Southwestern Electric Power Company v. Kenneth Lynch, Tommy Batchelor, and Twant Wilson

CourtTexas Supreme Court
DecidedFebruary 28, 2020
Docket18-0768
StatusPublished

This text of Southwestern Electric Power Company v. Kenneth Lynch, Tommy Batchelor, and Twant Wilson (Southwestern Electric Power Company v. Kenneth Lynch, Tommy Batchelor, and Twant Wilson) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Electric Power Company v. Kenneth Lynch, Tommy Batchelor, and Twant Wilson, (Tex. 2020).

Opinion

IN THE SUPREME COURT OF TEXAS 444444444444 NO. 18-0768 444444444444

SOUTHWESTERN ELECTRIC POWER COMPANY, PETITIONER, v.

KENNETH LYNCH, TOMMY BATCHELOR, AND TWANT WILSON, RESPONDENTS 4444444444444444444444444444444444444444444444444444 ON PETITION FOR REVIEW FROM THE COURT OF APPEALS FOR THE SIXTH DISTRICT OF TEXAS 4444444444444444444444444444444444444444444444444444

Argued December 5, 2019

JUSTICE GREEN delivered the opinion of the Court.

JUSTICE BLAND did not participate in the decision.

This dispute centers on the width of several general easements that an electric company

acquired from the respondent landowners’ predecessors-in-title in 1949. The petitioner electric

company argues that the easements are general easements with no fixed width, while the landowners

contend that the easements should have a fixed, thirty-foot width. After conducting a bench trial,

the trial court concluded that the easements are fixed at a thirty-foot width, and therefore the trial

court rendered judgment for the landowners. The court of appeals affirmed the trial court’s

judgment, concluding that because the original 1949 easements did not specify a width, the trial

court was within its discretion to admit extrinsic evidence of past use to determine how much of the landowners’ land “was reasonably necessary” for the petitioner to utilize pursuant to the easements.

581 S.W.3d 292, 304–06 (Tex. App.—Texarkana, pet. granted). We disagree with the court of

appeals and conclude that the easements have no fixed width, but the petitioner’s use of the land

under the easements nevertheless must be reasonable and necessary. We reverse in part the

judgment of the court of appeals and render judgment for the petitioner.

I. Background

In 1949, Southwestern Gas & Electric Company (Southwestern) acquired a number of

easements over a stretch of land in northeast Texas to construct a transmission line. Pursuant to the

easements, Southwestern constructed a wooden-pole transmission line in 1949 that crossed the

encumbered properties. Southwestern Electric Power Company (SWEPCO) subsequently acquired

these easements. The easements authorize SWEPCO “to erect towers, poles and anchors along” a

set course on a right-of-way that traverses several privately owned properties. In addition, these

easements grant SWEPCO the right to ingress and egress over the encumbered properties “for the

purpose of constructing, reconstructing, inspecting, patrolling, hanging new wires on, maintaining

and removing said line and appurtenances.” The easements limit the number of poles, towers, and

anchors that SWEPCO may construct on the properties, but also give SWEPCO the option to

increase the number of poles, towers, or anchors by compensating the landowners. Since acquiring

the easements from Southwestern, SWEPCO has continued to utilize the easements to maintain the

transmission line following the same general path since the line’s construction.

Kenneth Lynch, Tommy Batchelor, and Twant Wilson (collectively, the Landowners)

purchased land encumbered by the 1949 easements in different transactions that took place from

2 1986 to 2007. In 2014 and 2015, SWEPCO undertook a modernization project on the original

transmission line. This modernization project included replacing the line’s wooden poles with steel

poles. As part of the modernization project, SWEPCO made offers to many of the landowners

whose properties were encumbered by the 1949 easements to supplement the easements to “bring

the rights and restrictions to SWEPCO’s standard right of way requirements.” Specifically, the

supplemental terms to the 1949 easements included additional rights for SWEPCO and proposed

setting the easements’ width at 100 feet. SWEPCO offered landowners $1,000 if they accepted the

supplemental terms. Some of those landowners accepted SWEPCO’s proposal, but the Landowners

did not. SWEPCO therefore proceeded to complete the modernization project on the Landowners’

properties under the original, unamended terms of the 1949 easements.

