National Technical Systems v. Superior Court

118 Cal. Rptr. 2d 465, 97 Cal. App. 4th 415, 2002 Daily Journal DAR 3623, 2002 Cal. Daily Op. Serv. 2980, 2002 Cal. App. LEXIS 3647
CourtCalifornia Court of Appeal
DecidedApril 4, 2002
DocketB152512
StatusPublished
Cited by11 cases

This text of 118 Cal. Rptr. 2d 465 (National Technical Systems v. Superior Court) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Technical Systems v. Superior Court, 118 Cal. Rptr. 2d 465, 97 Cal. App. 4th 415, 2002 Daily Journal DAR 3623, 2002 Cal. Daily Op. Serv. 2980, 2002 Cal. App. LEXIS 3647 (Cal. Ct. App. 2002).

Opinion

Opinion

KLEIN, P. J.

Plaintiff National Technical Systems (NTS) seeks a writ of mandate directing respondent superior court to vacate its order granting certain motions in limine filed by defendant and real party in interest United Pacific Insurance Company (UPIC or the surety) and to enter a new order denying the motions.

In this action, NTS, a subcontractor, seeks to enforce a stop notice release bond against UPIC, the bond surety. The trial court’s rulings preclude NTS from presenting evidence of the prior trial or judgment it obtained against the general contractor, and from presenting evidence regarding its attorney fees and statutory interest penalties. The issues presented are whether the *418 surety is bound by the judgment in the prior action against its principal to which the surety was not a party, and whether the surety’s liability on the stop notice release bond extends to attorney fees and statutory penalties.

We conclude the surety is not bound by the earlier judgment against its principal and therefore UPIC is not bound by the provisions in that judgment awarding attorney fees and statutory penalties to NTS. However, a surety’s liability on the bond is commensurate with that of its principal. Therefore, upon an appropriate showing, NTS may recover attorney fees and statutory penalties against UPIC. The petition is granted with directions.

Factual and Procedural Background

1. The prior action.

On April 9, 1996, Commercial Contractors, Inc. (the general contractor) entered into a contract with the City of Long Beach (the city), a public entity, to perform remediation and excavation work in the Port of Long Beach. 1 On April 16, 1996, the general contractor hired NTS as a subcontractor on the project.

NTS claimed it was only partially paid for services rendered to the general contractor, and on March 21, 1997, NTS filed a stop notice with the city in the amount of $343,905. 2

On April 8, 1997, the general contractor obtained a stop notice release bond from UPIC, the surety, in the sum of $429,881 to release money withheld on the stop notice. On April 30, 1997, UPIC notified NTS that the general contractor had filed a bond to release money withheld on the stop notice.

Although NTS was aware of UPIC’s issuance of the bond, on May 17, 1997, NTS filed suit against the general contractor (NTS v. CCI (Super. Ct. L.A. County, 1997, No. NC021319)), seeking damages on the contract, *419 enforcement of the stop notice, and recovery on the bond, without naming the surety.

On or about January 31, 1999, on the eve of trial, NTS moved for leave to file a second amended complaint to add UPIC as a party and to add a new cause of action for recovery on the bond “so that it may avail itself of the summary proceeding provided by . . . section 996.440 [of the California Bond and Undertaking Law (Code Civ. Proc., § 995.010 et seq.] [¶] Otherwise, [plaintiff] will be required to file a separate civil action against [the general contractor] and the Surety to recover on the Bond.” 3

The general contractor opposed the motion to amend, arguing UPIC had not participated in any manner during the course of the litigation and that it would be unduly prejudicial to UPIC to force it to defend itself on the eve of trial. The trial court denied leave to amend because trial was imminent and UPIC had not been involved in any of the discovery or other trial preparation in the action. The matter came on for a jury trial, the amount due and owing from the general contractor to NTS was litigated, and the trial court entered judgment in favor of NTS. Neither party appealed.

