Silberstein v. Kitrick

169 P. 250, 35 Cal. App. 91, 1917 Cal. App. LEXIS 384
CourtCalifornia Court of Appeal
DecidedOctober 23, 1917
DocketCiv. No. 1735.
StatusPublished
Cited by1 cases

This text of 169 P. 250 (Silberstein v. Kitrick) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Silberstein v. Kitrick, 169 P. 250, 35 Cal. App. 91, 1917 Cal. App. LEXIS 384 (Cal. Ct. App. 1917).

Opinion

CHIPMAN, P. J.

The action is to recover from defendants the sum of ten thousand dollars on a bond given by them for that amount as sureties of the Burnight-Kennedy Company, a corporation, which had entered into a contract with plaintiff to erect a building in the city of Chico. The cause was tried by the court without a jury and defendants had findings and judgment in their favor. Plaintiff appeals from the judgment and from the order denying his motion for a new trial, The contract price for the building was forty-one thousand five hundred dollars, to be paid by progressive payments, as follows:

“First—The sum of two thousand ($2000) dollars when all excavation is completed and the walls are up ready to receive first or street floor joists.
“Second—The sum of twenty-nine thousand one hundred ($29,100) dollars from time to time as the work progresses, from the date of the first payment until the completion of the building; said sum of $29,100 to be paid in the sums of $2000 each, when labor and material have been performed and placed in the building, exceeding said several sums by 25 per cent. *92 Bach payment shall he a stop or rest, and the next payment of $2000 to be made when an additional amount of labor and material has been performed and furnished 25 per cent in excess of the payment to be made. After thirteen payments of $2000 have been made and upon the final completion and delivery of the building the sum of $31,000 shall be made, and the balance and last payment of the contract price, to-wit, the sum of $10,400 shall be made thirty-six (36) days after the completion and delivery of the building.”

By appropriate averments in their answer, defendants sought to have corrected an obvious ambiguity or mistake in the latter part of clause “Second,” which provided for a completion payment of thirty-one thousand dollars, so as to read thirty-one hundred dollars, and the court, on sufficient evidence, found that it was the intention of the parties that this payment should be thirty-one hundred dollars. Thus construed, payments should have been made as follows:

First payment...........................$ 2,000
13 $2000 payments ....................... 26,000
Completion payment...................... 3,100
36 days after completion payment........... 10,400
$41,500

The first payment of two thousand dollars was made* on May 22, 1909, and at various times each month thereafter thirteen payments of two thousand dollars each were made, the last, or thirteenth, of date January 8, 1910. On January 22, 1910, there was a further payment made of two thousand dollars, which defendants claim was a premature payment and unauthorized. On March 16, 1910, the company quit work and ceased furnishing materials, leaving the building unfinished, and plaintiff took possession and completed the work on April 14, 1910, at a cost to him of $885.31 for labor and material, and on April 15, 1910, he filed notice of completion in the county recorder’s office.

As the work progressed, the architect named in the contract issued and delivered to the company certificates upon account of materials used and labor performed, and plaintiff paid to the company on said certificates up to and including the payment of January 22, 1910, the total sum of thirty thousand dollars. The contract provided, among other things, as pointed out by appellant, that in each case of payment *93 under the contract a certificate was to be “ obtained and signed by the said A. J. Bryan, architect”; that “should any dispute arise respecting the meaning of the drawings or specifications, the same shall be decided by A. J. Bryan, architect, and his decision shall be final, but should any dispute arise respecting the value of the extra work or works omitted” the dispute was to be arbitrated; that “all payments shall be made upon the certificates of the architect, and this contract is completed and the work is finished in accordance with the original plans and such modifications or alterations as may be made therein. The owner is to make payments promptly and upon the certificate of the architect.” No other powers of the architect appear at all pertinent to any issue here, so far as we can discover. The' bond made reference to the contract and among the provisions of the bond relating to the obligation of the sureties were the following:

“Now, therefore, if the said Burnight-Kennedy Company shall pay for all materials and supplies furnished for the performance of the work so contracted to be done and pay for all labor done and to be done of every kind and to complete and finish said building within the time named and according to the plans and specifications, then this obligation shall be void, otherwise the sureties herein will pay the same to the amount specified in said bond.
“It is further stipulated and a portion of this bond, that the said Burnight-Kennedy Company shall complete and turn over to the said H. Silberstein said building free and clear of all claims, liens or demands of any person, contractor, subcontractor, material men, laborers, etc., and in the event of the failure to do so, then the sureties on this bond are held as herein specified.”

The court found that the payment of two thousand dollars made January 22, 1910, was a premature payment, “and should not, under the terms of the contract entered into between H. Silberstein and Burnight-Kennedy Company, have been made until the final completion and delivery of the building to plaintiff and the acceptance of said building by him; that said payment was made without the knowledge or consent of the defendants, R. S. Kitrick and Harry Jacoby, or either of them.” The court also found that certain corporations and partnerships served notice under section 1184 of the Code of Civil Procedure,15 which notices were in proper *94 form, to withhold the amounts named in said notices from the payments due under said contract, or to thereafter become due to said Burnight-Kennedy Company.” These claims aggregated $7,573.70, as follows:

Diamond Match Company, notice served September

15, 1909 ..................................$5,617.10 Wygant & Collins, notice served December 26, 1909. 1,751.20 Chico Con. Co., notipe served January-4, 1910...... 205.40

The court found that without the knowledge or consent of defendants, plaintiff paid to the company “large sums of money which, under the laws of the state of California, it was his duty to withhold,” namely, after September 15, 1909, on which date the Diamond Match Company served its notice, plaintiff paid to the contracting company fourteen thousand dollars, as appears above. After the date of the Wygant & Collins notice, the sum of four,thousand dollars was paid by plaintiff to the company, and a like amount was paid after the notice of the Chico Construction Company was served.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Coast Engineering Co. v. Detroit Fidelity & Surety Co.
5 P.2d 888 (California Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
169 P. 250, 35 Cal. App. 91, 1917 Cal. App. LEXIS 384, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silberstein-v-kitrick-calctapp-1917.