Burnett v. Glas

97 P. 423, 154 Cal. 249, 1908 Cal. LEXIS 328
CourtCalifornia Supreme Court
DecidedSeptember 3, 1908
DocketSac. No. 1485.
StatusPublished
Cited by19 cases

This text of 97 P. 423 (Burnett v. Glas) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burnett v. Glas, 97 P. 423, 154 Cal. 249, 1908 Cal. LEXIS 328 (Cal. 1908).

Opinion

ANGELLOTTI, J.

This is an appeal by defendants, the owners of a lot of land in the town of Madera, 77% feet on Yosemite Avenue by 150 feet in depth on C Street, from a judgment given in several actions for the foreclosure of the liens of certain mechanics and materialmen arising in and about the construction of a building on said land, which actions were consolidated under section 1195 of the Code of Civil Procedure, and tried as one aetion.

The findings show the material facts to be as follows: On November 9, 1903, the appellants as owners, entered into a written contract with one W. J. Sircy, as contractor, for the erection on said land of a one-story and basement brick store building, the contractor agreeing therein “to furnish the necessary labor and materials . . . and perform and complete in a workmanlike manner, all the brick work, iron work, plastering and carpenter work and other works shown and described in and by and in conformity with the plans, drawings and specifications for the same, made by Julien Mourot, the authorized architect employed by the owner, and are signed by the parties hereto, and are to be kept and remain in the office of said architect subject to the inspection of the parties hereto and others concerned in said erection.” In the *252 contract it was further provided that said building was to be a “one-story and basement brick store building with corrugated galvanized iron roof, said building to be 77' Q" x 80 ft.” It was expressly found that the plans, drawings, and specifications mentioned in said contract were a material, important, and necessary part thereof, and this conclusion was manifestly correct. The plans, drawings, and specifications were never filed in the county recorder’s office. The remainder of the contract was so filed on November 19, 1903. According to the terms thereof, the consideration of $7320 was to be paid in five installments of $1464 each, the fourth installment to be paid when the building was completed and accepted, and the last installment, which was only twenty per cent of the whole contract price, was to be retained for thirty-five days after completion. On November 17, 1903, the contractor gave a bond upon said contract, with M. R. Madary and C. J. Craycroft as sureties, by which the sureties guaranteed the performance of said contract, and the delivery of the building free of liens. Work was commenced by the contractor in November, 1903, and continued to December 24, 1903, when a further written agreement was entered into by appellant and Sircy, whereby Sircy agreed to construct for $1318 a second story to said building, the same to be paid when “the story is up ready for the ceiling joists.” This writing was never filed in the county recorder’s office. The work was continued under these two writings to April 9, 1904, when the building was completed and delivered to and accepted by the appellants. Appellants have paid on account of the contract price $7,387.50, leaving in their hands a balance of $1,250.50. The various lien claimants whose liens were allowed by the trial court, furnished to the contractor materials to be and which were used in the construction of said building, or performed labor thereon, as follows: J. H. Burnett furnished materials at an agreed price, — namely, $300. J. A. Sircy, whose claim was assigned to plaintiff, Barrett-Hiclcs Co., a corporation, performed labor at an agreed price of $3.50 per day, to the extent of $86.70. J. A. Dyer furnished materials under contract with the contractor, for which the contractor agreed to pay “the reasonable market price thereof from time to time as the same were furnished and as the work on said building progressed,” the amount of his allowed claim therefor being *253 $5S5.45. J. A. Dyer and 0. J. Craycroft, copartners, under the name and style of J. A. Dyer, furnished the contractor, under contract with him, brick at a fixed price per thousand brick, to be paid for as the same were placed in the building, the balance of their claim, which was allowed, being $717.65. Watkins & Thurman furnished materials “to be paid for at the regular and usual market price, in cash upon delivery of the same,” such price being found to be $276.64. The claims of lien of these parties were all filed for record in the office of the county recorder of Madera County within the proper time, and were all in proper form. In the claim of Watkins & Thurman so filed there was included separately a claim for an amount due them in addition to the $276.64, for one half the cost of constructing a party wall, and as to this the court found they should be paid by the other owners of the party wall and were not entitled to a lien against appellants’ property. It, however, found that such claim was made without any wrongful intent, but with an honest belief that they were entitled to a lien for the amount. This finding is not attacked. On November 17, 1903, appellants borrowed from defendant Commercial Bank of Madera, the sum of eight thousand dollars, and gave their mortgage covering said property to secure payment thereof, with interest at eleven per cent per annum. This mortgage was duly recorded on the day of its execution. As appears from the mortgage introduced in evidence, the note given for this loan was dated November 19, 1903, and was payable “five years after date.” The mortgagee appeared in the actions, and in its answers set up said mortgage, alleged that “no part of the principal sum mentioned . . . has been paid,” that the same with interest is wholly unpaid, and is a valid and first lien on said property, but it did not ask foreclosure of its lien. The interest on this note was paid to May 19, 1905. The court found that claimants J. A. Dyer and Dyer & Craycroft both commenced to furnish the materials furnished by them respectively on November 13, 1903, a date prior to the attaching of the lien of defendant bank’s mortgage. This finding is not attacked. The other liens were confessedly subject to said mortgage. There were claims of lien on behalf of some other parties which wrere rejected by the trial court, but these parties have not appealed, and that matter is immaterial here. *254 It was further found that of said land on which the building was constructed, the amount necessary for the convenient use and occupation of the building was 77% feet on Yosemite Avenue by 100 feet in depth on C Street. This finding is not attacked.

