Fisher v. Groff

3 Pa. D. & C.2d 49, 1955 Pa. Dist. & Cnty. Dec. LEXIS 294
CourtPennsylvania Court of Common Pleas, Lancaster County
DecidedJanuary 21, 1955
Docketno. 7
StatusPublished

This text of 3 Pa. D. & C.2d 49 (Fisher v. Groff) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Lancaster County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fisher v. Groff, 3 Pa. D. & C.2d 49, 1955 Pa. Dist. & Cnty. Dec. LEXIS 294 (Pa. Super. Ct. 1955).

Opinion

Wissler, J.,

This is a matter arising on a scire facias on a mechanic’s lien by claimant, George A. Fisher, against the three named defendants. The case came to trial before a jury and on November 16, 1954, a verdict was rendered in favor of claimant, George A. Fisher, and against defendants in the sum of $4,392.78 (no interest to be added thereto). On November 19, 1954, defendants filed a motion and eight reasons for a new trial and a motion for judgment n. o. v.

Claimant and defendants entered into a written contract on June 16, 1954, for claimant to install a two-room walk-in refrigerator in the building of defendants in the Borough of Elizabethtown, Pa., for the sum of $5,450, to be paid in full within 30 days from the completion of the job. Claimant performed part of the work in accordance with the contract, but has never completed the work because of a fire breaking out in the refrigerator room while claimant and an employe were working there, and since the fire no work has been done by claimant.

[50]*50The first three reasons of defendants for new trial are based on the verdict being against the law, the evidence, and the weight of the evidence. It is well settled that a new trial will not be granted because of a mere conflict in testimony or because the trial judge on the same facts would have arrived at a different conclusion: Wilson v. Kallenbach, 332 Pa. 253. A complaint that a verdict is against the evidence is applicable to a case only when there is no conflict in the testimony: Landis, Admx., v. Conestoga Transportation Company et al. no. 1, 349 Pa. 97. It is true, as a general rule, that a new trial will be granted where the verdict is clearly against the weight of the evidence, but it is equally true that in order to warrant the granting of a new trial on such ground the preponderance of the evidence must be clear and decisive. This court feels that there was more than a scintilla of evidence to support the verdict, and that a new trial should not be granted for either of the first three reasons assigned.

As to the fourth, fifth and sixth reasons, namely: “ (4) The verdict was against the charge of the court; (5) The learned court erred in charging the jury that they could find a verdict in favor of the claimant; (6) The learned court erred in submitting to the jury the question as to the building being destroyed by fire ; since all the evidence was to the effect that the building was destroyed by fire”; the court feels that it fairly presented to the jury the questions of fact involved when it submitted the contentions of claimant and defendants in its charge: “Now, it is the contention of the plaintiff that he substantially performed his part of the written contract of June 16, 1954, entered into between himself and the defendants, and that he was prevented from full performance because of the fire and also because of the defendants, and that he had obtained and had available to the defendants the [51]*51remainder of the equipment not installed before the fire at a cost in amount of $2,315.34, and that the amount of the materials installed was $2,077.44. It is further the contention of the plaintiff that the building in which the materials were installed was not constructed by him and that the building of which the installation of the refrigerators formed a part was not so destroyed as to be nonusable in its then present condition. The defendants, on the other hand, contend that the building in which the plaintiff’s installations were made was destroyed by fire and there was no building left against which the plaintiff’s mechanic’s lien could be filed, and that plaintiff did not complete the written contract of June 16, 1954, before the fire, which contract called for payment in full within 30 days of completion. It is for you to determine which of these contentions you believe.” And the court further affirmed defendants’ fifth point, namely: “No. 5. If you find that the building in question was substantially destroyed, your verdict must be for the defendants. That point is affirmed.”

As to the seventh reason, namely: “(7) The learned court erred in refusing defendants’ motion for a non-suit”; the refusal to enter a compulsory nonsuit is not the subject of review or a proper reason for a new trial (Commonwealth, to use, v. Whittaker & Diehl Co. et al., 44 Lane. 580; Northern Trust Co., Exec., v. Huber et ux., 274 Pa. 329), and hence this reason need not be considered.

