Burleigh Building Co. v. Merchant Brick & Building Co.

13 Colo. App. 455
CourtColorado Court of Appeals
DecidedSeptember 15, 1899
DocketNo. 1634
StatusPublished
Cited by2 cases

This text of 13 Colo. App. 455 (Burleigh Building Co. v. Merchant Brick & Building Co.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burleigh Building Co. v. Merchant Brick & Building Co., 13 Colo. App. 455 (Colo. Ct. App. 1899).

Opinion

Bissell, P. J.

A judgment ought never to have been entered against the sureties on the bond. This matter is very easily demonstrated by a comparatively brief consideration of the terms of the instrument and of a few facts respecting the contract under which the brick was sold. There are many questions suggested by the record which if decided would necessarily call for the construction of a number of the provisions of the lien act of 1893. While this construction is requested and a good deal of argument directed to the propositions which would compel the consideration, we cannot easily imagine the necessity to consider them, though possibly there may be other suits pending in which a decision of some of these matters would be desirable. The act of 1893, however, has been repealed and a new act was passed in 1899. The later act, of course, contains many of the provisions of the act of 1893 as well as some additional ones, as the last legislature, like all others which have legislated on this question, has attempted to broaden the statute and enlarge the rights and further secure the interests of the material men and builders. We have already had occasion to animadvert on this species of legislation, but it may be wisest for the courts to construe the acts which the legislature has passed and not criticise the policy which has led to the enactments. The repeal, however, and the change in the act is a complete excuse for our refusal to consider any other questions than those which are absolutely indispensable to the determination of the present appeal. We shall therefore only consider those matters which we regard as vital, and which being determined adversely to the appellee, must reverse the judgment.

The statement shows the bond was executed by the Burleigh Building Company and the O’Donnells as sureties, on a condition in effect that the Burleigh Building Company should pay any judgment which should be legitimately [461]*461rendered against it and be declared to be a lien on the premises, provided the premises were then subject to the hen of the judgment. This is the legal effect of the condition. Manifestly then to entitle the Merchant Brick and Building Company to recover from the sureties, it must regularly and lawfully obtain a judgment against the Burleigh Building Company, and the evidence must warrant it, otherwise the sureties may not be held. If this be not true, it would follow that should the Merchant Brick and Building Company obtain a judgment against the Burleigh company without right or warrant, the sureties would still be bound and remediless because without the right to question the character of the judgment. This could never be for the rights of the sureties are to be measured by the terms of the contract into which they have entered, and unless their principal be legally held, no judgment can rightfully be entered against them. It remains then to determine the validity of this judgment against the Burleigh Building Company. We conclude there is no evidence in the record to justify it. By this we mean no evidence which warrants a personal judgment against the Burleigh Building Company. We do not refer to a decree of foreclosure legitimately entered against Mr. Burleigh, the antecedent owners and possibly the building company. This is true because the condition of the bond is that the Burleigh Building Company shall pay any judgment rendered against them and adjudged and decreed to be a lien on the premises. It therefore follows, there must be some judgment rendered against the building company for the value of the materials sold and delivered which the company is bound to pay, and this judgment must likewise be declared a lien on the premises. We are quite ready to concede a bond might have been drawn containing a condition that if the lien should be established against the property and whatever interests the Burleigh company acquired by the transfer of April 22, then, and in such event, the sureties should be liable. This was not the bond, however, and such is not its condition. Its condition is to pay any judgment rendered against the com[462]*462pany in the suit which can only mean a money judgment which the Burleigh Building Company is bound to pay, and for which the sureties must respond. Under these circumstances in order to establish a liability against the O’Donnells it is incumbent on the plaintiff to prove facts entitling it to a personal judgment against the Burleigh Building Company for that money. This it wholly failed to do. Referring to the statement, it shows the property was owned by Henry J. Burleigh on the 1st of April, at the time Burleigh and Snell talked with the appellee about the sale of brick. If any contract was made, it was made then and made with those parties only. In it the Burleigh 'Building Company had no interest, nor so far as the record shows had they then any title to, or interest in, the property. Under these circumstances the corporation was in no manner bound by the contract of purchase, nor did the fact that this corporation ultimately became the purchaser of the property or the holder of the title bind them to pay for the brick which had been delivered prior to the 22d day of April, nor was it bound for the 13,000 brick thereafter delivered unless it was made to appear the company accepted the brick and appropriated it for the purpose of the building. This was not established. No evidence was introduced to show the Burleigh Building Company accepted or agreed to carry out or in any wise became bound by the original contract for the purchase of the brick made either with Burleigh or Snell or both. Under these circumstances there could be no personal judgment against the Burleigh Building Company for the brick delivered prior to the 22d day of April. As to the 13,000 brick thereafter delivered, there is nothing to show that the company received them, had any knowledge of them, became bound to pay for them, or under the terms of its purchase of the property from Henry J. Burleigh became obligated to pay for them. It may easily be, and I can readily conceive, the Burleigh Building Company took title under an agreement to assume these outstanding obligations. This concession, hoAvever, in no manner justifies the judgment. The [463]*463judgment must rest on evidence. The sureties have a right to insist the plaintiff shall prove his case, and failing to support it by competent and sufficient testimonj'- no judgment shall be entered against the principal by which they shall be concluded. We agree with them that the plaintiff made out no case which entitled it to a personal judgment against the Burleigh Building Company, and it therefore was not entitled to recover as against them. Doubtless on the subsequent trial counsel may be able to produce testimony which will obviate the difficulty. With this possibility we have no concern, simply determining that on the record as it stands, he was not entitled to judgment against the company and therefore he ought* not to have had judgment against the sureties.

There is another proposition to which we will advert as it will have a good deal of bearing on the subsequent trial. According to the statute if the brick was sold to Snell as a contractor, he was bound to file his lien within a fixed time and if a subcontractor within another fixed date, and in any event according to section 6, the lien could not hold the property more than four months after the completion of the structure or improvement unless an action should be commenced within that time to enforce it. By the provisions of section 3 a cessation of labor on any unfinished building is the equivalent of completion. We are quite unable to determine Snell’s connection or relation to the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perkins v. Boyd
16 Colo. App. 266 (Colorado Court of Appeals, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
13 Colo. App. 455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burleigh-building-co-v-merchant-brick-building-co-coloctapp-1899.