Kalfountzos v. Hartford Fire Insurance Co.

37 Cal. App. 4th 1655, 44 Cal. Rptr. 714, 44 Cal. Rptr. 2d 714, 95 Cal. Daily Op. Serv. 6902, 95 Daily Journal DAR 11791, 1995 Cal. App. LEXIS 841
CourtCalifornia Court of Appeal
DecidedAugust 30, 1995
DocketC019445
StatusPublished
Cited by7 cases

This text of 37 Cal. App. 4th 1655 (Kalfountzos v. Hartford Fire Insurance Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kalfountzos v. Hartford Fire Insurance Co., 37 Cal. App. 4th 1655, 44 Cal. Rptr. 714, 44 Cal. Rptr. 2d 714, 95 Cal. Daily Op. Serv. 6902, 95 Daily Journal DAR 11791, 1995 Cal. App. LEXIS 841 (Cal. Ct. App. 1995).

Opinion

Opinion

NICHOLSON, Acting P. J.

A subcontractor on a public works project sued the general contractor for money claimed due. The subcontractor also *1657 sued the surety on the contractor’s payment- and stop-notice release bonds. At trial, the subcontractor asserted the surety could not raise the contractor’s defenses and setoffs because the contractor was in corporate suspense because of nonpayment of franchise fees and could not defend itself in court. We affirm the trial court’s judgment in favor of the surety. A surety, under these circumstances, can assert defenses and setoffs to the underlying obligation, even though the contractor who obtained the bond is disabled legally.

Facts and Procedure

We quote from the trial court’s statement of decision those portions relevant to this appeal:

“This action originally arose out of a dispute between R.D. Hart, Inc., (Hart) a general engineering contractor, and Nikiforos Kalfountzos (Kalfountzos), an electrical subcontractor doing business as Engineered Electric (Engineered). Engineered was Hart’s electrical subcontractor on a public works construction project (Project) for the benefit of the Sacramento Regional County Sanitation District (District). The Project involved construction of an addition to the District’s waste water treatment plant in 1984. Hartford Fire Insurance Co. is a party by reason of several bonds that were issued in connection with the Project.
“Hart was awarded the general contract by competitive bid and in turn accepted Engineered’s subcontract bid for electrical work on the Project in the amount of $68,000. Engineered initially refused to sign a subcontract and obtain required bonds. As a consequence Hart obtained another electrical subcontractor Rich Electric to commence the electrical subcontract work. Engineered then protested the Rich Electric contract and after a hearing before a county hearing officer signed the subcontract and obtained the necessary bonds.
“Engineered then commenced work on the Project. As the Project was a public works project, all contractors were required by law to pay their employees prevailing wages established by the California Department of Industrial Relations. Subcontractors were required to submit certified payroll records to demonstrate compliance with the prevailing wage requirements. Engineered refused to submit certified payroll records and Hart in turn refused to pay Engineered. Ultimately after a hearing before a county hearing officer in March 1986, Engineered was removed as a subcontractor from the Project. Because of Engineered’s failure to pay prevailing wages, funds were withheld from Hart by the District under the Project and penalties were imposed.
*1658 “After Engineered was removed, Hart completed the electrical subcontract work. Hart then filed suit against Engineered for the cost of completing and redoing portions of the electrical work. Engineered cross-complained against Hart and its sureties seeking unpaid progress payments and claims for extra work.
“Hart did not appear at the first trial because it had gone out of business. Its corporate status had been suspended for nonpayment of franchise fees. Hartford, the surety, did appear. However, the trial court entered Hart’s default and further ruled that Hartford was bound by the default of its principal Hart. . . . [T]he court ultimately refused to enter judgment for Engineered on the cross-complaint against Hartford. It concluded that the illegality of not paying prevailing wages precluded recovery on the subcontract or in quantum meruit.
“On appeal the trial court was reversed and the matter remanded for further proceedings. [Kalfountzos v. Hartford Fire Ins. Co. (Mar. 30, 1993) C012438 [nonpub. opn.].] The appellate court found that the trial court erred in ruling that the subcontract was illegal in its entirety. It concluded that the Legislature intended that statutory penalties were the exclusive remedy for the failure to pay prevailing wages. The appellate court declined to decide as premature the ‘interesting legal issue’ raised by Hartford in a cross-appeal of the trial court’s determination that Hartford was bound by the default of Hart.
“On remand the trial judge for the first trial recused himself and the matter was reassigned to this trial department. The initial issue is whether Hartford can defend the action in view of the failure of Hart to appear at trial and Hart’s failure to pay its corporate franchise taxes.
“Hartford’s liability, if any, is as a surety by reason of the payment and stop notice release bonds that were issued to Hart. As general contractor Hart provided a payment bond to the District for its benefit as well as all subcontractors on the Project.”

The trial court decided Hartford could assert Hart’s defenses and setoffs. Applying those defenses and setoffs, the court concluded Engineered was not entitled to recover under the subcontract with Hart and that, therefore, Hartford was entitled to judgment against Engineered. Engineered appeals.

Discussion

The general rule is that a surety may raise all defenses that would be allowed the principal. (Flickinger v. Swedlow Engineering Co. (1955) 45 *1659 Cal.2d 388, 394 [289 P.2d 214].) The surety must pay on the bond only if the claimant establishes, without reference to the bond, a legal obligation on the part of the principal to pay. (Lewis & Queen v. N. M. Ball Sons (1957) 48 Cal.2d 141, 155 [308 P.2d 713].)

“The obligation of a surety must be neither larger in amount nor in other respects more burdensome than that of the principal; and if in its terms it exceeds it, it is reducible in proportion to the principal obligation.” (Civ. Code, § 2809.) “Therefore, since the liability of a surety is commensurate with that of the principal, where the principal is not liable on the obligation, neither is the guarantor.” (U.S. Leasing Corp. v. duPont (1968) 69 Cal.2d 275, 290 [70 Cal.Rptr. 393, 444 P.2d 65].)

The “obligation,” as referred to in Civil Code section 2809 and U.S. Leasing Corp., is the obligation the principal (Hart) originally undertakes as to the creditor (Engineered). Here, the obligation was defined in the subcontract between Hart and Engineered. Since the surety is not liable to the creditor unless liability arises under the obligation, the surety may raise any defenses or setoffs, with respect to the obligation, to reduce or eliminate the amount due on the bond, even though the principal, as here, is precluded from raising those defenses and setoffs because of a legal disability having nothing to do with the validity of the defenses and setoffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perez v. Century Indemnity Co. CA1/2
California Court of Appeal, 2024
Cadle Co. v. World Wide Hospitality Furniture, Inc.
50 Cal. Rptr. 3d 480 (California Court of Appeal, 2006)
Reliance Insurance Company v. Superior Court
100 Cal. Rptr. 2d 807 (California Court of Appeal, 2000)
Wm. R. Clarke Corp. v. Safeco Insurance of America
938 P.2d 372 (California Supreme Court, 1997)
Royster Construction Co. v. Urban West Communities
40 Cal. App. 4th 1158 (California Court of Appeal, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cal. App. 4th 1655, 44 Cal. Rptr. 714, 44 Cal. Rptr. 2d 714, 95 Cal. Daily Op. Serv. 6902, 95 Daily Journal DAR 11791, 1995 Cal. App. LEXIS 841, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kalfountzos-v-hartford-fire-insurance-co-calctapp-1995.