Weseloh Family Ltd. Partnership v. K.L. Wessel Construction Co.

22 Cal. Rptr. 3d 660, 125 Cal. App. 4th 152, 2004 Daily Journal DAR 15150, 2004 Cal. Daily Op. Serv. 11242, 2004 Cal. App. LEXIS 2195
CourtCalifornia Court of Appeal
DecidedDecember 21, 2004
DocketG032874
StatusPublished
Cited by14 cases

This text of 22 Cal. Rptr. 3d 660 (Weseloh Family Ltd. Partnership v. K.L. Wessel Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weseloh Family Ltd. Partnership v. K.L. Wessel Construction Co., 22 Cal. Rptr. 3d 660, 125 Cal. App. 4th 152, 2004 Daily Journal DAR 15150, 2004 Cal. Daily Op. Serv. 11242, 2004 Cal. App. LEXIS 2195 (Cal. Ct. App. 2004).

Opinion

Opinion

FYBEL, J.

INTRODUCTION

Design engineers designed retaining walls for an automobile dealership project. They contracted with the builder of the walls. After a portion of the retaining walls failed and the project suffered damage, the property owner sued the design engineers for negligence. The general contractor sued the design engineers for negligence and equitable indemnity. The trial court granted motions for summary judgment on the ground the design engineers did not owe a duty of care to the property owner or the general contractor. We affirm.

We apply the burden-shifting standards of Code of Civil Procedure section 437c, subdivision (p)(2), and conclude the design engineers met their *159 initial burden of showing no duty of care existed. The burden then shifted to the property owner and the general contractor to produce evidence showing the existence of a duty or a triable issue of material fact relevant to determining whether a duty existed. The property owner and the general contractor failed to carry this burden, considering the factors set forth in Biakanja v. Irving (1958) 49 Cal.2d 647 [320 P.2d 16] (Biakanja) and Bily v. Arthur Young & Co. (1992) 3 Cal.4th 370 [11 Cal.Rptr.2d 51, 834 P.2d 745] (Bily). Therefore, the design engineers did not owe the property owner or the general contractor a duty of care in this case.

Because the design engineers did not owe such a duty to the property owner, the general contractor’s claim for equitable indemnity also fails. (BFGC Architects Planners, Inc. v. Forcum/Mackey Construction, Inc. (2004) 119 Cal.App.4th 848 [14 Cal.Rptr.3d 721].)

SUMMARY OF UNDISPUTED FACTS 1

Weseloh Family Limited Partnership (Weseloh) owns property in San Juan Capistrano (the property) which is leased by Weseloh & Sons, LLC, and Weseloh Corporation. (All three entities are collectively referred to as the Weseloh plaintiffs.)

On May 10, 1999, the Weseloh plaintiffs contracted with a general contractor, K.L. Wessel Construction Co., Inc. (Wessel), to construct automobile dealership facilities on the property (the project). Subcontractor Sierra Pacific Earth Retention Corporation (Sierra), which has done business under the name Retaining Wall Company North, built the retaining walls for the project. Charles Randle performed consulting work on the project for Sierra and “ ‘supervised the design work of the design engineers that worked on the Weseloh project at all times.’ ” Randle, who was employed by Owen Engineering Company (Owen) during unspecified time periods, was paid $1,500 or $2,200 for his design of two Keystone walls. Randle was aware that Weseloh owned the property.

Neither Randle nor Owen ever (1) contracted with the Weseloh plaintiffs or Wessel to construct the retaining walls; (2) contracted with the Weseloh plaintiffs or Wessel to prepare any design, engineering, planning, and/or review of construction, grading, manufacture and/or installation of the property or any improvements; or (3) had a role in the construction of the *160 retaining walls. At Sierra’s request, both Randle and Owen inspected the retaining walls following construction. On February 12, 2001, a portion of the retaining walls failed.

