Sweet v. Fresno Hotel Co.

164 P. 788, 174 Cal. 789, 1917 Cal. LEXIS 867
CourtCalifornia Supreme Court
DecidedApril 19, 1917
DocketS. F. No. 7268.
StatusPublished
Cited by17 cases

This text of 164 P. 788 (Sweet v. Fresno Hotel Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sweet v. Fresno Hotel Co., 164 P. 788, 174 Cal. 789, 1917 Cal. LEXIS 867 (Cal. 1917).

Opinion

SHAW, J.

The cases here presented are actions to foreclose mechanics’ liens.

All the parties appealed. The appeal of the plaintiffs, Brandt Bros., was presented in case No. 6915 and has been decided, the judgment having been held good against their attacks. (Brandt Bros. v. Fresno Hotel Co., 173 Cal. 209, [159 Pac. 434].) The appeals of the other parties are presented by the record in this case (No. 7268), and will now be considered. The contract was made and filed and the work was begun prior to the enactment of the amendments of 1911 to the mechanic’s lien law. The rights of the respective parties are therefore dependent on the law existing before those *791 amendments took effect, and onr references to code sections are to be understood as referring to them in their pre-existing form.

The Fresno Hotel Company contracted with H. C. Farley & Co., a corporation, for the erection of a building by said Farley & Co., on certain lots in the city of Fresno belonging to the Hotel Company. The Hotel Company therein agreed, in consideration of the erection of said building, “to pay, or cause to be paid, to the contractor,” the sum of one hundred and ninety-nine thousand five hundred dollars “at times and in the manner following, to wit: Seventy-five per cent of the completed work done during the preceding month to be paid on the first of every succeeding month.” It was also provided that at the final completion of the work the architect should certify to that fact in writing to the contractor, stating therein the amount then due. There were no provisions or agreements for the payment of the remaining twenty-five per cent of the contract price, other than those above set forth, nor any statement that the same should be “payable at least thirty-five days after the final completion of the contract,” as required by section 1184 of the Code of Civil Procedure. This contract was duly filed in the office of the county recorder on December 17, 1910, before the work thereunder was begun. The contractor proceeded with the erection of the proposed building until November 15, 1911, at which time it ceased work thereon and it has never resumed the same. On December 21, 1911, the Hotel Company, pursuant to the first clause of section 1187 of the Code of Civil Procedure, filed in the recorder’s office a notice of cessation of labor on the building.

On January 12, 1912, the plaintiff, Sweet, filed in the recorder’s office his claim of lien against the property for certain labor performed and materials furnished for and used in the building, under agreements with the original contractor. On January 15, 1912, plaintiffs, Brandt Bros., filed their claim of lien against the property for certain work performed and materials furnished by them therefor and used therein, under agreements with the contractor. The present actions are for the foreclosure of these liens.

The court found that the balance owing to Sweet for the materials furnished and labor performed by him in the erection of the building was $3,231.06, and that the balance owing to Brandt Bros, for the labor performed and materials *792 furnished by them in the erection of said building was $5,585.65. Judgment of foreclosure was duly rendered in favor of the respective plaintiffs for these sums.

We will first consider the appeals of the Hotel Company.

