Powers Regulator Co. v. Seaboard Surety Co. of New York

204 Cal. App. 2d 338, 22 Cal. Rptr. 373, 1962 Cal. App. LEXIS 2250
CourtCalifornia Court of Appeal
DecidedJune 4, 1962
DocketCiv. 25676
StatusPublished
Cited by26 cases

This text of 204 Cal. App. 2d 338 (Powers Regulator Co. v. Seaboard Surety Co. of New York) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Powers Regulator Co. v. Seaboard Surety Co. of New York, 204 Cal. App. 2d 338, 22 Cal. Rptr. 373, 1962 Cal. App. LEXIS 2250 (Cal. Ct. App. 1962).

Opinion

ASHBURN, J.

Defendant Seaboard Surety Company of New York appeals from judgment in favor of plaintiff Powers Regulator Company in an action brought to recover $9,868, with interest, upon a public works bond given by a general contractor, Allison Honer Company, and said surety company pursuant to sections 4200 et seq., Government Code, 1 in connection with the construction for the County of Orange of a psychiatric building for the county hospital.

Allison Honer Company, the prime contractor, made a subcontract with Clark Company to do that part of the work consisting of installation of plumbing, heating and ventilating systems, and Clark Company in turn subcontracted with plaintiff Powers Regulator Company to install a pneumatic temperature control system in the building. 2 As to payment, *342 the Allison Honer contract with Clark says: “Payment will be made each month for 90% of the work completed the previous month as certified by the Owner’s Representative, such payment to be made on or before the 10th prox., and final payment in full will be made within 30 days after final acceptance.”

The subcontract between Clark and Powers contains these terms of payment: “All progress payments, less 10% retainer, and the final 10% retainer payment, as approved by the Arehitect/Owner will be paid in full to Powers Regulator Company, on or before 5 days after the reetept of each payment by Clark Company, from the General Contractor, Allison Honer Company, Santa Ana, California. Please invoice us for all progress payments, on or about the 20th day of each month, as of the last day of each month. Mail (3) copies of invoices to Clark Company.”

After the work had been accepted on February 16, 1959, Mr. Honer, partner in Allison Honer Company, instructed Mr. Clark (owner of Clark Company) to get releases from his major subcontractors and suppliers. Clark prepared a release to be signed by Powers Regulator Company and mailed it to that company’s accountant with the explanation that he would have to have it in order to get his money, and that upon its receipt duly signed Clark would get its money and pay Powers the amount due it, $9,868. On March 10th Powers executed and delivered the release, which reads as follows: “Powers Regulator Company, 3200 Temple Street, Los Angeles 26, Calif, hereby releases Allison Honer Company, 312 North Main St. Santa Ana, Calif., Contractors, and the property known and described as Psychiatric Building at Orange County General Hospital, in the city of Placentia Ave., County of Orange, State of California, from all claims and demands for or on account of materials and/or labor and material furnished by the undersigned to and including the 30th day of November, 1958, purchased by the Clark Company, 188 So. ‘I’ Street, San Bernardino, Calif. Except 10% retainer wit/ield per P.O. No. C-167-6, for use in the property above described. Powers Regulator Company by: S.J. Wallace, title: Ass’t. Bkpr.”

*343 Clark got its money on March 23, 1959, but never paid Powers. Mr. Honer testified he would not have paid Clark if he had not received the release, or would have made the payment by check payable jointly to Clark and Powers. This joint check procedure had been followed in several instances but not with Clark, and there is no evidence that Powers knew of such practice.

It is now claimed by appellant Surety Company that Powers is estopped to assert its claim in its action against appellant because Allison Honer gave up its right to make payment by joint check, thereby suffered a detriment and that a defense of estoppel arose in favor of Allison Honer, which defense inured to the benefit of Seaboard Surety Company as its surety.

Section 4204, Government Code, provided: “To be approved, the contractor’s bond shall provide that if the person or his subcontractors, fail to pay for any materials, provisions, provender or other supplies, or teams, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind . . . that the surety or sureties will pay for the same, in an amount not exceeding the sum specified in the bond, and also, in case suit is brought upon the bond, a reasonable attorney’s fee, to be fixed by the court.” (Emphasis added.) The bond in suit is set forth in full in the complaint and in footnote 3 hereof. 3 The condition of the *344 bond is: “Now, Therefore, if the above bounden Principal, contractor, person, company or corporation, or his or its subcontractor, fails to pay for any materials, provisions, provender or other supplies, or teams, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind . . . with respect to such work or labor, the SURETY on this bond bill pay the same in an amount not exceeding the sum specified in this bond. ...” (Emphasis added.) (The word “bill” is obviously a misprint meaning “will.”) Neither the statute nor the bond requires the “principal” on the bond to pay—this for the obvious reason that the bond is designed primarily to protect materialmen and others who have no right to look to the general contractor for their money, persons with whom the general contractor has no contractual relationship. 4