In the eighth reason assigned, namely: “(8) The learned court erred in permitting over exceptions of the defendants’ for plaintiff to amend his answer to the question, ‘Was this building destroyed by fire?’, to which the defendants reply ‘yes’,” the words “destroyed by fire” could mean partial or total destruction, and to be asked to explain in reexamination after having previously testified to what was damaged in [52]*52parts of building and refrigerators would seem proper, and a reasonable exercise of discretion on the part of the trial judge. As to matters that require explanation or where new matter is introduced by the opposing interest, a party has a right in rebuttal to reexamine his witness: Asay v. Hay, 89 Pa. 77. The extent of reexamination is within the discretion of the trial judge: Stern, Trustee, v. Stanton et al., 184 Pa. 468.

Defendants do not in their oral argument raise any question as to the amount of the verdict, nor make a distinction between materials already placed in the building and those that had not been so placed before the fire, nor do they raise the question of partial performance and claim that the contract itself has no bearing on the question involved. Their contention is that the mechanic’s lien is invalid because there was no building upon defendants’ land after the fire to which the lien could attach. This, then, brings us to defendants’ motion for judgment n. o. v. The sole question for determination on a motion for judgment n. o. v. on the whole record, after a request for binding instructions, is whether such request should have been granted: Strawbridge v. Hawthorne, 47 Pa. Superior Ct. 647. A trial court cannot enter judgment n. o. v. because of inconsistency in the testimony: Willetts et al. v. Butler Township, 141 Pa. Superior Ct. 894. A motion for judgment upon the entire record must be disposed of upon the record as it existed at the close of the trial. The court can neither eliminate evidence which may have been improperly admitted, nor insert offers of evidence which should have been admitted but were excluded; the remedy in either case is a new trial: Mincy v. Washington National Insurance Company, 130 Pa. Superior Ct. 285.

The evidence, considering it in the light most favorable to claimant as the court is required to do, warrants a finding that claimant was by written contract [53]*53to build two walk-in refrigerators in a concrete block building of defendants, which building with roof was erected previously by another builder for defendants. However, claimant put in the plumbing and drains in the floor, which was done while the builder was putting up the blocks and before the concrete floor was put it. The walk-in refrigerators consisted of two rooms with a connecting door, one a chill box and the other a holding room. The sides and ceiling were put on with enamelite and cork and finished with a white layer of plaster. Claimant also did the wiring. The door jambs were set in with the blocks at the time the wall was constructed. The doors themselves (11 feet 6 inches high by 3 feet) were made up by the Jamison Door Company of Hagerstown, Md., but had not been hung at the time of the fire.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Butler v. Ng Chung
117 P. 512 (California Supreme Court, 1911)
Wilson v. Kallenbach
2 A.2d 727 (Supreme Court of Pennsylvania, 1938)
Landis v. Conestoga Transportation Co.
36 A.2d 465 (Supreme Court of Pennsylvania, 1944)
Mincy v. Washington National Insurance
196 A. 893 (Superior Court of Pennsylvania, 1937)
Presbyterian Church v. Stettler
26 Pa. 246 (Supreme Court of Pennsylvania, 1856)
Wigton & Brooks's Appeal
28 Pa. 161 (Supreme Court of Pennsylvania, 1857)
Asay v. Hay
89 Pa. 77 (Supreme Court of Pennsylvania, 1879)
Short v. Miller & Co.
14 A. 374 (Supreme Court of Pennsylvania, 1888)
Short v. Ames
15 A. 607 (Supreme Court of Pennsylvania, 1888)
Linden Steel Co. v. Rough Run Mfg. Co.
27 A. 895 (Supreme Court of Pennsylvania, 1893)
Wheeler v. Pierce, Kelley & Co.
31 A. 649 (Supreme Court of Pennsylvania, 1895)
Stern v. Stanton
39 A. 404 (Supreme Court of Pennsylvania, 1898)
Northern Trust Co. v. Huber
118 A. 217 (Supreme Court of Pennsylvania, 1922)
Montgomery v. Keystone Fibre Co.
1 Pa. Super. 261 (Superior Court of Pennsylvania, 1896)
Strawbridge v. Hawthorne
47 Pa. Super. 647 (Superior Court of Pennsylvania, 1911)
Holland v. Farrier
130 N.E. 823 (Indiana Court of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
3 Pa. D. & C.2d 49, 1955 Pa. Dist. & Cnty. Dec. LEXIS 294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fisher-v-groff-pactcompllancas-1955.