State Ready Mix, Inc. v. Moffatt & Nichol

232 Cal. App. 4th 1227, 181 Cal. Rptr. 3d 921, 2015 Cal. App. LEXIS 11
CourtCalifornia Court of Appeal
DecidedJanuary 8, 2015
DocketB253421
StatusPublished
Cited by10 cases

This text of 232 Cal. App. 4th 1227 (State Ready Mix, Inc. v. Moffatt & Nichol) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ready Mix, Inc. v. Moffatt & Nichol, 232 Cal. App. 4th 1227, 181 Cal. Rptr. 3d 921, 2015 Cal. App. LEXIS 11 (Cal. Ct. App. 2015).

Opinion

Opinion

YEGAN, J.

Mixing concrete, like baking a cake, is fraught with problems when the recipe is not followed. Here, concrete supplier, State Ready Mix, Inc. (State), wrote the concrete mix design (the recipe) and prepared a bad batch of concrete that was used to construct a harbor pier. State blames the bad concrete on the civil engineer who drafted the pier plans and helped the general contractor by gratuitously reviewing State’s concrete mix design. In the words of Clare Boothe Luce, “No good deed goes unpunished.” (See Wright v. Beverly Fabrics, Inc. (2002) 95 Cal.App.4th 346, 348 [115 Cal.Rptr.2d 503].)

*1230 When State was sued to recoup the cost of replacing the concrete, it filed a cross-complaint for equitable indemnity and contribution against the civil engineer, Moffatt & Nichol (Moffatt). The trial court sustained, without leave to amend, Moffatt’s demurrer to the second amended cross-complaint. State appeals. We affirm and conclude the cross-complaint is barred by the economic loss rule. (Aas v. Superior Court (2000) 24 Cal.4th 627, 643 [101 Cal.Rptr.2d 718, 12 P.3d 1125].) State cannot seek equitable indemnity or contribution for damages caused by the breach of its own contract. (Stop Loss Ins. Brokers, Inc. v. Brown & Toland Medical Group (2006) 143 Cal.App.4th 1036, 1041-1044 [49 Cal.Rptr.3d 609] (Stop Loss).)

Facts and Procedural History

In 2012, Bellingham Marine, Inc. (Bellingham), a marine project manager, hired Major Engineering Marine, Inc. (Major), to construct a travel lift pier at the Channel Islands Harbor. Bellingham hired Moffatt, a civil engineering firm, to prepare the plans for the pier. The plans required that the concrete have an air entrainment of 2 to 4 percent and that the concrete, when cured, attain a compressive strength of 5,000 PSI in 28 days. Major’s contract with Bellingham provided that if the concrete failed to meet the 5,000 PSI compression strength standard, it would be removed and replaced at Major’s expense.

After Major hired State to supply the concrete, State submitted a concrete mix design (Mix Design SR50RD) stating that Micro Air (an air-entrainment chemical) would be added to each batch of concrete. 1 Moffatt, at the request of Major, reviewed and approved Mix Design SR50RD. It was not part of Moffatt’s job duties.

On February 14, 2012, State delivered seven truckloads of wet premixed concrete to the project site. After the concrete was cast, Major’s testing lab took a sample that showed the concrete had a compressive strength of only 3,650 PSI at 28 days.

Major asked State to investigate. In a March 9, 2012 e-mail, State’s technical advisor reported: “The day of the pour, 2-14-2012, State Ready Mix encountered a mechanical failure in their chemical dispensing equipment and had to manually add the ‘Air Entrainment’ chemical into the trucks. There was an error in the calculations and the chemical was over dosed. This is the *1231 reason for the lower compressive strengths.” 2 Major determined that the Micro Air admixture was 6.5 times greater than the amount necessary to attain the air entrainment specified in the plans.

Major demolished and rebuilt the affected portion of the pier. It sued for the money spent to remove and replace the defective concrete based on contract and warranty theories. State filed a cross-complaint for implied equitable indemnity and contribution, alleging that Moffatt failed to use reasonable care in reviewing and approving Mix Design SR50RD. After three pleading attempts, the trial court sustained Moffatt’s demurrer without leave to amend because Moffatt was not in privity of contract with Major or State and because the cross-complaint was barred by the economic loss rule.

Indemnification

The trial court correctly ruled that State could not sue for equitable indemnity or contribution. No facts are alleged that Moffatt owed State “a duty of care sounding in tort.” (Stop Loss, supra, 143 Cal.App.4th at p. 1041.) Nor can State sue for equitable indemnification based on the theory that Moffatt negligently performed its contract with Bellingham. (Id., at pp. 1042-1043.) “[C]onduct amounting to a breach of contract becomes tortious only when it also violates a duty independent of the contract arising from principles of tort law. [Citation.] ‘ “ ‘An omission to perform a contract obligation is never a tort, unless that omission is also an omission of a legal duty.’ ” ’ [Citation.]” (Erlich v. Menezes (1999) 21 Cal.4th 543, 551 [87 Cal.Rptr.2d 886, 981 P.2d 978], italics added.)

In BFGC Architects Planners, Inc. v. Forcum/Mackey Construction, Inc. (2004) 119 Cal.App.4th 848 [14 Cal.Rptr.3d 721], the project owner (a school district) sued its architect for breach of contract and professional negligence that caused $4 million in extra project costs. The architect filed a cross-complaint for equitable indemnity against the general contractors, alleging that they negligently failed to comply with the terms of their contracts with the school district. The Court of Appeal held that no cognizable claim for equitable indemnity was stated. “The only allegations of defendants’ misconduct are based on their alleged breach of contract .... This is an improper *1232 attempt to recast a breach of contract cause of action as a tort claim. Nor is there any social policy that would demand resort to tort remedies. Without any action sounding in tort, there is no basis for a finding of potential joint and several liability on the part of defendants, thereby precluding a claim for equitable indemnity.” (Id., at p. 853.)

The same principle applies here. State cannot recast Major’s complaint for breach of contract/breach of warranty as a tort action. “A person may not ordinarily recover in tort for the breach of duties that merely restate contractual obligations.” (Aas v. Superior Court, supra, 24 Cal.4th at p. 643 (Aas).) In Aas, homeowners sued the developer, contractor, and subcontractors in negligence for construction defects that caused no property damage. Our Supreme Court held that the economic loss rule precludes recovery for damages such as “the difference between price paid and value received, and deviations from standards of quality that have not resulted in property damage or personal injury.” (Id., at p. 636.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mosler v. Gerace
Supreme Court of The Virgin Islands, 2024
Luzuriaga v. R.C. Berger Construction CA4/2
California Court of Appeal, 2021
Lichtman v. Siemens Industry Inc.
California Court of Appeal, 2017
Lichtman v. Siemens Indus. Inc.
224 Cal. Rptr. 3d 725 (California Court of Appeals, 5th District, 2017)
Banayan v. Onewest Bank, F.S.B. CA4/1
California Court of Appeal, 2015

Cite This Page — Counsel Stack

Bluebook (online)
232 Cal. App. 4th 1227, 181 Cal. Rptr. 3d 921, 2015 Cal. App. LEXIS 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ready-mix-inc-v-moffatt-nichol-calctapp-2015.