Royster Construction Co. v. Urban West Communities

40 Cal. App. 4th 1158, 47 Cal. Rptr. 2d 684, 95 Cal. Daily Op. Serv. 9320, 95 Daily Journal DAR 16178, 1995 Cal. App. LEXIS 1186
CourtCalifornia Court of Appeal
DecidedDecember 6, 1995
DocketB083429
StatusPublished
Cited by13 cases

This text of 40 Cal. App. 4th 1158 (Royster Construction Co. v. Urban West Communities) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royster Construction Co. v. Urban West Communities, 40 Cal. App. 4th 1158, 47 Cal. Rptr. 2d 684, 95 Cal. Daily Op. Serv. 9320, 95 Daily Journal DAR 16178, 1995 Cal. App. LEXIS 1186 (Cal. Ct. App. 1995).

Opinion

Opinion

GODOY PEREZ, J.

Defendants and cross-complainants Urban West Communities, UWC-Valley Circle, UWC-Canoga and the American Insurance Company appeal from the judgment following bench trial entered for plaintiff and cross-defendant Royster Construction Company. For the reasons set forth below, we modify the judgment both in regard to its award of attorney fees and its award of prejudgment interest.

Facts and Procedural History

Defendants and appellants UWC-Valley Circle and UWC-Canoga are limited partnerships which owned two tracts of land slated for residential development in Canoga Park (the West Hills project). Defendant and appellant Urban West Communities, a California corporation, is a general contractor and a partner in UWC-Valley Circle and UWC-Canoga. 1 Plaintiff and respondent Royster Construction Company (Royster) is a grading contractor. In August 1985, Royster entered into a written agreement with UWC to act as the grading subcontractor for the West Hills project. The contract contained a clause calling for the payment of attorney fees to the prevailing party in an action arising from the agreement. Pursuant to the contract, Royster obtained a performance bond at UWC’s expense. Cross-defendant and cross-complainant Transamerica Premier Insurance Company (Transamerica) was the surety on that performance bond. 2

Royster began grading work in January 1986. Because the project was more difficult than expected, the original estimate of $896,849 eventually *1163 ballooned to $3,772,032.11. By March 1987, Royster’s work was nearly 95 percent complete. Disputes arose between Royster and UWC over delays by UWC in making progress payments and the length of time it was taking Royster to finish grading. In May 1987, UWC notified Royster the contract was being terminated for cause and hired another grading subcontractor to finish the job. UWC owed Royster an unpaid balance of $359,289 at that time.

On August 27, 1987, Royster recorded two claims of mechanic’s lien, one against each tract of the West Hills project, each in the amount of $405,069.31. On November 24, 1987, Royster sued UWC (and other parties not relevant to this appeal) for breach of contract, various common counts and to foreclose the mechanic’s liens. As to each cause of action, Royster sought to recover prejudgment interest “at the legal rate.” Royster’s complaint gave rise to various cross-complaints, none of which are relevant to this appeal.

Pursuant to Civil Code section 3143, UWC posted two bonds of $607,604 each to release both tracts of land in the West Hills project from Royster’s mechanics’ liens. 3 The surety on the release bonds was defendant and appellant the American Insurance Company (American), which was added as a party defendant by Royster’s supplemental complaint on March 30, 1989. 4

Based on the parties’ stipulation, the superior court appointed retired Judge Judith Ryan as temporary judge for all further proceedings. A bench trial began on March 23, 1992, with 29 days of testimony taken sporadically until February 24, 1993. Judge Ryan filed her notice of intended decision on July 30, 1993, finding that UWC breached the contract by terminating Royster from the West Hills project on May 9, 1987. Royster was to recover damages of $359,289, lost profits of more than $80,000, along with “judgment on the lien release bond in addition to costs, interest and attorneys’ fees to be determined.”

