T&R Painting Construction Inc. v. St. Paul Fire & Marine Insurance

23 Cal. App. 4th 738, 29 Cal. Rptr. 2d 199, 94 Daily Journal DAR 3717, 94 Cal. Daily Op. Serv. 2044, 1994 Cal. App. LEXIS 243
CourtCalifornia Court of Appeal
DecidedMarch 22, 1994
DocketB076895
StatusPublished
Cited by21 cases

This text of 23 Cal. App. 4th 738 (T&R Painting Construction Inc. v. St. Paul Fire & Marine Insurance) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T&R Painting Construction Inc. v. St. Paul Fire & Marine Insurance, 23 Cal. App. 4th 738, 29 Cal. Rptr. 2d 199, 94 Daily Journal DAR 3717, 94 Cal. Daily Op. Serv. 2044, 1994 Cal. App. LEXIS 243 (Cal. Ct. App. 1994).

Opinion

Opinion

BOREN, P. J.

The question presented by this appeal is whether the surety on a construction bond is liable for attorney fees incurred by a bond beneficiary. The beneficiary’s contract with the surety’s principal calls for the payment of fees to the prevailing party in the event of any legal action.

Following the statutory mandate that a surety’s liability is commensurate with that of its principal (Civ. Code, § 2808), we conclude that the surety is liable for the attorney fees that its principal was ordered to pay to the beneficiary after a legal dispute was resolved in favor of the beneficiary.

Facts

A property owner, London Pacific Investors (LPI), hired a general contractor, Capitol Systems (Capitol), to construct a residential development called Sycamore Village. The contractor, Capitol, obtained performance and payment bonds from respondent St. Paul Fire and Marine Insurance Company (St. Paul). In the payment bond, St. Paul agreed to pay claims made by *742 subcontractors in the event that Capitol failed to pay the subcontractors for labor and materials supplied. 1 The payment bond does not have an attorney fees clause.

Appellant T&R Painting Construction, Inc. (T&R) entered into a subcontract with Capitol to work on the first phase of Sycamore Village. The subcontract entitled the prevailing party in any litigation to recover its attorney fees. After T&R completed a portion of its work, Capitol terminated the subcontract on the grounds that T&R’s work was defective. The dispute was submitted to arbitration, as required by the subcontract. The arbitrator found that the termination was not supported by the evidence, and that T&R was entitled to recover 75 percent of the subcontract price, or $62,062, plus interest, as the agreed value of its work. The arbitrator also awarded T&R its attorney fees and costs as the prevailing party on the subcontract.

After the arbitration award was rendered, Capitol filed a bankruptcy petition. The automatic bankruptcy stay was lifted to allow T&R to obtain judgment in state court on its arbitration award. In the meantime, T&R and LPI settled T&R’s action to foreclose on a mechanic’s lien. T&R retained its contractual rights against Capitol for its attorney fees and costs. Subsequently, T&R petitioned the superior court for confirmation of the arbitration award against Capitol, and judgment was entered thereon.

In March of 1993, T&R went to trial against St. Paul on the action it filed in 1989. The only issue before the trial court was whether St. Paul was liable for the attorney fees T&R incurred in prosecuting its claims, including arbitration, against Capitol. St. Paul prevailed. T&R appeals.

*743 Discussion

1. “One Final Judgment Rule”

Initially, St. Paul contends that this action is barred by the “one final judgment” rule. In support of its argument, St. Paul cites cases which set forth the doctrine of res judicata. St. Paul reasons that the judgment T&R obtained against Capitol after arbitration precludes any subsequent proceedings against St. Paul because a second action between the same parties on the same claim is impermissible (citing Clark v. Lesher (1956) 46 Cal.2d 874, 880 [299 P.2d 865]).

The two concepts to which St. Paul alludes are somewhat intertwined. The “one final judgment” rule prevents piecemeal dispositions and multiple appeals by requiring a final (as opposed to interlocutory) judgment before an appeal may lie. (9 Witkin, Cal. Procedure (3d ed. 1985) Appeal, § 43, pp. 66-67.) The doctrine of res judicata also addresses the issue of finality: it. gives conclusive effect to final judgments in subsequent litigation between the same parties over the same controversy. (7 Witkin, Cal. Procedure, supra, Judgment, §§ 188-189, pp. 621-622.)