PROCEDURAL BACKGROUND

The Weseloh plaintiffs sued Wessel, Sierra, Compaction Plus, Inc., Soils Southwest, Inc., Owen, and Randle. The second amended complaint alleged a claim against Soils Southwest, Owen, and Randle for professional negligence. The Weseloh plaintiffs alleged that Soils Southwest, Owen, and Randle “breached their respective duties of care to Plaintiffs by negligently and carelessly failing to use the care required of their respective professions in the design, planning, engineering and/or review of the construction, grading, manufacture and/or installation of the earth retention system of retaining walls on the SUBJECT PROPERTY and failed to comply with acceptable and applicable design standards, codes and relevant professional engineering customs and practices for the design of earth retention systems or retaining walls, as evidenced by the failure of such earth retention system or retaining wall designed by the Defendants as alleged herein.”

The Weseloh plaintiffs further alleged, “[a]s a result of the negligence of said Defendants, and each of them, as aforesaid, as manifested by the failure of the design and construction of the earth retention system, the SUBJECT PROPERTY and improvements thereon have sustained severe physical and structural property damage, and Plaintiffs are informed and believe and based thereon allege that additional damage to the SUBJECT PROPERTY may continue to occur and may be discovered from time to time in the future.” The Weseloh plaintiffs also alleged, “as a result and proximate cause of the negligence of Defendants SOILS SOUTHWEST, OWEN, RANDLE and DOES 51 THROUGH 90, as described herein, Plaintiffs have sustained and will sustain monetary damages in an amount not less than $6,000,000.”

Wessel’s second amended cross-complaint contained claims for equitable indemnity, total indemnity, contribution, and professional negligence against Randle and Owen. 2 With regard to its professional negligence claim, Wessel alleged it had “sustained and will sustain monetary damages including, but not limited to, litigation costs, contractor’s fees, attorney’s fees and consultants’ fees to inspect, repair and mitigate damages arising out of said negligent design, construction, repair and maintenance and to defend against [the Weseloh plaintiffs’] action herein.”

*161 In October 2002, the Weseloh plaintiffs, Wessel, and Sierra entered into a settlement agreement.

In April 2003, Randle and Owen filed motions for summary judgment on the Weseloh plaintiffs’ second amended complaint and Wessel’s second amended cross-complaint on the following common grounds: (1) Randle and Owen could not be liable to the Weseloh plaintiffs or Wessel for negligence because Randle and Owen had no contractual relationship with the Weseloh plaintiffs or Wessel, and there was no basis to recognize a duty of care; (2) no evidence supported the claim Randle or Owen caused the failure of the retaining walls; and (3) the Weseloh plaintiffs and Wessel released Randle and Owen as part of the release of Sierra in the settlement agreement. Randle and Owen’s motion for summary judgment against Wessel included the additional ground there was no basis for a claim of indemnity.

The trial court granted Randle and Owen’s motions for summary judgment. The order granting summary judgment against the Weseloh plaintiffs stated in relevant part: “After consideration of all of the moving and opposing evidence, the Court concludes that the defendants Owen Engineering Group and Charles J. Randle did not owe a duty to the plaintiffs as a matter of law. The analysis of the moving parties as to the [Biakanja] (1958) 49 Cal.2d 647 and [Bily]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lynch v. Peter & Associates etc.
California Court of Appeal, 2024
Lynch v. Peter & Associates etc. CA4/3
California Court of Appeal, 2024
Luzuriaga v. R.C. Berger Construction CA4/2
California Court of Appeal, 2021
In re TIBCO Software Inc. Stockholders Litigation
Court of Chancery of Delaware, 2015
State Ready Mix, Inc. v. Moffatt & Nichol
232 Cal. App. 4th 1227 (California Court of Appeal, 2015)
Burch v. Superior Court
223 Cal. App. 4th 1411 (California Court of Appeal, 2014)
Ponce v. Philco Construction CA4/3
California Court of Appeal, 2014
Philadelphia Indemnity Insurance v. SimplexGrinnell LP
937 F. Supp. 2d 1113 (N.D. California, 2013)
Shin v. Ahn
46 Cal. Rptr. 3d 271 (California Court of Appeal, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
22 Cal. Rptr. 3d 660, 125 Cal. App. 4th 152, 2004 Daily Journal DAR 15150, 2004 Cal. Daily Op. Serv. 11242, 2004 Cal. App. LEXIS 2195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weseloh-family-ltd-partnership-v-kl-wessel-construction-co-calctapp-2004.