Over the course of the modernization project, the Landowners did not object to SWEPCO’s

utilization of the 1949 easements to access their encumbered properties to upgrade the transmission

line. After the project was completed, however, the Landowners filed suit seeking a declaratory

judgment fixing SWEPCO’s easements to a thirty-foot width, fifteen feet on each side of the

transmission line. The Landowners argued that SWEPCO has only ever utilized thirty feet of the

encumbered properties, and thirty feet should be the maximum amount of land that SWEPCO may

utilize in the future. The Landowners were concerned that SWEPCO may, in the future, utilize more

than triple the amount of land it has used in the past. In support of this contention, the Landowners

pointed to SWEPCO’s offer to supplement the easements with a 100-foot fixed width as evidence

that SWEPCO intends to one day utilize the easement more than it has in the past.

3 In response to the Landowners’ suit for declaratory judgment, SWEPCO filed two pleas to

the jurisdiction, arguing that the Landowners had not suffered any injury, and therefore their claims

were not justiciable. The trial court denied SWEPCO’s pleas to the jurisdiction. SWEPCO also

filed counterclaims against the Landowners for trespass and breach of contract. SWEPCO

ultimately nonsuited these counterclaims before trial.

The trial court held a bench trial on the Landowners’ declaratory judgment claim. At trial,

the court admitted—over SWEPCO’s repeated objections—extrinsic evidence showing SWEPCO’s

historical use of the easements, which the Landowners offered in support of their argument that the

easements should have a thirty-foot width. SWEPCO meanwhile maintained that it possesses

general easements over the Landowners’ properties, and the easements are not limited to a specific

width but instead give SWEPCO the right to access the properties as much as is reasonably

necessary for the purposes specified in the easements. SWEPCO also asserted that it has no plans

to expand its use of the easements.

At the conclusion of the bench trial, the trial court entered findings of fact and conclusions

of law. The trial court found that SWEPCO “utilized, operated and maintained the transmission line

within a thirty (30) foot easement subsequent to the 2014-2015 rebuild and modernization of the

transmission line.” The trial court also found that a “thirty (30) foot easement is reasonably

necessary for the operation, use and maintenance of the transmission line across [the Landowners’]

respective properties.” Accordingly, the trial court concluded that SWEPCO’s easements are limited

to fifteen “feet on each side of the center point of the transmission line, amounting to a thirty (30)

4 foot utility easement” on the Landowners’ properties. The trial court also awarded the Landowners

attorneys fees and costs.

On appeal, SWEPCO argued that the trial court lacked subject matter jurisdiction over the

suit because there was no justiciable controversy. Specifically, SWEPCO argued that the

Landowners have not alleged that SWEPCO used the easements in an unreasonable manner or

beyond what was reasonably necessary. As for the trial court’s conclusion that the easements have

a fixed, thirty-foot width, SWEPCO argued that the 1949 easements are express general easements

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Manufacturers Mutual Insurance Co. v. Schaefer
124 S.W.3d 154 (Texas Supreme Court, 2003)
Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Brooks v. Northglen Ass'n
141 S.W.3d 158 (Texas Supreme Court, 2004)
Waco Independent School District v. Gibson
22 S.W.3d 849 (Texas Supreme Court, 2000)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Marcus Cable Associates, L.P. v. Krohn
90 S.W.3d 697 (Texas Supreme Court, 2002)
Texas Ass'n of Business v. Texas Air Control Board
852 S.W.2d 440 (Texas Supreme Court, 1993)
City of Mission v. Popplewell
294 S.W.2d 712 (Texas Supreme Court, 1956)
Coleman v. Forister
514 S.W.2d 899 (Texas Supreme Court, 1974)
Bonham State Bank v. Beadle
907 S.W.2d 465 (Texas Supreme Court, 1995)
Empire Life Insurance Co. of America v. Moody
584 S.W.2d 855 (Texas Supreme Court, 1979)
Royal Indemnity Company v. Marshall
388 S.W.2d 176 (Texas Supreme Court, 1965)
Crawford v. Tennessee Gas Transmission Co.
250 S.W.2d 237 (Court of Appeals of Texas, 1952)
Williams v. Thompson
256 S.W.2d 399 (Texas Supreme Court, 1953)
Houston Pipe Line Company v. Dwyer
374 S.W.2d 662 (Texas Supreme Court, 1964)
DeWitt County Electric Cooperative, Inc. v. Parks
1 S.W.3d 96 (Texas Supreme Court, 1999)
Knox v. Pioneer Natural Gas Company
321 S.W.2d 596 (Court of Appeals of Texas, 1959)
Mayhew v. Town of Sunnyvale
964 S.W.2d 922 (Texas Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Southwestern Electric Power Company v. Kenneth Lynch, Tommy Batchelor, and Twant Wilson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-electric-power-company-v-kenneth-lynch-tommy-batchelor-and-tex-2020.