Reliance National Indemnity Co. v. Advance'd Temporaries, Inc.

227 S.W.3d 46, 50 Tex. Sup. Ct. J. 858, 2007 Tex. LEXIS 529, 2007 WL 1650681
CourtTexas Supreme Court
DecidedJune 8, 2007
Docket05-0558
StatusPublished
Cited by53 cases

This text of 227 S.W.3d 46 (Reliance National Indemnity Co. v. Advance'd Temporaries, Inc.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance National Indemnity Co. v. Advance'd Temporaries, Inc., 227 S.W.3d 46, 50 Tex. Sup. Ct. J. 858, 2007 Tex. LEXIS 529, 2007 WL 1650681 (Tex. 2007).

Opinion

*47 Justice MEDINA

delivered the opinion of the Court.

In this case, we decide whether a temporary employment agency, which places workers at a construction project under a contract with a subcontractor, “furnishes labor” within the meaning of Chapter 53 of the Texas Property Code, thus qualifying for a mechanic’s lien. The trial court denied the temporary agency’s lien, concluding that it had not “furnish[ed] labor” within the statute’s meaning. See Tex. PROp.Code § 53.021 The court of appeals, however, reversed the trial court’s judgment and remanded the case for further proceedings. 165 S.W.3d 1. Although we do not agree with the court of appeals’ analysis in all respects, we do agree that the temporary employment agency furnished labor within the statute’s meaning and therefore affirm.

I

L & T, J.V. (“Lamar”) agreed to serve as general contractor during construction of the Corpus Christi Crosswinds Apartments and obtained a performance bond as its contract with the project’s owner required. Thereafter, Lamar subcontracted with Cesar Gonzalez, doing business as Gonzalez Construction, who agreed to frame, drywall, and roof the apartment project. Gonzalez, however, did not have an adequate work force for the job, and therefore sought additional workers from Advance’d Temporaries, Inc.

The agreement between Gonzalez and Advance’d identified these temporary workers as Advance’d’s employees and obligated Advance’d to obtain workers’ compensation and general liability insurance for them. Advance’d further offered a limited guarantee of its employees’ work. Advance’d agreed to promptly replace any temporary worker, upon notification within the first two hours of work, if Gonzalez was not satisfied with the worker’s performance. The contract further provided that temporary workers were not to operate machinery, automotive equipment, or work on ladders or scaffolds without Advance’d’s prior written approval. Finally, Gonzalez agreed to pay Advance’d $2500 in liquidated damages if he hired any temporary worker within three months of the agreement.

Advance’d recruited and supplied more than 100 workers for Gonzalez, qualified the legal status of each worker, and completed the necessary paper work and insurance requirements. Advance’d also paid the temporary workers and their payroll taxes, invoicing Gonzalez weekly for its services. This relationship was only a few months old when Lamar abruptly terminated Gonzalez’s work.

Lamar apparently paid Gonzalez all that was owed for his work, but Gonzalez failed to pay the full amount owed to Advance’d. Advance’d nevertheless took care of the temporary workers, paying them for their labor. Advance’d then gave notice of its claim under the mechanic’s hen statute, which Lamar disputed. Advance’d thereupon filed an affidavit claiming a mechanic’s hen. Advance’d sued Gonzalez for the balance owed under its contract after it was unable to cohect from Gonzalez’s or Lamar’s surety bond. The Crosswinds Apartments, Lamar, and the surety were also joined in the litigation.

Following a bench trial, the judge rendered judgment against Gonzalez, but denied Advance’d recovery against the other parties. The judge concluded that Advance’d was not entitled to recover against Lamar’s surety bond because Advance’d had not furnished labor as the mechanic’s statute requires, but had simply extended credit to Gonzalez for its payroll.

*48 Advance’d appealed, complaining that it had furnished labor at the Crosswinds project under a contract with a subcontractor and was thus entitled to the benefits of the mechanic’s lien statute, including a judgment against the general contractor’s bond. The court of appeals agreed, reversed the trial court’s judgment, and remanded the case for the trial court to determine the remaining issues regarding the validity and amount of Advance’d’s claim. 165 S.W.3d 1.

II

Lamar and its surety, Reliance National Indemnity Co. (hereafter “Reliance”), appeal, asserting three errors. First, Reliance argues that, contrary to the court of appeals’ analysis, Advance’d did not “furnish labor” on the Crosswinds project and thus was not entitled to a mechanic’s lien. In a related issue, Reliance argues that the court of appeals applied an erroneous standard of review by mistakenly viewing the question of whether Advance’d “furnished labor” as a legal question rather than a fact question. Finally, Rebanee complains that even if Advance’d might have been entitled to a lien, it did not timely perfect its rights, and the court erroneously failed to consider that as an alternative basis for affirming the trial court’s judgment.

A

Relevant to the first two issues is how one qualifies under the mechanic’s lien statute as a person who “furnishes labor.” Tex. PROp.Code § 53.021(a). The statute provides, in relevant part, that a person has a ben if the person “labors ... or furnishes labor or materials for construction or repair in this state of [] a house, building, or improvement” and “the person labors ... or furnishes the labor or materials under or by virtue of a contract with the owner or the owner’s agent [which includes contractors and subcontractors among others].” Id. § 53.021(a)(1),(2). Chapter 53 defines “labor” as “labor used in the direct prosecution of the work” and defines “work” as “any part of construction or repair performed under an original contract.” Id. §§ 53.001(3), (14). An “original contract” is “an agreement to which an owner is a party either directly or by implication of law.” Id. § 53.001(7). These provisions led the court of appeals to conclude that Chapter 53 protects those who labor in Texas as well as those who furnish labor under contract for the benefit of an owner’s construction project. 165 S.W.3d at 4-5.

Rebanee argues, however, that Advance’d did not “furnish labor” for the Crosswinds project because it did not control or supervise the temporary workers and was not responsible for the quality of their work. Reliance further submits that the temporary workers were Gonzalez’s employees under the borrowed-employee doctrine. See St. Joseph Hosp. v. Wolff, 94 S.W.3d 513, 538 (Tex.2003)(quoting Comm, on Pattern Jury Charges, State Bar of Tex., Texas Pattern Jury Charges: Malpractice, Premises & Products PJC 52.2 (1997)(“An employee ceases to be an employee of his general employer if he becomes the ‘borrowed employee’ of another.”)). Reliance then reasons that Advance’d did not furnish labor for the project because it was not the employer of the temporary workers who actually performed the work. The court of appeals concluded, however, that the temporary workers were Advance’d’s employees, and we agree.

The contract clearly identifies the temporary workers as Advance’d’s employees and makes Advance’d the responsible party. Advance’d was responsible for recruiting and screening these workers. Ad- *49 vanee’d was responsible for hiring, firing, paying and insuring them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Juan Nava v. William Schmidt
Court of Appeals of Texas, 2023
Gary Bruce Peek v. Linda Mayfield
Court of Appeals of Texas, 2023
Austin JSB, Ltd. v. Otwell Realty, Ltd.
Court of Appeals of Texas, 2023
Donald Wayne Stevens v. the State of Texas
Court of Appeals of Texas, 2022
in the Interest of J.M.M., a Child
Court of Appeals of Texas, 2021
Bos v. Smith
556 S.W.3d 293 (Texas Supreme Court, 2018)
Sanders Oil & Gas, Ltd. v. Big Lake Kay Constr., Inc.
554 S.W.3d 79 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
227 S.W.3d 46, 50 Tex. Sup. Ct. J. 858, 2007 Tex. LEXIS 529, 2007 WL 1650681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliance-national-indemnity-co-v-advanced-temporaries-inc-tex-2007.