 896, 111 Cal. 286, 1896 Cal. LEXIS 577
CourtCalifornia Supreme Court
DecidedFebruary 20, 1896
DocketNo. 10035
StatusPublished
Cited by23 cases

This text of 43 P. 896 (Joost v. Sullivan) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joost v. Sullivan, 43 P. 896, 111 Cal. 286, 1896 Cal. LEXIS 577 (Cal. 1896).

Opinion

Haynes, C.

Action to foreclose subcontractors’ liens. Pending the litigation the claim of Joost Brothers was [289]*289paid, and the only defendants served were Eugene and Kate Sullivan. The claims of Byron and Bayreutlier were sustained by the court, and from the judgment, enforcing their liens and from an order denying a new trial this appeal is prosecuted.

Eugene Sullivan was the owner, and his wife, Kate Sullivan, was made a party, the complaint alleging that she claimed some interest in the property. Eugene Sullivan died before the trial, and Kate Sullivan, having been duly appointed administratrix of his estate, was substituted, as such administratrix, in his stead; and as such, and as an individual, has taken this appeal.

A contract was made by Eugene Sullivan with one Westcott to raise, make alterations, additions, and repairs to a two-story frame building upon a lot situate at No. 625 Natoma street, city of San Francisco. Plaintiffs alleged that neither said contract nor any memorandum thereof was ever filed in the recorder’s office; “that said building was completed on or about the fourteenth day of October, 1891, and further alleged the filing of their respective liens before the expiration of thirty days from and after the completion of the building.”

The answer denied each of these allegations, and alleged that the building was completed on October 10, 3891. Bayreuther’s notice of lien was filed November 11,1891, and Byron’s on November 12th; and, therefore, if the building was completed on October 10th, both claims were filed too late.

The court found that neither the contract nor any memorandum thereof was filed, and that the building was completed bn October 14th, and appellant contends that these findings are not justified by the evidence.

Byron’s subcontract was for the brickwork, for which he was to receive two hundred and thirty-five dollars, and his work was finished September 24, 1891. He testified that he was at the house (the building in question) on October 14th; that it was then completed; that he did not know how long before that it had been completed; that he could not say when, prior to October 14bh, was, [290]*290the last time he had been there, and that he did not know whether it was completed before October 14th or not.

Mr. Bayreuther testified that he furnished the material for four closets, two bathtubs, the kitchen sinks, etc., that he furnished the materials and completed the work which included all the plumbing in the building according to the specifications, and did some extra work which consisted of tinning in gutters and one extra gas-fitting in the two lower flats, and that he completed his work on October 3d; that he saw the building on October lltli and 14th; that the contractor took his tools away on the 14th; that he was called there on Sunday morning, October 11th, by Miss Sullivan because one of the closets in the building made a rattling noise, and he sent a man there on the 12th to repair it; that he went the next day to see if everything was all right, and saw the contractor moving his tools away; that “ the building was completed that day. The alterations consisted of raising an old house, making three flats of it—two upper and one lower flat. The defendants were living at that time in the upper flat.” He further testified that when he called there Sunday -morning, October 11th, there was a doorknob not on in the upper flat, and a rim to a bath on the lower flat had not been put on, and did not "observe anything else unfinished; that putting on the doorknob and rim of the bathtub was not his work; that the closet was not broken, but made a noise; that he had an agreement that in case anything was wrong with the closets lie would repair them- and make them in good order, and that he formed the conclusion that the building was completed on the 14th from what others told him, and from seeing the contractor moving his tools away. Mr. Westcott, the contractor, was not subpoenaed by the plaintiffs, and was not at the trial.

M. J. Welch, the architect in charge "of the work, was called by plaintiff and testified as to other matters, but was not examined as to the date of the completion of the work, and plaintiffs thereupon rested.

[291]*291Mr. Welch-was then called for defendants, and testified that the building was completed on the 8th or 9th of October. Upon cross-examination he testified that he was sure it was the 8th or 9th, because it took him several days to straighten out the business affairs before he issued the certificate for the payment which was to be made upon completion of the work; that he delayed because there was a doubt about the contractor paying his bills; that he wished to find out how his bills stood and see that things were straightened out before the certificate was issued; that he was fully a week going to the bondsmen and seeing the creditors, and that it was fully a week after the building was completed before he issued the certificate, and the certificate was dated and issued October 15, 1891. He further testified that the building was partly occupied by the defendant and his family the first week of October, 1891.

