Jew v. Pacific Employers Insurance

196 Cal. App. 2d 310, 16 Cal. Rptr. 542, 1961 Cal. App. LEXIS 1579
CourtCalifornia Court of Appeal
DecidedOctober 16, 1961
DocketCiv. 25500
StatusPublished
Cited by3 cases

This text of 196 Cal. App. 2d 310 (Jew v. Pacific Employers Insurance) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jew v. Pacific Employers Insurance, 196 Cal. App. 2d 310, 16 Cal. Rptr. 542, 1961 Cal. App. LEXIS 1579 (Cal. Ct. App. 1961).

Opinion

WOOD, P. J.

This is an action against the surety on a building contractor’s bond. Plaintiffs appeal from a summary judgment in favor of the defendant surety.

The complaint alleged that on August 12, 1957, plaintiffs entered into a written agreement with the J. W. Janes Construction Company whereby that company agreed (1) to construct a building for plaintiffs according to certain plans and specifications for $61,717, and (2) to complete the work within a reasonable time; that to secure the faithful perform *? anee of the agreement, the company, as principal, and the defendant, as surety, executed their bond in said amount for the benefit of plaintiffs; the construction company failed to faithfully perform the building contract; about January 2, 1959, the Sullivan Electric Company commenced an action against the plaintiffs herein and the construction company for goods delivered and services rendered; in that action the plaintiffs herein filed a cross-complaint against thé construction company to recover damages in the amount of $30,000 for the negligent manner in which the company constructed the building, and for its failure to complete the building within a reasonable time; it was adjudged therein that plaintiffs herein recover $23,224.34 and costs from the construction company as damages for the faulty, negligent, unskillful, and delayed performance of the building contract; the judgment, which was entered on March 1, 1960, remains wholly unpaid; by reason thereof, the defendant, as surety, is liable to plaintiffs on said bond for the amount of the unpaid judgment.

In the present action the defendant insurance company admitted, in its answer, that the construction company failed to faithfully perform the contract, and the plaintiffs herein obtained said judgment against the construction company; and the defendant herein denied that it is liable for the payment of the judgment or any other amount. Defendant alleged, as a separate defense, that plaintiffs’ action herein was not instituted within the time required by provisions of the bond.

In support of its motion for a summary judgment, the defendant filed an affidavit of its attorney, Mr. Van Tassel. That affidavit was in substance, as follows: The copy of the bond attached to the complaint is a correct copy of the contract bond executed by the defendant. The coverage provided in the bond was subject to conditions, one .of which (fifth condition) was, as follows: “That no suit, action or proceeding to recover on this bond shall be sustained unless the same be commenced within six months from the completion of said structure or work of improvement, as ‘completion’ is defined in Section 1193.1 of the Code of Civil Procedure of California. Any notice to the Surety may be addressed to or served upon it at its office at 1033 So. Hope Street, Los Angeles, California.” On August 28, 1958, a notice of com-■ pletion, executed by plaintiffs, was recorded in the office of the Recorder of Los Angeles County, a copy of which notice is attached to the answer of defendant. On September 9, 1960, *313 defendant served upon plaintiffs interrogatories to be answered by plaintiffs. The answers to the interrogatories were received by the affiant on November 23, 1960. In those answers, the plaintiffs admit “the occupancy and use of their building since September of 1958,” and they admitted therein that the last work performed upon their building by the construction company or any of its contractors was performed in April 1959. Plaintiffs’ action was not instituted until April 22, 1960, and accordingly was not commenced within six months from completion of the building.

In opposition to the motion, Mr. Jew stated in his affidavit, as follows: That although he executed the notice of completion, a copy of which is attached to defendant’s answer, and although he did occupy and use the building since September 1958, he had done so with the understanding and assurance that the major defects existing in the building would be corrected by the construction company. Attempts to correct the defects were made by the company and its subcontractors to and including April 1959, or more than six months after the notice of completion was recorded and more than six months after occupancy and use of the building by affiant. Subsequent to the recording of the notice of completion on August 28,1958, and to the occupancy and use of the building in September 1958, various claims and mechanics’ liens were filed against affiant’s property by subcontractors. Defendant had notice of the claims and liens, and it had assured affiant that all claims and liens would be taken care of to the satisfaction of affiant. Defendant ultimately compromised and settled said claims and liens by April 1959, or more than six months after the notice of completion was recorded and more than six months after the occupancy and use of the building by affiant. In the meantime, about January 12, 1959, the Sullivan Electric Company, a subcontractor, commenced an action against affiant and the construction company for goods delivered and services performed. Affiant filed a cross-complaint against the construction company on January 22, 1959, and served it on that company, within six months of the recordation of the completion notice and within six months of the occupancy and use of the building by affiant. Defendant had notice of the action on the complaint and cross-complaint, but it did not defend the construction company in said action. Judgment therein for $1,055 was rendered in favor of the electric company and against the construction company, and judgment for $23,538.34 was rendered in favor of affiant and *314 against the construction company. The judgment for $1,055 was paid by the construction company, but no part of the judgment in favor of affiant has been paid.

In opposition to the motion, Mr. Kwan, attorney for plaintiffs, stated in his affidavit, as follows: On February 16, 1959, a conference was held at plaintiffs’ premises (the building involved here), and those present at that time were Mr. Jew, Mr. Van Tassel who is the attorney for defendant, Mr. Janes of the Janes Construction Company, and Mr. Sullivan of the Sullivan Electric Company which was a subcontractor. Those persons were taken on a tour through the building, and patent defects in the workmanship were pointed out by Mr. Jew. During that conference, Mr. Janes promised and assured the affiant and Mr. Jew that any defects, including defects in the roof deck, the warehouse floor, the conveyor unit, the electrical equipment, and the walls would be corrected. Mr. Van Tassel assented to Mr. Janes’ statements and urged him to correct those defects.

Defendant’s motion for summary judgment was granted, and the judgment provided that plaintiffs take nothing and that defendant recover its costs.

Appellants contend that the court erred in finding there is no triable issue of fact. They assert that the motion for summary judgment was based on the theory that the “appellants are barred from instituting an action” against the surety by the provisions of the fifth condition in the bond. As above stated, that condition was, in part: “That no suit, action or proceeding to recover on this bond shall be sustained unless the same be commenced within six months from the completion of said structure or work of improvement, as ‘completion’ is defined” in section 1193.1 of the Code of Civil Procedure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Technical Systems v. Superior Court
118 Cal. Rptr. 2d 465 (California Court of Appeal, 2002)
All Bay Mill & Lumber Co., Inc. v. Surety Co.
208 Cal. App. 3d 11 (California Court of Appeal, 1989)
Honolulu Roofing Co. v. Felix
426 P.2d 298 (Hawaii Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
196 Cal. App. 2d 310, 16 Cal. Rptr. 542, 1961 Cal. App. LEXIS 1579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jew-v-pacific-employers-insurance-calctapp-1961.