Card Construction Co. v. Ledbetter

16 Cal. App. 3d 472, 94 Cal. Rptr. 570, 1971 Cal. App. LEXIS 1602
CourtCalifornia Court of Appeal
DecidedMarch 31, 1971
DocketCiv. 10183
StatusPublished
Cited by14 cases

This text of 16 Cal. App. 3d 472 (Card Construction Co. v. Ledbetter) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Card Construction Co. v. Ledbetter, 16 Cal. App. 3d 472, 94 Cal. Rptr. 570, 1971 Cal. App. LEXIS 1602 (Cal. Ct. App. 1971).

Opinion

*475 Opinion

AULT, J.

Card Construction Company, Inc. (Card) appeals from a judgment of dismissal entered after demurrers to the complaint by respondents, Ledbetter & Son (Ledbetter) and San Diego Pacific Rentals (Pacific), had been sustained without leave to amend. The original complaint was brought by Card and its bonding company, Insurance Company of North America (I.N.A.).

The dispute arises out of a contract and a series of subcontracts for work performed on a state improvement project and centers upon the legal effect of certain releases executed by respondents Ledbetter and Pacific. It is also concerned with the legal effect of a previous lawsuit in which all the parties to this litigation appeared.

For purposes here, the facts are not in dispute. In March 1967, Pylon, Inc. (Pylon), as general contractor, entered into a written contract with the State of California, acting by and through the Department of Water Resources, to construct a public improvement described as the San Diego Desalted Water Transmission Facility, for a consideration of $192,240.36. In April 1967, Pylon entered into a written subcontract with plaintiff Card under which Card agreed to perform a portion of the work covered by the prime contract between Pylon and the State for the sum of $103,913.80. Card, in turn, subcontracted a portion of its work to John F. Butler and John D. Couchman, doing business as Wymore Construction Co., Inc. (Wymore), on a time and material basis. Wymore again subcontracted a portion of its work to Ledbetter on a time plus 10 percent of gross billing basis.

In September 1967, after the work on the project had been completed, Ledbetter, who had furnished labor, equipment and material on the project, and Pacific, who had furnished materials, signed releases in which they represented they had been paid in full for all labor, equipment and materials furnished on the construction project. The releases were given to Wymore and contained a statement they were signed “for the purpose of inducing” Card to pay Wymore’s billings. Wymore presented these releases to Card, and Card paid Wymore all sums due under its subcontract.

In fact, Wymore had not paid Ledbetter and Pacific and failed to pay either of them after it received payment from Card. Wymore was not bonded, defaulted in the ensuing litigation and is evidently judgment proof, Ledbetter and Pacific filed stop-notices with the State of California and with Pylon, the general contractor, and eventually sued everybody, including Pylon, its bonding company, Great American Insurance Company (Great American), Card, and the State of California. The complaint, *476 entitled “Complaint for Breach of Contract: To Enforce Stop Notice and upon Statutory Payment Bond,” spawned a proliferation of cross-complaints between the various parties which the court severed and ordered tried after the complaint.

Ultimately Ledbetter and Pacific were awarded summary judgments against Great American, the bonding company for Pylon, the general contractor. At the same time it was ordered that “Plaintiffs take nothing by reason of their complaint against the other defendants,” which included Card.

Because of its written agreement of indemnity with Great American, Pylon paid the judgments. It then obtained judgment for the amount it had paid on its cross-complaint against Card and I.N.A., who now have paid and satisfied Pylon’s judgment against them.

Card and I.N.A., as plaintiffs in the instant action, sought to recoup their loss from Ledbetter and Pacific. Their six-count complaint (three causes of action against each defendant) alleges alternative theories of recovery based upon: (1) intentional misrepresentation, (2) negligent misrepresentation, and (3) implied indemnity.

The issues raised on appeal are: 1. Did the complaint state a cause of action in implied indemnity? 2. Did the previous action operate as a bar under the doctrines of res judicata or collateral estoppel, or by reason of the compulsory cross-complaint statute? (Code Civ. Proc., § 439.)

