Contractors Labor Pool, Inc. v. Westway Contractors, Inc.

53 Cal. App. 4th 152, 53 Cal. App. 2d 152, 61 Cal. Rptr. 2d 715, 97 Cal. Daily Op. Serv. 1600, 97 Daily Journal DAR 3038, 1997 Cal. App. LEXIS 157
CourtCalifornia Court of Appeal
DecidedFebruary 28, 1997
DocketB091490
StatusPublished
Cited by33 cases

This text of 53 Cal. App. 4th 152 (Contractors Labor Pool, Inc. v. Westway Contractors, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contractors Labor Pool, Inc. v. Westway Contractors, Inc., 53 Cal. App. 4th 152, 53 Cal. App. 2d 152, 61 Cal. Rptr. 2d 715, 97 Cal. Daily Op. Serv. 1600, 97 Daily Journal DAR 3038, 1997 Cal. App. LEXIS 157 (Cal. Ct. App. 1997).

Opinion

Opinion

CROSKEY, J.

Defendant, appellant and cross-respondent American Bonding Company (hereafter, ABC) appeals from a judgment of the superior court, in which, after a court trial, the court found in favor of plaintiff, respondent and cross-appellant, Contractors Labor Pool, Inc. (CLP) in CLP’s action against ABC and codefendants Westway Contractors, Inc., and its president. CLP’s complaint sought recovery of damages for breach of contract and common counts as well as recovery on a payment bond which had been furnished by ABC pursuant to Civil Code section 3248. CLP cross-appeals from a postjudgment order awarding it attorney fees under Civil Code section 3250. 1 CLP contends the award was so grossly inadequate as to constitute an abuse of discretion.

In the judgment, the court found Westway and its president liable to CLP for damages and also found CLP entitled to recover against ABC on the *156 bond. On a cross-complaint by ABC, the court found ABC entitled to indemnification from Westway. 2 In its postjudgment order awarding attorney fees and costs, the court awarded CLP a total of $12,543.17, including $7,965.49 in attorney fees. CLP had filed a motion for $43,151 in attorney fees for attorneys’ services prior to judgment and had later requested an additional $8,064 for its successful resistance of ABC’s motion for a new trial.

The trial court correctly found CLP to be a claimant entitled to recover against the payment bond. However, the court did not correctly assess the extent of its discretion to award attorney fees under section 3250. We therefore affirm the judgment and remand the matter for a redetermination of the amount of the attorney fee award.

Factual and Procedural Background

CLP is a California corporation in the business of furnishing skilled and unskilled temporary workers to licensed construction contractors. Defendant Westway is a contractor to whom CLP furnished workers for a public works project in which Westway was involved as a subcontractor. The general contractor was R.A. Francis, Inc. (Francis). ABC provided a $567,464 payment bond for the project.

In late 1991, the California Department of Transportation (Cal-Trans) awarded Francis a contract to construct the Vermont Street Station, a passenger station on the Green Line electric railway in Los Angeles County, California. Francis subcontracted with Westway for Westway to do structural concrete work on the station. Westway contracted with CLP for CLP to supply workers for the project. The contract between CLP and Westway was a printed form contract drafted by CLP and entitled “Contractors Labor Pool Labor Agreement.” It provided, among other things, that: (1) Westway would pay CLP an hourly rate for each hour a CLP employee (Special Employee) performed services for Westway; (2) CLP would be responsible for the Special Employees’ payroll taxes, workers’ compensation and other insurance premiums, federal and state withholding, and fringe benefits; (3) Westway would control the activities of the Special Employees while on the job; (4) Westway would indemnify CLP for damages to persons or property arising out of work performed or not performed by the Special Employees *157 and/or Westway in connection with the labor agreement; (5) Westway would provide CLP with all information needed to maintain CLP’s mechanic’s lien rights and would cooperate with CLP as reasonably requested in connection with filing such liens.

After the labor agreement was executed by CLP and Westway, Westway placed orders for workers, such as carpenters, laborers and superintendents, by calling CLP and making a verbal request. If a particular worker was not satisfactory to Westway, Westway had the right to send that worker back, and Westway directed, controlled and supervised the workers’ activities on the jobsite. CLP paid the workers’ wages and employment benefits, provided workers’ compensation insurance, and was responsible for the workers’ tax withholding. CLP invoiced Westway weekly, based on the actual hours worked by the Special Employees.