The judgment of the court below was given upon the theory that the contract was invalid as to third persons because of its failure to provide that one-fourth of the contract price should not be payable until thirty-five days after completion, and that consequently the plaintiffs were entitled to a lien for the full amount unpaid of the value of their labor and materials furnished, although the balance unpaid from the owner to the contractor was not sufficient to pay such claims in full. Section 1184 expressly declares that if a building contract does not “conform substantially” to its provisions, “the labor done and materials furnished by all persons except the contractor shall be deemed to have been done and furnished at the personal instance and request of the person who contracted with the contractor, and they shall have a lien for the value thereof. ’ ’ Our decisions uniformly hold that where such substantial conformity is wanting the contract price does not limit the amount of the liability as to liens. (San Diego L. Co. v. Woolredge, 90 Cal. 574, 578, [27 Pac. 431] ; Willamette etc. Co. v. Los Angeles etc. Co., 94 Cal. 229, 234, [29 Pac. 629]; Merced L. Co. v. Bruschi, 152 Cal. 374, [92 Pac. 844] ; Burnett v. Glas, 154 Cal. 249, 256, [97 Pac. 423]; D. I. Nofziger L. Co. v. Solomon, 13 Cal. App. 621, 625, [110 Pac. 474].) The Hotel Company claims that this defect in the contract is not a lack of substantial conformity with section 1184. The argument is that inasmuch as the contract does not declare that the final one-fourth shall be paid prior to the expiration of the thirty-five days after completion, but is silent as to the time of such payment, it does not expressly violate the section, and that the law itself becomes a part of the contract, with the result that, by force of the statute, that installment would not be payable until thirty-five days after completion. We do not so understand the provision in question. The part of the section to which all contracts must substantially conform reads as follows:

“No part of the contract price shall, by the terms of any such contract, be made payable, nor shall the same or any part thereof be paid in advance of the commencement of the work, but the contract price shall, by the terms of the con *793 tract, be made payable in installments at specified times after the commencement of the work, or on the completion of specified portions of the work, or on the completion of the whole work; provided, that at least twenty-five per cent of the whole contract price shall be made payable at least thirty-five days after the final completion of the contract. ’ ’

This language is mandatory. It does not, as the argument assumes, declare the legal effect of such contract; it relates to the terms of the contracts and prescribes what such terms shall be; its declaration is, in effect, that such contracts must, by their terms, declare that at least twenty-five per cent of the contract price shall be “payable at least thirty-five days” after final completion. There is a reason for this requirement. The contract must be filed in the recorder’s office so that all laborers and other persons interested may see it and learn therefrom at first hand the time of payment. The purpose was to have it expressed on the face of the contract and not left to implication founded on principles of construction not universally understood. This purpose would be defeated if a failure to speak were held innocent on the theory proposed by the defendant. This contract contains an express agreement to pay the whole price, $199,500. By the general principles of law whatever of this sum remained unpaid on final completion would be immediately payable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tri-State Employment Services, Inc. v. Mountbatten Surety Co.
788 N.E.2d 1023 (New York Court of Appeals, 2003)
Contractors Labor Pool, Inc. v. Westway Contractors, Inc.
53 Cal. App. 4th 152 (California Court of Appeal, 1997)
Primo Team, Inc. v. Blake Construction Co.
3 Cal. App. 4th 801 (California Court of Appeal, 1992)
Rich-Lee Equipment Rentals, Inc. v. Intermountain Construction Co.
79 Cal. App. 3d 581 (California Court of Appeal, 1978)
Contractors Dump Truck Service, Inc. v. Gregg Construction Co.
237 Cal. App. 2d 1 (California Court of Appeal, 1965)
Calhoun v. Huntington Park First Savings & Loan Ass'n
186 Cal. App. 2d 451 (California Court of Appeal, 1960)
In re of Lightner
184 F. Supp. 825 (S.D. California, 1960)
Southern Coal Co. v. Martin's Fork Coal Co.
151 S.W.2d 394 (Court of Appeals of Kentucky (pre-1976), 1940)
Glassco v. El Sereno Country Club, Inc.
17 P.2d 703 (California Supreme Court, 1932)
Peoples National Bank v. Southern Surety Co.
288 P. 827 (California Court of Appeal, 1930)
Asnon v. Foley
288 P. 792 (California Court of Appeal, 1930)
Burr v. Peppers Cotton Lumber Co.
266 P. 1025 (California Court of Appeal, 1928)
Hirsh v. Ogden Furniture & Carpet Co.
172 P. 318 (Utah Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
164 P. 788, 174 Cal. 789, 1917 Cal. LEXIS 867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sweet-v-fresno-hotel-co-cal-1917.