Obviously, Capitol and St. Paul are not, strictly speaking, the “same parties.” As principal and surety, respectively, they have a unity of interest. Because of the nature of the principal/surety relationship, the courts have carved out a special rule for cases involving sureties and other parties having a unity of interest. The rule is that when one party to a judgment has a unity of interest with another party whose rights are not determined by the judgment, no appeal lies until the rights or duties of the interested party have been resolved by a final judgment. (Millsap v. Federal Express Corp. (1991) 227 Cal.App.3d 425, 430, fn. 2 [277 Cal.Rptr. 807]; Fleuret v. Hale Constr. Co. (1970) 12 Cal.App.3d 227, 230 [90 Cal.Rptr. 557]; Call v. Alcan Pacific Co. (1967) 251 Cal.App.2d 442, 449, fn. 11 [59 Cal.Rptr. 763] [“When a lawsuit involves a single claim against principal and surety, an appellate court should not be subjected to their separate appeals.”].)

In this case, St. Paul did not participate in the arbitration proceeding which led to the award in favor of T&R, even though St. Paul was individually named in T&R’s suit. The arbitrator did not address the issue of St. Paul’s liability as surety. Because that issue remained unresolved, the judgment was not yet final for purposes of taking an appeal.

We also note that “[i]n an action against several defendants, the Court may, in its discretion, render judgment against one or more of them, leaving *744 the action to proceed against the others, whenever a several judgment is proper.” (Code Civ. Proc., § 579.) Here, T&R was required to arbitrate its claims against Capitol, by virtue of the subcontract which contained an arbitration clause. T&R then obtained judgment against Capitol when the arbitration award was confirmed. It was an appropriate exercise of the court’s discretion to allow the case to continue on against Capitol’s surety because the arbitrator did not purport to resolve the issue of St. Paul’s liability on the bond.

2. Liability for Attorney Fees

A bond securing a work of improvement “will be construed most strongly against the surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall a surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner and original contractor or on the part of any obligee named in such bond . . . (Civ. Code, § 3226.)

As a subcontractor, T&R is by law a person for whose benefit a bond is given, and who may enforce liability on the bond against both the principal and surety. (Civ. Code, §§ 3110, 3226; Code Civ. Proc., §§ 995.130, 996.410.) The labor and material payment bond itself states that it is “for the use and benefit of claimants.” A claimant is defined in the bond as “one having a direct contract with the Principal [Capitol] or with a subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract. . . .”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Karton v. Ari Design & Construction, Inc.
California Court of Appeal, 2021
Karton v. Ari Design & Construction
California Court of Appeal, 2021
Vigil v. Wesco Ins. Co. CA4/1
California Court of Appeal, 2015
Granite Construction v. Bond Safeguard Ins. CA3
California Court of Appeal, 2014
Series AGI West Linn of Appian Group Investors DE, LLC v. Eves
217 Cal. App. 4th 156 (California Court of Appeal, 2013)
Pierce v. Western Surety Co.
207 Cal. App. 4th 83 (California Court of Appeal, 2012)
First National Insurance v. Cam Painting, Inc.
173 Cal. App. 4th 1355 (California Court of Appeal, 2009)
Alfaro v. Community Housing Improvement System & Planning Assn., Inc.
171 Cal. App. 4th 1356 (California Court of Appeal, 2009)
Colorado Structures, Inc. v. Insurance Co. of the West
161 Wash. 2d 577 (Washington Supreme Court, 2007)
Colonial American Casualty & Surety Co. v. Scherer
214 S.W.3d 725 (Court of Appeals of Texas, 2007)
Cuevas v. Truline Corp.
12 Cal. Rptr. 3d 706 (California Court of Appeal, 2004)
National Technical Systems v. Superior Court
118 Cal. Rptr. 2d 465 (California Court of Appeal, 2002)
Holland v. MORSE DIESEL INTERNAT., INC.
104 Cal. Rptr. 2d 239 (California Court of Appeal, 2001)
Mesa Forest Products, Inc. v. St. Paul Mercury Insurance
86 Cal. Rptr. 2d 398 (California Court of Appeal, 1999)
Royster Construction Co. v. Urban West Communities
40 Cal. App. 4th 1158 (California Court of Appeal, 1995)
Granite Constr. Co. v. Am. Motorists Ins. Co.
29 Cal. App. 4th 658 (California Court of Appeal, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
23 Cal. App. 4th 738, 29 Cal. Rptr. 2d 199, 94 Daily Journal DAR 3717, 94 Cal. Daily Op. Serv. 2044, 1994 Cal. App. LEXIS 243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tr-painting-construction-inc-v-st-paul-fire-marine-insurance-calctapp-1994.