On October 11, 1999, NTS made demand upon UPIC for payment of $466,552, including the damages award of $178,631, prejudgment interest, $204,468 in attorney fees, and statutory interest penalties pursuant to Business and Professions Code section 7108.5 of 2 percent per month.

UPIC refused to pay. It advised NTS by letter that it “was never served with the lawsuit or made a party to the lawsuit. The first notice of claim was [the subcontractor’s] letter of October 11, 1999. The verdict does not mention either the stop notice, the [city] or [the surety]. [The subcontractor’s] judgment is only against [the general contractor], [¶] . . . [¶] While we do not require that you file an action to enforce your rights, [the surety] is not bound by the judgment.... There is no basis at this time to make payment to your client. If your client seeks to enforce its rights on the stop notice release bond, [the surety] will have the opportunity to assert all the relevant defenses on the claim. . . .”

On March 14, 2000, NTS filed a motion for summary enforcement of the judgment against UPIC pursuant to section 996.440. NTS asserted that having obtained a judgment against the general contractor, and the judgment having become final, NTS was now entitled to enforce the judgment against the surety.

*420 On April 18, 2000, the trial court denied NTS’s motion for summary enforcement against UPIC of the judgment NTS had obtained against the general contractor. NTS appealed.

In National Technical Systems v. Commercial Contractors, Inc. (2001) 89 Cal.App.4th 1000 [108 Cal.Rptr.2d 67], this court affirmed the order denying NTS’s motion for summary enforcement of the judgment. Because the issuance of the stop notice release bond preceded the filing of the lawsuit, the bond was not “given in an action or proceeding,” and hence, the summary enforcement procedure of section 996.440 was inapplicable. Instead, because the bond preceded the lawsuit, the surety had a right to be joined as a party and to defend the action. (§ 996.430.) NTS’s failure to join UPIC as a party to the action barred NTS from summarily enforcing the judgment against UPIC. Therefore, NTS would have to litigate the liability on the bond as against UPIC. (National Technical Systems, supra, 89 Cal.App.4th at p. 1011.)

2. The instant action.

On March 1, 2000, during the pendency of NTS’s prior action against the general contractor, NTS filed the instant action against the surety (NTS v. UPIC (Super. Ct. L.A. County, 2000, No. NC027374)). NTS alleged causes of action for (1) recovery on the stop notice release bond and (2) breach of the written bond contract between the general contractor and UPIC, which had been issued for NTS’s benefit.

On or about January 30, 2001, UPIC filed two motions in limine. The first motion sought to preclude evidence of the previous trial and judgment against the general contractor on the ground that UPIC was not named as a party to the prior action and therefore UPIC was not bound by NTS’s judgment against the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Grand Corp. v. Malibu Hillbillies, LLC
California Court of Appeal, 2019
United Grand Corp. v. Malibu Hillbillies, LLC
248 Cal. Rptr. 3d 294 (California Court of Appeals, 5th District, 2019)
American Master Lease v. Idanta Partners CA2/7
California Court of Appeal, 2014
Granite Construction v. Bond Safeguard Ins. CA3
California Court of Appeal, 2014
Pierce v. Western Surety Co.
207 Cal. App. 4th 83 (California Court of Appeal, 2012)
First National Insurance v. Cam Painting, Inc.
173 Cal. App. 4th 1355 (California Court of Appeal, 2009)
McAlpine v. Zangara Dodge, Inc.
2008 NMCA 064 (New Mexico Court of Appeals, 2008)
Scott Co. v. United States Fidelity & Guaranty Insurance
132 Cal. Rptr. 2d 89 (California Court of Appeal, 2003)
People v. Bernal
123 Cal. Rptr. 2d 622 (California Court of Appeal, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
118 Cal. Rptr. 2d 465, 97 Cal. App. 4th 415, 2002 Daily Journal DAR 3623, 2002 Cal. Daily Op. Serv. 2980, 2002 Cal. App. LEXIS 3647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-technical-systems-v-superior-court-calctapp-2002.