Luzuriaga v. R.C. Berger Construction CA4/2

California Court of Appeal·Decided February 23, 2021·No. E072526·Unpublished

Opinion

Filed 2/23/21 Luzuriaga v. R.C. Berger Construction CA4/2

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA FOURTH APPELLATE DISTRICT DIVISION TWO

DEBORAH LUZURIAGA, Plaintiff and Appellant, E072526 v. (Super.Ct.No. RIC1602017)

R.C. BERGER CONSTRUCTION, INC. et OPINION al.,

Defendants and Respondents.

APPEAL from the Superior Court of Riverside County. Raquel A. Marquez and Angel M. Bermudez, Judges.* Affirmed.

Law Offices of Jonathan C. Stevens and Jonathan C. Stevens for Plaintiff and Appellant.

* Judge Marquez ruled on the motions for summary judgment/summary adjudication, although Judge Bermudez signed the formal order on those motions. Judge Bermudez also denied the motion for leave to amend and entered judgment.

The Mouzis Law Firm, Gerald W. Mouzis, and Amanda L. Voivedich for Defendants and Respondents R.C. Berger Construction, Inc., Carla Berger, and Ronald Berger.

Richard A. Nervig for Defendant and Respondent Gary Cuellar.

Deborah Luzuriaga sought to construct a veterinary hospital on property that she owned in Wildomar. Mechanic’s liens against the property started to mount up, and she came to believe that the general contractor (not a party to this action) had embezzled construction funds. She fired the general contractor and took over management of the project herself. Needless to say, litigation ensued, on several fronts. This is not even the first time that some of that litigation has come before this court. (See Precision Framing Systems Inc. v. Luzuriaga (2019) 39 Cal.App.5th 457, 459.)

In this particular action, Luzuriaga sued the grading subcontractor, along with various other individuals and entities that were also involved in the grading. She alleges that the grading was not done in accordance with the plans and specifications. As a result, she had to pay to have it partially redone; moreover, she incurred additional expenses to obtain the release of a mechanic’s lien. She also alleges that some of the defendants carried out grading work without being licensed to do so, and that some of the defendants claimed a mechanic’s lien without being legally entitled to do so.

The grading subcontractor defaulted. Its owner declared bankruptcy. The trial court granted summary judgment in favor of all the other defendants. It ruled that they were not required to have contractor’s licenses. It also ruled that they were not negligent

because they did not owe Luzuriaga a duty of care. Finally, it ruled that Luzuriaga had failed to plead her theory that one of the defendants improperly claimed a mechanic’s lien because it acted only as a go-between and thus did not provide work for the work of improvement. It denied Luzuriaga’s motion for leave to amend to plead this theory.

Luzuriaga appeals. We will uphold the trial court on all points. Hence, we will affirm.

I

STATEMENT OF FACTS

We consider all of the evidence set forth in the papers, except evidence to which the trial court sustained an objection. (Code Civ. Proc., § 437c, subd. (c).) Moreover, because the evidence in support of the three motions was generally consistent, and because it appears that the trial court considered all three motions together, we consider the evidence offered in connection with all three motions collectively.

A. Grading Work.

Luzuriaga and her husband own a piece of property in Wildomar. She undertook to develop it as a veterinary hospital.

She hired a general contractor. The contract between them was an American Institute of Architects (AIA) standard form construction contract. It incorporated the plans and specifications. It provided that the contractor must require each subcontractor to be bound by the plans and specifications. It also provided that a subcontractor must require each sub-subcontractor to be bound by the plans and specifications, “[w]here

appropriate.” It defined a “sub-subcontractor” as “a person or entity who has a direct or indirect contract with a Subcontractor to perform a portion of the Work at the site.”

1. July 2013 grading work.

In July 2013, the general contractor hired B&T Works, Inc. (B&T) as a grading subcontractor. The contract between them required B&T’s work to conform to the plans and specifications.

Giovanni Nanci, the owner of B&T, testified that it was “exclusively” the duty of B&T to ensure that the grading work was done in accordance with the plans and specifications and within the standard of care.

B&T had a contractor’s license; however, its license was suspended from July 17, 2013, through August 22, 2013.

B&T, in turn, entered into a contract with R.C. Berger Construction, Inc., dba RC Grading (RC) (owned by Ronald and Carla Berger). RC did not have a contractor’s license at all.

According to Carla Berger, RC is an equipment broker; it rents out equipment, with or without an operator, to construction projects. It may or may not own the equipment. Its contract with B&T merely required it to provide equipment and an operator, which would not require a contractor’s license. According to Luzuriaga, however, the contract required RC to do grading work, which would require a contractor’s license.