Pneucrete Corp. v. United States Fid. & Guar. Co., 7 Cal.App.2d 733, 736 [46 P.2d 1000] : “The purpose of the bond provision of the Public Works Act, we believe, was to give to materialmen and laborers who furnish material for and render services upon public works an additional means of receiving compensation.” Page 737: “No lien being *345 available to those who perform labor or furnish material on public works (Cooley v. Freeman, 204 Cal. 59 [266 P. 545]), the provisions of the Public Works Act requiring a bond were obviously enacted to create a fund in lieu of the building or work itself against which materialmen and laborers might proceed as an additional and contemporaneous remedy. The bond required is not a voluntary bond but a statutory bond (Williamson v. Egan, 209 Cal. 343, 344 [287 P. 503]; Continental Nat. Bank v. Republic Cas. Co., 202 Cal. 586, 589 [262 P. 300]), and affords an additional or cumulative remedy.” Page 738 : “The action upon the statutory bond is not in any sense based upon the personal liability of the contractor but is based upon the obligation of the bond, since the bond provides a separate and distinct and statutory remedy. The obligation of the bond, therefore, is enforceable without reference to any contract between the contractor and the material-man.” There was no contractual relationship between Allison Honer (the bond “principal”) and Powers.

It seems to be settled law that in an instance of true suretyship defenses (e.g., estoppel) arising in favor of the principal are available to the surety.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Violante v. Communities Sw Development
41 Cal. Rptr. 3d 673 (California Court of Appeal, 2006)
Violante v. Communities Southwest Development & Construction Co.
138 Cal. App. 4th 972 (California Court of Appeal, 2006)
Scott Co. v. United States Fidelity & Guaranty Insurance
132 Cal. Rptr. 2d 89 (California Court of Appeal, 2003)
Fed. Ins. Co. v. Superior Court of Ventura Cty.
60 Cal. App. 4th 1370 (California Court of Appeal, 1998)
DEPARTMENT OF INDUS. REL. v. Fidelity Roof Co.
60 Cal. App. 4th 411 (California Court of Appeal, 1997)
Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Lewin v. Anselmo
56 Cal. App. 4th 694 (California Court of Appeal, 1997)
Department of Industrial Relations v. Seaboard Surety Co.
50 Cal. App. 4th 1501 (California Court of Appeal, 1996)
Golden Eagle Insurance v. First Nationwide Financial Corp.
26 Cal. App. 4th 160 (California Court of Appeal, 1994)
T&R Painting Construction Inc. v. St. Paul Fire & Marine Insurance
23 Cal. App. 4th 738 (California Court of Appeal, 1994)
Blair Excavators, Inc. v. Paschen Contractors, Inc.
9 Cal. App. 4th 1815 (California Court of Appeal, 1992)
Milo Equipment Corp. v. Elsinore Valley Municipal Water District
205 Cal. App. 3d 1282 (California Court of Appeal, 1988)
Sukut-Coulson, Inc. v. Allied Canon Co.
85 Cal. App. 3d 648 (California Court of Appeal, 1978)
C. A. Magistretti Co. v. Merced Irrigation District
27 Cal. App. 3d 270 (California Court of Appeal, 1972)
Consolidated Electrical Distributors, Inc. v. Kirkham, Chaon & Kirkham, Inc.
18 Cal. App. 3d 54 (California Court of Appeal, 1971)
Card Construction Co. v. Ledbetter
16 Cal. App. 3d 472 (California Court of Appeal, 1971)
Pacific Employers Insurance v. State of California
477 P.2d 129 (California Supreme Court, 1970)
McDonagh v. Gourneau
2 Cal. App. 3d 1033 (California Court of Appeal, 1969)
General Electric Co. v. Central Surety & Insurance
232 Cal. App. 2d 590 (California Court of Appeal, 1965)
United States v. James Stewart Company
336 F.2d 777 (Ninth Circuit, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
204 Cal. App. 2d 338, 22 Cal. Rptr. 373, 1962 Cal. App. LEXIS 2250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/powers-regulator-co-v-seaboard-surety-co-of-new-york-calctapp-1962.