The trial court concluded upon these facts that the contract between the appellants and Sirey was void for failure to comply with the provisions of sections 1183 and 1184 of the Code of Civil Procedure, and that under the terms of said sections the labor done and materials furnished by the claimants must be deemed to have been done and furnished at the personal instance of the appellants, and they were entitled to a lien therefor, regardless of the amount due from appellants to the contractor. It found the amounts due such claimants, allowing interest on all the claims prior to judgment, and also attorney fees. Judgment was given accordingly, directing the sale of the portion of the lot found to be necessary for the convenient use and occupation of the building, and the building thereon, and the application of the proceeds as follows, viz.: 1. To the payment of the costs, etc., of sale; 2. To the payment of the amounts due claimants J. A. Dyer and. Dyer & Craycroft; 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Leonard
243 N.W.2d 887 (Supreme Court of Iowa, 1976)
Schmidt v. Waterford Winery, Ltd.
177 Cal. App. 2d 28 (California Court of Appeal, 1960)
Lineman v. Schmid
195 P.2d 408 (California Supreme Court, 1948)
Associated Wholesale Electric Co. v. S. H. Kress & Co.
54 P.2d 38 (California Court of Appeal, 1936)
Municipal Bond Co. v. Balboa Construction Co.
34 P.2d 1032 (California Court of Appeal, 1934)
Simpson v. Bergmann
13 P.2d 531 (California Court of Appeal, 1932)
Combs v. Eberhard
7 P.2d 338 (California Court of Appeal, 1932)
Hobart Estate Co. v. Jones
274 P. 921 (Nevada Supreme Court, 1929)
Armour & Co. v. McPhee & McGinnity Co.
275 P. 12 (Supreme Court of Colorado, 1929)
Sweet v. Fresno Hotel Co.
164 P. 788 (California Supreme Court, 1917)
Roystone Co. v. Darling
154 P. 15 (California Supreme Court, 1915)
Schade v. Muller
146 P. 144 (Oregon Supreme Court, 1915)
Peterson v. Freiermuth
121 P. 299 (California Court of Appeal, 1911)
Coghlan v. Quartararo
115 P. 664 (California Court of Appeal, 1911)
D. I. Nofziger Lumber Co. v. Solomon
110 P. 474 (California Court of Appeal, 1910)
Barrett-Hicks Co. v. Glas
99 P. 856 (California Court of Appeal, 1908)
Klokke v. Raphael
96 P. 392 (California Court of Appeal, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
97 P. 423, 154 Cal. 249, 1908 Cal. LEXIS 328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burnett-v-glas-cal-1908.