Ratcliff Architects v. Vanir Construction Management, Inc.

106 Cal. Rptr. 2d 1, 88 Cal. App. 4th 595, 2001 Daily Journal DAR 3845, 2001 Cal. Daily Op. Serv. 3137, 2001 Cal. App. LEXIS 290
CourtCalifornia Court of Appeal
DecidedMarch 23, 2001
DocketA089533
StatusPublished
Cited by33 cases

This text of 106 Cal. Rptr. 2d 1 (Ratcliff Architects v. Vanir Construction Management, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ratcliff Architects v. Vanir Construction Management, Inc., 106 Cal. Rptr. 2d 1, 88 Cal. App. 4th 595, 2001 Daily Journal DAR 3845, 2001 Cal. Daily Op. Serv. 3137, 2001 Cal. App. LEXIS 290 (Cal. Ct. App. 2001).

Opinion

Opinion

LAMBDEN, J.

The trial court sustained demurrers by Vanir Construction Management, Inc. (Vanir) and Don Todd Associates, Inc. (Todd) without leave to amend against the cross-complaint filed by The Ratcliff Architects (Ratcliff). The court found that Ratcliff did not have legal standing to sue, and we agree.

Background

In March 1994, the Berkeley Unified School District (BUSD) retained Ratcliff to provide architectural services for the rebuilding of BUSD’s *599 Columbus Elementary School project (school project). In a contract signed in August 1995 (contract), BUSD retained Vanir and Todd to be the construction manager of the school project.

The contract contained a number of indemnification clauses. One such clause, paragraph 8.2, is relevant to the issues raised by this appeal. This provision provided the following: “Construction Manager shall indemnify and save harmless BUSD, and its officers, agents, representatives, and employees from and against any and all loss, cost, damage, expense, liability, and claims including attorneys’ fees or consultant’s costs thereof, for solely economic loss arising out of or connected to the Facilities Construction Plan and the individual Projects comprising the Plan (as those terms are defined in Appendix ‘A’), including but not limited to contractor claims, architect claims, engineer claims, neighborhood claims, or claims from any other party, entity or person, resulting directly or indirectly from Construction Manager’s performance of this Agreement, to the extent of Construction-Manager’s fault, negligence or failure to perform this Agreement caused, contributed to or resulted in the loss, cost, damage, injury, liability or claim.”

The contract also contained two other provisions critical to the issues raised by this appeal. Paragraph 10.7 specified, “Nothing in this Agreement shall operate to confer rights or benefits on persons or entities not party to this Agreement.” Near the end of the contract, paragraph 26.4 stated, “This Agreement shall not create any rights in persons not party to this Agreement, whether third party beneficiary, or otherwise.”

In 1998, BUSD sued Ratcliff, Vanir, and Todd, alleging that each had contributed to a cost overrun of more than $1,934,000 on the school project. Vanir and Todd settled with BUSD for $215,000 and an additional $75,000 credit to BUSD for “future construction management services” on other projects. The settlement contained a provision releasing and dismissing all of BUSD’s claims against Vanir and Todd regarding the school project.

BUSD applied for a judicial determination that it had settled with Vanir and Todd in good faith. Over Ratcliff’s opposition and after a hearing, the trial court found that the settlement was made in good faith pursuant to Code of Civil Procedure, section 877.6. 1

Ratcliff filed a cross-complaint against BUSD, Vanir, and Todd, for among other things, breach of contract and indemnity. Vanir and Todd *600 demurred, and the trial court sustained the demurrers with leave to amend against the claims for express contractual indemnity, breach of written contract by third party beneficiary, and declaratory relief. The court sustained without leave to amend the demurrers against the claim for contribution and/or comparative equitable indemnity and apportionment of fault.

Ratcliff filed an amended cross-complaint for express contractual indemnity (fourth cause of action), breach of written contract by third party beneficiary (fifth cause of action), negligence (sixth cause of action), and declaratory relief (seventh cause of action) against Vanir and Todd. 2 Vanir and Todd again demurred, and on November 12, 1999, the trial court sustained the demurrers without leave to amend.

Ratcliff filed a notice of appeal on December 21, 1999. On February 7, 2000, the trial court entered a judgment of dismissal on Ratcliff’s cross-complaint against Vanir and Todd.

