Bowman v. Santa Clara County

315 P.2d 67, 153 Cal. App. 2d 707, 1957 Cal. App. LEXIS 1546
CourtCalifornia Court of Appeal
DecidedSeptember 11, 1957
DocketCiv. 17247
StatusPublished
Cited by9 cases

This text of 315 P.2d 67 (Bowman v. Santa Clara County) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowman v. Santa Clara County, 315 P.2d 67, 153 Cal. App. 2d 707, 1957 Cal. App. LEXIS 1546 (Cal. Ct. App. 1957).

Opinion

WOOD (Fred B.), J.

Plaintiff Sherrol Bowman brought this action against the county, a sanitation district, an improvement district within the sanitation district, and Manuel Smith, general contractor, for compensation for certain trench digging work plaintiff performed as a subcontractor.

*710 On the day that he started work (July 28, 1953) plaintiff prepared and he and Smith signed a written memorandum which said merely “Dig ditch for 18" x 21" x 24" pipe at 50$ per foot,” identifying the job simply by the words, “Address of Job: Milpitas, Calif.”

The court overruled defendants’ contention that this, was a fully integrated contract which was unambiguous in its terms and that none of the negotiations that led up to it and no terms not expressed in it could be considered.

Plaintiff Bowman testified that he was engaged in the business of sewer contracting. In July of 1953 Smith came to Bowman’s house with the plans for the ditch and wanted to know if Bowman had a machine with which he could dig ditches big enough to install a 24 inch pipe. Bowman said he had such a machine. Smith asked what Bowman would dig the ditch for and said Bowman would have to dig 400 feet a day. Bowman “meditated a little while and then I told him I’d dig it for fifty cents a foot. ‘Now, remember,’ he [Smith] says, ‘I’ve got to have 400 feet a day.’ ” About a week later Smith returned and told Bowman to go ahead, telling the latter he would have to dig 400 feet a day.

Bowman also testified that 400 feet per day was an average rate of production in his business and “that is on what we base our figures.”

The work started on the 28th of July. During that day the written portion of the agreement was signed. Prom then until August 21, when Bowman quit, there were numerous delays, resulting in an average rate of production of only 100 feet per day. On one occasion he was required to move his machine from one end of the job to the other to dig a test hole. He was unable to dig any ditch that day. On occasion he would dig 25 feet and then Smith would stop him for the rest of the day. He said the interruptions were caused by Smith’s failure to have enough men and materials to do the bracing of the trench behind the machine as the digging proceeded. It was usual and customary for the general contractor to do the bracing.

Two men were on the job each working day between July 28 and August 21, an operating engineer and an oiler employed by plaintiff. The plaintiff substituted on occasion when the engineer did not show up.

Plaintiff said he pulled off the job on August 21 because of the shutdowns, Smith’s refusal at that time to pay for the same, and the resulting failure to dig enough to make expenses.

*711 In a few days plaintiff received a letter from Smith’s attorney demanding that plaintiff resume work. On the 28th of August plaintiff returned to the job, writing Smith in part as follows: “I stopped digging on this job about Friday, August 21st, for the reason that your superintendent continually kept me from going ahead with the work. We would go a few feet and then be stopped. We cannot keep men and equipment idle on the job and dig ditches at $.50 per foot. I have, pursuant to your demand, commenced digging ditches on this job again today. Hereafter unless we are permitted to proceed continually with the ditch digging, we will charge any time that we are stopped from digging a rate per hour as the cost would be were we permitted to proceed according to the number of feet per hour we would normally work at $.50 per foot. Therefore, in the future it will be necessary to bill you and I will so bill you at this rate for the amount of time each day that we are prevented from proceeding with the regular digging.”

There were further interruptions in the work from then on, from the same causes, in respect to which plaintiff billed Smith at the rate of $17 per hour (which plaintiff testified was a reasonable rate of compensation) and a few hours of showup time (two hours pay per man, required by union rules when a man reports for work and then is told there is no work for the day) at $5.21 per hour.

This evidence was admissible. It did not vary the writing, which merely specified the rate of pay per lineal foot and did not represent a complete integration of the agreement. Its incompleteness appeared upon the face of the writing. It left various important elements unexpressed. Where was this trench to be dug? Between what points and along what course? How deep was it to be? When was the work to commence? Was it to be completed within a limited period of time? What was the required rate of progress, if any per day? The answers to many of these questions, doubtless, would be furnished by the sanitation district’s plans and specifications. The required rate of progress, Bowman’s testimony showed, was 400 lineal feet per day. It was not in conflict with the portion of the contract which they put in writing, a piece price rate, 50 cents per lineal foot.

The parol evidence rule applies [w]hen the terms of an agreement have been reduced to writing.”' (Code Civ. Proc., § 1856.) It sometimes happens, as in this case, that the parties put in writing only a portion of their agreement. *712 In such a case it is competent to prove the unwritten portion if not inconsistent with the written portion of the agreement. “ It has long been the rule that when the parties have not incorporated into an instrument all of the terms of their contract, evidence is admissible to prove the existence of a separate oral agreement as to any matter on which the document is silent and which is not inconsistent with its terms. (Buckner v. A. Leon & Co., 204 Cal. 225, 227 [267 P. 693] [buyer of grapes deemed to have agreed to furnish lug boxes pursuant to local custom; the writing was silent on that subject] ; Crawford v. France, 219 Cal. 439, 443 [27 P.2d 645] [writing specified architect’s fee as a percentage of construction cost but was silent as to latter; parol evidence competent to show agreed limit of cost of construction] ; Stockburger v. Dolan, 14 Cal.2d 313, 317 [94 P.2d 33, 128 A.L.R. 83] [oral understanding that lessee under oil lease would procure a zone variance, provable by parol evidence because not inconsistent with written portion which was silent on that subject] ; Lindsay v. Mack, 5 Cal.App.2d 491, 496-497 [43 P.2d 350] [parol evidence rule does not apply to a collateral agreement upon which the instrument is silent and which does not purport to affect the terms of the instrument]; Gibson v. De La Salle Institute, 66 Cal.App.2d 609, 631-632 [152 P.2d 774

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wells Fargo Bank v. Kabbai CA4/1
California Court of Appeal, 2016
Scott Co. v. United States Fidelity & Guaranty Insurance
132 Cal. Rptr. 2d 89 (California Court of Appeal, 2003)
U. S. Industries, Inc. v. Vadnais
270 Cal. App. 2d 520 (California Court of Appeal, 1969)
Schwartz v. Shapiro
229 Cal. App. 2d 238 (California Court of Appeal, 1964)
Powers Regulator Co. v. Seaboard Surety Co. of New York
204 Cal. App. 2d 338 (California Court of Appeal, 1962)
Buffalo Arms, Inc. v. Remler Co.
179 Cal. App. 2d 700 (California Court of Appeal, 1960)
Noel v. Dumont Builders, Inc.
178 Cal. App. 2d 691 (California Court of Appeal, 1960)
Howard J. White, Inc. v. Varian Associates
178 Cal. App. 2d 348 (California Court of Appeal, 1960)
Mangini v. Wolfschmidt, Ltd.
331 P.2d 728 (California Court of Appeal, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
315 P.2d 67, 153 Cal. App. 2d 707, 1957 Cal. App. LEXIS 1546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowman-v-santa-clara-county-calctapp-1957.