Miss Ella Sullivan testified that she was living with her parents in the house when she sent for Mr. Bayreuther on October 11th; that Westcott was there when Bayreuther called; that the house was then completed and the men had all gone away except Westcott; that they were then living on the upper floor; that the locks mentioned rvere on the old work and not on the new; and that Westcott did not take his tools away until the 14th because he was waiting for someone to lend him a horse and wagon for that purpose.

Mrs. Kate Sullivan, one of the defendants, testified that the house was completed before Bayreuther was called to fix the closet, and she was then occupjdng the upper floor, and the ground floor was also rented and occupied. Upon cross-examination she testified that it was completed a week before Bayreuther called, but .afterward changed the time to a week, or maybe more, before she paid the third payment, which was on October 15th. The foregoing is. the substance of all the evidence relating to the date at which the building was completed.

The finding that the date of completion was October [292]*292l4th is not justified by the evidence. Byron testified that he did not know whether it was completed before that date or not. Bayreuther completed his contract on October 3d, and there is no evidence that any work was done on the building after that date, except fixing a closet which “ made a noise,” and which was confessedly the “ repair” of his completed work. Under these circumstances the testimony of the plaintiffs could only be regarded as showing that the building was in a completed state or condition on the 14th, and not that the work ended on that day, and therefore does not conflict with the positive testimony of the architect and of Mrs. Sullivan and her daughter that it was completed at least as early as the 10th. Besides, the putting on of a doorknob which appears to have been mislaid, and of the rim of a bathtub, were in themselves “trivial imperfections” which would not have invalidated plaintiffs’ liens if they had filed them on Monday, the 12th. (Harlan v. Stufflebeem, 87 Cal. 508.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alioto v. Hoiles
531 F. App'x 842 (Tenth Circuit, 2013)
Davis v. Ssd Dept. of Ed.
2011 S.D. 51 (South Dakota Supreme Court, 2011)
Trabin v. Title Insurance & Trust Co.
339 P.2d 136 (California Supreme Court, 1959)
Lewis v. Hopper
295 P.2d 93 (California Court of Appeal, 1956)
Durand v. Cline
119 P.2d 891 (Idaho Supreme Court, 1941)
Nelson v. Boise Petroleum Corp.
32 P.2d 782 (Idaho Supreme Court, 1934)
Fractional School District No. 1 v. Township School District
242 N.W. 843 (Michigan Supreme Court, 1932)
Offeman v. Robertson-Cole Studios, Inc.
251 P. 830 (California Court of Appeal, 1926)
Hodges v. City of Roswell
247 P. 310 (New Mexico Supreme Court, 1926)
Gem State Lumber Co. v. Witty
217 P. 1027 (Idaho Supreme Court, 1923)
Union Hollywood Water Co. v. City of Los Angeles
195 P. 55 (California Supreme Court, 1920)
Mott v. Wright
184 P. 517 (California Court of Appeal, 1919)
Sanders v. Austin
182 P. 449 (California Supreme Court, 1919)
McEwen v. City of Coeur D'Alene
132 P. 308 (Idaho Supreme Court, 1913)
Burnett v. Glas
97 P. 423 (California Supreme Court, 1908)
Los Angeles Pressed Brick Co. v. Higgins
97 P. 414 (California Court of Appeal, 1908)
Stimson Mill Co. v. Los Angles Traction Co.
74 P. 357 (California Supreme Court, 1903)
L. W. Blinn Lumber Co. v. Walker
61 P. 664 (California Supreme Court, 1900)
Bringham v. Knox
59 P. 198 (California Supreme Court, 1899)
Burleigh Building Co. v. Merchant Brick & Building Co.
13 Colo. App. 455 (Colorado Court of Appeals, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
43 P. 896, 111 Cal. 286, 1896 Cal. LEXIS 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joost-v-sullivan-cal-1896.