Discussion

I. Appeal from Nonappealable Order *

II. Standard of Review

The trial court sustained without leave to amend Vanir and Todd’s demurrers to Ratcliff’s first amended complaint. When considering an appeal from a demurrer, we accept the facts pleaded as true. (American Philatelic Soc. v. Claibourne (1935) 3 Cal.2d 689, 699 [46 P.2d 135].) The trial court erred if the pleading states a cause of action under any possible legal theory; it abused its discretion if the face of the pleadings shows a reasonable probability the defects could be cured by a properly amended pleading. (Services by Medallion, Inc. v. Clorox Co. (1996) 44 Cal.App.4th 1807, 1812 [52 Cal.Rptr.2d 650]; Gami v. Mullikin Medical Center (1993) 18 Cal.App.4th 870, 877 [22 Cal.Rptr.2d 819].) We conclude that the trial court neither erred nor abused its discretion.

III. Demurrers

A. Contract Clauses of Action

Ratcliff contends that the trial court erred in sustaining demurrers to its claims for express contractual indemnity (fourth cause of action) and *601 breach of written contract by third party beneficiary (fifth cause of action). It claims that the contract between BUSD and Vanir and Todd required Vanir and Todd to indemnify Ratcliff. Specifically, Ratcliff asserts that it was an agent of BUSD (see Barron Estate Co. v. Woodruff Co. (1912) 163 Cal. 561, 575 [126 P. 351] [architect is owner’s agent]), and paragraph 8.2 of the contract between BUSD and Vanir and Todd provided that the latter “shall indemnify and save harmless BUSD, and its . . . agents . . . from and against any and all loss . . . arising out of or connected to [the construction of the school project].” 4

Vanir and Todd assert that the above clause did not provide Ratcliff with the right to indemnification because paragraphs 10.7 and 26.4 make it clear that only BUSD had the right to enforce any right under the contract. Paragraph 10.7 specified that the agreement did not confer rights on anyone who was not a party to the contract and paragraph 26.4 reiterated that the agreement did not create any rights in a nonparty to the agreement, including third party beneficiaries. Ratcliff was not a party to the agreement between BUSD and Vanir and Todd.

In interpreting the provisions of a contract, the rules are well settled. “The whole of a contract is to be taken together, so as to give effect to every part, if reasonably practicable, each clause helping to interpret the other.” *602 (Civ. Code, § 1641; see also City of Atascadero v. Merrill Lynch, Pierce, Fenner & Smith, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alarcon v. The Avalon Management Group CA2/3
California Court of Appeal, 2026
Dorian v. San Jose Towers CA6
California Court of Appeal, 2025
Ourfali v. 21st Century Ins. Co. CA2/4
California Court of Appeal, 2024
Rezapour v. U.S. Bank Nat. Assn. CA1/3
California Court of Appeal, 2021
Sugarman Family Partners v. Banc of Cal. CA4/3
California Court of Appeal, 2021
Storm v. The Standard Fire Ins. Co.
California Court of Appeal, 2020
McHenry v. Asylum Entertainment Delaware, LLC
California Court of Appeal, 2020
(PS) Devore v. CDCR
E.D. California, 2019
Goonewardene v. ADP, LLC
California Supreme Court, 2019
Eith v. Ketelhut
California Court of Appeal, 2019
Eith v. Ketelhut
242 Cal. Rptr. 3d 566 (California Court of Appeals, 5th District, 2018)
Lathan Co. v. State
237 So. 3d 1 (Louisiana Court of Appeal, 2017)
Kalnoki v. First American Trustee Servicing Solutions, LLC
8 Cal. App. 5th 23 (California Court of Appeal, 2017)
Goonewardene v. ADP
California Court of Appeal, 2016
Goonewardene v. ADP, LLC
5 Cal. App. 5th 154 (California Court of Appeal, 2016)
Mehr v. Féderation Internationale de Football Ass'n
115 F. Supp. 3d 1035 (N.D. California, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
106 Cal. Rptr. 2d 1, 88 Cal. App. 4th 595, 2001 Daily Journal DAR 3845, 2001 Cal. Daily Op. Serv. 3137, 2001 Cal. App. LEXIS 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ratcliff-architects-v-vanir-construction-management-inc-calctapp-2001.