All parties agree the basic theory underlying the complaint is implied indemnity. The three causes of action only attempt to state a cause of action for recovery under implied indemnity on different theories.

In the complaint, Card and I.N.A. (to whom Card is ultimately financially responsible under a bonding indemnity agreement) claim Led-better and Pacific, by intentionally giving false and untrue releases to Wymore, or by negligently giving such releases, have, in effect, caused them to pay twice for the same labor and material. Card paid on the first occasion when it paid Wymore upon the presentation of the releases. Card and I.N.A. paid again when they were compelled to satisfy Pylon’s judgment.

In the previous superior court action, Ledbetter and Pacific obtained judgment against Great American, the bonding company for Pylon, the general contractor. In that action, based upon the statutory bond, the releases previously given were wholly immaterial and could not be successfully urged as a defense by the bonding company. (See Powers Regulator Co. v. Seaboard Surety Co., 204 Cal.App.2d 338, 346-353 [22 Cal.Rptr. *477 373]; Sherman v. American Surety Co., 178 Cal. 286, 292 [173 P. 161]; 41 Cal.Jur.2d, Public Works and Contracts, § 77, p. 453.) By reason of its bonding indemnity agreement, Great American shifted the burden of the judgment to its principal, Pylon, who, by virtue of its contractual relation with Card and I.N.A., was able to shift the burden of paying respondents’ judgments to them. Asserting the loss was occasioned by the giving of the false releases, Card claims the right to. indemnity from Led-better and Pacific and seeks to recover the amount paid to satisfy Pylon’s judgment together with interest and attorney’s fees.

Although not fitting precisely within usual patterns, we believe Card and I.N.A. stated a cause of action for indemnity against Ledbetter and Pacific on each of the alternative grounds. In Alisal Sanitary Dist. v. Kennedy, 180 Cal.App.2d 69, 75-76 [4 Cal.Rptr. 379], the court states:

“ ‘The right of indemnity rests upon a difference between the primary and secondary liability of two persons each of whom is made responsible by the law to an injured party. It is a right which enures to a person who, without active fault on his part, has been compelled by reason of some legal obligation, to pay damages occasioned by the initial negligence of another, and for which he himself is only secondarily liable. The difference between primary and secondary liability is not based on a difference in degrees of negligence or on any doctrine of comparative negligence—a doctrine which, indeed, is not recognized by the common law; ... It depends on a difference in the character or kind of the wrongs which cause the injury and in the nature of the legal obligation owed by each of the wrongdoers to the injured person. . . .’”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson Private Investors v. Colak CA2/2
California Court of Appeal, 2013
Wal-Mart Stores, Inc. v. RLI Insurance
163 F. Supp. 2d 1025 (W.D. Arkansas, 2001)
County of Contra Costa v. KAISER FOUND. HEALTH
47 Cal. App. 4th 237 (California Court of Appeal, 1996)
County of Contra Costa v. Kaiser Foundation Health Plan, Inc.
47 Cal. App. 4th 237 (California Court of Appeal, 1996)
Christian v. County of Los Angeles
176 Cal. App. 3d 466 (California Court of Appeal, 1986)
People Ex Rel. Department of Transportation v. Superior Court
608 P.2d 673 (California Supreme Court, 1980)
Pena v. Sita World Travel, Inc.
88 Cal. App. 3d 642 (California Court of Appeal, 1978)
E. L. White, Inc. v. City of Huntington Beach
579 P.2d 505 (California Supreme Court, 1978)
Gardner v. Murphy
54 Cal. App. 3d 164 (California Court of Appeal, 1975)
People Ex Rel. Department of Public Works v. Daly City Scavenger Co.
19 Cal. App. 3d 277 (California Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
16 Cal. App. 3d 472, 94 Cal. Rptr. 570, 1971 Cal. App. LEXIS 1602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/card-construction-co-v-ledbetter-calctapp-1971.