Westway eventually fell behind in paying CLP’s invoices, and by April of 1993, Westway owed CLP $170,495.47. When this amount remained unpaid, CLP ceased to provide workers to Westway and, in addition, filed the within action to recover the amounts owing. After a trial, the court found (1) Westway liable to CLP in the amount of $170,495.47, plus service charges, (2) Westway’s president liable to CLP in the amount of $50,000 plus interest, and (3) CLP entitled to recover $170,495.47, plus service charges against the payment bond furnished by ABC. A motion by ABC for a new trial was denied. This timely appeal followed.

Contentions

ABC contends that (1) CLP has no right to recover against the payment bond because it is not a claimant protected by section 3110; (2) alternatively, pursuant to Business and Professions Code section 7031, CLP has no right to any recovery under its contract with Westway, because if CLP is indeed a claimant protected by section 3110, then it necessarily was acting in the capacity of a contractor when its employees performed services on the work of improvement, and CLP had no contractor’s license when these services were performed. CLP disputes each of the above contentions and further argues that the court’s postjudgment order awarding attorney fees was so inadequate as to constitute an abuse of discretion.

Discussion

1. CLP, as a Furnisher of Labor, Was Entitled to Recover on the Payment Bond.

ABC contends CLP is not entitled to recover against the bond, because it is not entitled to a mechanic’s lien under section 3110. ABC cites *158 Primo Team, Inc. v. Blake Construction Co. (1992) 3 Cal.App.4th 801 [4 Cal.Rptr.2d 701] (hereafter, Primo Team) in support of its claim that CLP is not entitled to recover against the bond. Primo Team held that an employment services company which performed personnel and payroll services for a subcontractor on a public project, but was not actually the employer of the workers, was not entitled to recover against a performance bond. (Id. at p. 804.) ABC argues that “[F]or all meaningful purposes, the workers were really employed by Westway while they were on the jobsite because West-way in fact directed and controlled their activities.” Therefore, ABC argues that CLP was an employer of the workers in name only and, like the plaintiff in Primo Team, is consequently not entitled to recover on the performance bond.

We disagree. As a furnisher of labor contributing to the public work of improvement, CLP was a claimant protected by the mechanic’s lien law and was therefore entitled to recover against the payment bond. (Myers v. Alta Construction Co. (1951) 37 Cal.2d 739, 742 [235 P.2d 1]; Sweet v. Fresno Hotel Co. (1917) 174 Cal. 789, 797 [164 P 788]; Primo Team, supra, 3 Cal.App.4th at p. 807;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zale Design Studio v. Leevan CA2/1
California Court of Appeal, 2024
Rummell v. Lindsey CA4/1
California Court of Appeal, 2024
Lorch v. Super. Ct.
California Court of Appeal, 2024
People v. Tenerelli CA3
California Court of Appeal, 2022
In re Crescent Associates, LLC
C.D. California, 2021
Luzuriaga v. R.C. Berger Construction CA4/2
California Court of Appeal, 2021
Siry Investment v. Farkhondehpour
California Court of Appeal, 2020
Rustam v. Golditch CA2/3
California Court of Appeal, 2016
Cosco Fire Protection v. Siry Investments CA4/1
California Court of Appeal, 2015
Campbell v. Campbell CA4/3
California Court of Appeal, 2013
Enpalm, Lcc v. Teitler Family Trust
75 Cal. Rptr. 3d 902 (California Court of Appeal, 2008)
Cruz v. Ayromloo
66 Cal. Rptr. 3d 725 (California Court of Appeal, 2007)
Thompson Pacific Construction Inc. v. City of Sunnyvale
66 Cal. Rptr. 3d 175 (California Court of Appeal, 2007)
Fergus v. Songer
59 Cal. Rptr. 3d 273 (California Court of Appeal, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
53 Cal. App. 4th 152, 53 Cal. App. 2d 152, 61 Cal. Rptr. 2d 715, 97 Cal. Daily Op. Serv. 1600, 97 Daily Journal DAR 3038, 1997 Cal. App. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contractors-labor-pool-inc-v-westway-contractors-inc-calctapp-1997.