Proposals and objections concerning the ultimate judgment were filed by the parties. UWC objected to having attorney fees assessed against the lien release bonds. Transamerica proposed that interest of 10 percent run on the sums owed under the contract and mechanic’s lien foreclosure claims as of May 9, 1987. UWC did not object to the latter proposal. Judge Ryan’s final *1164 judgment was entered on December 6, 1993. On the breach of contract claim, Royster was awarded: damages of $359,289 for breach of contract, with interest to run at 10 percent as of May 9, 1987; lost profits of $80,831, with interest to run at 10 percent from the date Royster’s complaint was filed in November 1987; and costs of suit and attorney fees, to be determined in a later costs bill. As for the mechanic’s lien claim, Royster was awarded $359,289, plus interest at 10 percent as of May 9, 1987, along with costs of suit and attorney fees as determined by the court, all against the lien release bonds. 5

UWC then brought a motion for new trial or to vacate the judgment (Code Civ. Proc., §§ 659, 663a, respectively) on the grounds that the judgment as phrased provided for a double recovery and that the judgment impermissibly awarded attorney fees on Royster’s mechanic’s lien claim. Those motions were denied and the court ruled that Royster was entitled to recover attorney fees against the mechanic’s lien release bonds. Appellants raise three issues on appeal: (1) attorney fees are never recoverable on a mechanic’s lien claim, a rule which should apply even when recovery is sought against a section 3143 release bond; (2) it was error to award prejudgment interest of 10 percent on the mechanic’s lien claim when a rate of 7 percent was applicable; and (3) it was error to award prejudgment interest on the breach of contract claim at 10 percent when a rate of 7 percent was applicable.

Discussion

1. Recoverability of Attorney Fees Against the Release Bonds

Appellants do not dispute Royster’s entitlement to attorney fees on its contract cause of action since their agreement expressly provided for such fees. Instead, appellants challenge the court’s award of attorney fees against American’s release bond on the mechanic’s lien claim. Nor does Royster dispute that attorney fees are not recoverable in a mechanic’s lien action (Abbett Electric Corp. v. California Fed. Savings & Loan Assn. (1991) 230 Cal.App.3d 355, 359-360 [281 Cal.Rptr. 362], hereafter Abbett), but asks that we carve out an exception to this rule when recovery is sought against a release bond posted under section 3143. No reported decision has considered whether the bar against recovering attorney fees on a mechanic’s lien claim *1165 applies when a release bond has been filed under section 3143. We conclude that it does. 6

Though the statutory scheme for mechanic’s liens at one time provided for the recovery of attorney fees, that provision was declared unconstitutional in Builders’ Supply Depot v. O’Connor (1907) 150 Cal. 265, 268 [88 P. 982], Since no similar provision was ever later enacted, it is “black letter law that except for any cause of action on a contract between the lien claimant and the owner of the improved property which provides for fees, a lienholder has no entitlement to them from the owner. . . . [¶] . . . [I]f indeed a contract exists, then that is the separate source of attorney’s fees; it is not the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torres v. Superior Court CA2/5
California Court of Appeal, 2021
2 Ton Plumbing, L.L.C. v. Thorgaard
2015 UT 29 (Utah Supreme Court, 2015)
Palomar Grading v. Wells Fargo
California Court of Appeal, 2014
Palomar Grading & Paving, Inc. v. Wells Fargo Bank, N.A.
230 Cal. App. 4th 686 (California Court of Appeal, 2014)
T.O. IX, LLC v. Superior Court
165 Cal. App. 4th 140 (California Court of Appeal, 2008)
People v. SPEEDEE OIL CHANGE SYSTEMS
54 Cal. Rptr. 3d 225 (California Court of Appeal, 2007)
People ex rel. Department of Corps. v. Speedee Oil Change Systems, Inc.
147 Cal. App. 4th 424 (California Court of Appeal, 2007)
National Technical Systems v. Superior Court
118 Cal. Rptr. 2d 465 (California Court of Appeal, 2002)
Department of Forestry & Fire Protection v. LeBrock
117 Cal. Rptr. 2d 790 (California Court of Appeal, 2002)
Campbell v. Scripps Bank
93 Cal. Rptr. 2d 635 (California Court of Appeal, 2000)
Wm. R. Clarke Corp. v. Safeco Insurance of America
938 P.2d 372 (California Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
40 Cal. App. 4th 1158, 47 Cal. Rptr. 2d 684, 95 Cal. Daily Op. Serv. 9320, 95 Daily Journal DAR 16178, 1995 Cal. App. LEXIS 1186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royster-construction-co-v-urban-west-communities-calctapp-1995.