RC carried out grading work between July 17 and July 22, 2013; it billed B&T, on an hourly basis, a total of $3,759. The work was done by Ronald Berger, using a skip loader that RC did not own, but rather leased from one L. Moreno.

Ronald Berger worked under the supervision and control of B&T; RC never reviewed the plans and specifications for the project.

RC received full payment for its work in June.

2. December 2013 grading work.

In October 2013, the general contractor rehired B&T to do additional grading work. By this time, B&T was properly licensed.

Once again, B&T entered into a contract with RC. RC, in turn, contracted with Gary Cuellar, dba Cuellar Grading & Excavation. Cuellar was a licensed grading contractor. He did the work using a skip loader that he owned. He worked under the supervision and control of B&T. He did exactly what the B&T foreman told him to do. He never reviewed the plans and specifications for the project.

Cuellar carried out grading work between December 11 and 16, 2013, for which he billed RC, on an hourly basis, a total of $2,852. RC turned around and billed B&T $3,850. RC, and thus Cuellar, were never paid for the December work.

On January 30, 2014, Luzuriaga fired the general contractor. She then assumed control of the project.

On June 19, 2014, RC recorded a mechanic’s lien against the property. Luzuriaga obtained a release of the lien by filing a bond, issued by American Contractors Indemnity Company (American).

Luzuriaga hired a different grading subcontractor to complete the project.

Meanwhile, she discovered that the grading work already done, first by Ronald Berger and then by Cuellar, was not in conformance with the plans and specifications. It cost her $22,657.88 to correct their nonconforming work.

B. The Prior Action.

In September 2014, RC filed an action against American to recover against the bond. As the bond required, Luzuriaga provided American with a defense.

RC was seeking the $3,850 that it had billed for the December work. On the eve of trial, American and RC settled for $2,500. On behalf of American, Luzuriaga paid RC this amount. RC then paid Cuellar $1,000. Luzuriaga also incurred attorney fees and costs.

II

STATEMENT OF THE CASE

Luzuriaga filed this action in 2016. The operative (second amended) complaint named B&T (along with Giovanni Nanci), RC (along with Ronald and Carla Berger),1 and Cuellar as defendants. It asserted causes of action for:

Free access — add to your briefcase to read the full text and ask questions with AI

Luzuriaga v. R.C. Berger Construction CA4/2, (Cal. Ct. App. 2021).

Luzuriaga v. R.C. Berger Construction CA4/2 (Luzuriaga v. R.C. Berger Construction CA4/2) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Erlich v. Menezes
981 P.2d 978 (California Supreme Court, 1999)
Stewart v. Cox
362 P.2d 345 (California Supreme Court, 1961)
Biakanja v. Irving
320 P.2d 16 (California Supreme Court, 1958)
Lewis & Queen v. N. M. Ball Sons
308 P.2d 713 (California Supreme Court, 1957)
Bily v. Arthur Young & Co.
834 P.2d 745 (California Supreme Court, 1992)
Andrew v. Conner
225 P.2d 943 (California Court of Appeal, 1951)
Rowland v. Christian
443 P.2d 561 (California Supreme Court, 1968)
Frisvold v. Leahy
60 P.2d 151 (California Court of Appeal, 1936)
Roemer v. Retail Credit Co.
44 Cal. App. 3d 926 (California Court of Appeal, 1975)
Rodoni v. Harbor Engineers
191 Cal. App. 2d 560 (California Court of Appeal, 1961)
Contractors Dump Truck Service, Inc. v. Gregg Construction Co.
237 Cal. App. 2d 1 (California Court of Appeal, 1965)
Dahl-Beck Electric Co. v. Rogge
275 Cal. App. 2d 893 (California Court of Appeal, 1969)
Weseloh Family Ltd. Partnership v. K.L. Wessel Construction Co.
22 Cal. Rptr. 3d 660 (California Court of Appeal, 2004)
Lowe v. California League of Professional Baseball
56 Cal. App. 4th 112 (California Court of Appeal, 1997)
Bostrom v. County of San Bernardino
35 Cal. App. 4th 1654 (California Court of Appeal, 1995)
Laabs v. City of Victorville
163 Cal. App. 4th 1242 (California Court of Appeal, 2008)
Sanchez v. Swinerton & Walberg Co.
47 Cal. App. 4th 1461 (California Court of Appeal, 1996)
Contractors Labor Pool, Inc. v. Westway Contractors, Inc.
53 Cal. App. 4th 152 (California Court of Appeal, 1997)
Oakland Raiders v. National Football League
32 Cal. Rptr. 3d 266 (California Court of Appeal, 2005)
Stonegate Homeowners Ass'n v. Staben
50 Cal. Rptr. 3d 709 (California Court of Appeal, 2006)