Crawford v. France

27 P.2d 645, 219 Cal. 439, 1933 Cal. LEXIS 413
CourtCalifornia Supreme Court
DecidedNovember 28, 1933
DocketDocket No. L.A. 14381.
StatusPublished
Cited by25 cases

This text of 27 P.2d 645 (Crawford v. France) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crawford v. France, 27 P.2d 645, 219 Cal. 439, 1933 Cal. LEXIS 413 (Cal. 1933).

Opinion

THOMPSON, J.

This action was brought by an architect for a fee claimed to be due him under the terms of a written contract for professional services in connection with the construction of a hotel building. Judgment was rendered for the defendant and the plaintiff has appealed.

More specifically, the contract for the plaintiff’s services provided:

“(1) That the Architect is to design a hotel building suitable for the needs of the Owner; is to furnish all necessary preliminary sketches and estimates of cost; is to furnish complete working drawings, specifications and details necessary for the construction of such a hotel building.
(2) The Architect is to supervise all of the work committed to his control. The Architect is to carry all of the necessary administrative work required in the proper keeping of accounts, the issuance of certificates of payment and such superintendence of the work as is hereinafter mentioned.
*441 “(3) The Architect is to keep an inspector acceptable to the Owner on the work during the pouring of concrete or the erection of masonry construction. The cost of such an inspector is to be paid by the Architect.
“ (4) The Owner agrees that the Architect is to be paid for his services, the sum equal to six per cent of the cost of the work exclusive of the cost of the land, in installments as follows: % of the total fee based upon the estimated cost, on acceptance of preliminary drawings and estimates of cost; on completion of working drawings exclusive of details, a sum sufficient to bring the total payments to % of the total fee based on the estimated cost or upon the lowest reputable bids for construction; the balance, %, to be in installments as the work progresses.”

There was a fifth paragraph which required the owner to pay for surveys and borings and to make prompt statements of his requirements and decisions relating to the conduct of the work.

The plaintiff prepared plans and specifications for a thirty-room hotel which the defendant admits were satisfactory to him. Thereafter bids for its construction were sought and the lowest bid received was something over $61,000. The defendant thereupon abandoned the project because of the excessive cost of construction and refused to pay the plaintiff on the theory that he had failed to perform his part of the contract in the preparation of plans suitable to the needs of the defendant. This action was commenced on the written contract for the sum of $1963.50, % of the total fee based upon the lowest bid submitted, in accordance with the provisions of paragraph (4) of the contract.

The defendant’s answer contained a general denial and, in addition thereto, affirmative allegations of the oral agreement of the plaintiff to prepare plans and specifications for a hotel building which would not cost over $45,000; that the plaintiff failed to design a hotel building “suitable to the needs of the owner” since one of the defendant’s known needs was that the cost of construction should not exceed $45,000; and, predicating it upon these same facts, fraud in inducing the defendant to enter into the written contract.

At the trial defendant abandoned the defense of fraud “because proof constituting the elements of fraud was lacking”, but the defendant was allowed by the trial court to *442 introduce parol evidence of the prior conversation, conduct and acts of the parties for the purpose of proving the parol agreement as to the cost of the building. It is the appellant’s contention that this evidence was inadmissible except to substantiate the third affirmative defense of fraud, and that, after this defense had been abandoned, it could not properly be considered by either the court or the jury with respect to any of the remaining issues. It is urged as error that the trial court allowed the defendant to add by parol an “entirely new, distinct and independent clause” to the written contract. It is also urged that the defendant’s failure to make an affirmative showing and ask for the reformation of the contract on the ground of mistake precluded the introduction of any evidence in support of the omitted clause of the contract.

The appellant further complains of numerous instructions, refusals to give instructions and changes made by the trial' court in instructions offered by the plaintiff, which resulted in the jury’s being told that they might find that plaintiff and defendant had orally agreed that the plans and specifications were to be prepared for a building, the cost of construction of which was not to exceed $45,000, and, if they further found that the plaintiff had failed to furnish such plans and specifications, the defendant would not be bound to accept the plans and that unless he did accept or make use of them he would not be liable for the plaintiff’s services. One such instruction was as follows: “If you find that the plaintiff agreed to design a building so that the cost thereof should not exceed $45,000, there is the implied agreement that the architect cannot recover unless he performs his contract in this respect, and it is not necessary in order to produce this result that the parties should expressly agree that the architect should receive no pay in the event that he failed to perform this part of the agreement.”

The one question to be determined upon this appeal is whether it was proper to permit defendant to show the oral agreement limiting the cost of construction. Its solution depends upon whether the ease can be said to come within one of the recognized exceptions to the parol evidence rule upon which the appellant relies. Although a contract has been reduced to writing by the parties, parol evidence is admissible to show fraud, accident or mistake, to show *443 the omitted portion of the contract where the writing is incomplete on its face, and to clear up an ambiguity or uncertainty. (Ayers v. Southern Pac. R. R. Co., 173 Cal. 74, 81 [159 Pac. 144, L. R A. 1917F, 949]; and see note, 70 A. L. R 752, collecting cases.)

This evidence was offered to complete the written contract by adding a term which was obviously omitted and with which the appellant admittedly had not complied. The written contract was entirely silent as to cost of construction, the only subject which it covered with any degree of thoroughness being the architect’s fees and the manner of their payment, which fees, however, could not be determined until the estimated cost was ascertained. “It has long been the rule that when parties have not incorporated into an instrument all of the terms of their contract evidence is admissible to prove the existence of a separate oral agreement as to any matter on which the document is silent and which is not inconsistent with its terms. ...” (Buckner v. Leon & Co., 204 Cal. 225, 227 [267 Pac. 693].) Where it appears upon the face of the writing that it is incomplete, parol evidence may be received for the purpose of supplying the missing matter. “If the writing does not show upon its face it was intended to express the whole agreement between the parties, parol evidence is admissible to show other conditions or explain latent ambiguities. (Kreuzberger

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. City of Colton CA4/2
California Court of Appeal, 2015
In Re Amica, Inc.
130 B.R. 792 (N.D. Illinois, 1991)
Masterson v. Sine
436 P.2d 561 (California Supreme Court, 1968)
Pasqualetti v. Galbraith
200 Cal. App. 2d 378 (California Court of Appeal, 1962)
Caldwell v. United Presbyterian Church
180 N.E.2d 638 (Ashtabula County Court of Common Pleas, 1961)
Spurgeon v. Buchter
192 Cal. App. 2d 198 (California Court of Appeal, 1961)
Mangini v. Wolfschmidt, Ltd.
192 Cal. App. 2d 64 (California Court of Appeal, 1961)
Bowman v. Santa Clara County
315 P.2d 67 (California Court of Appeal, 1957)
American Industrial Sales Corp. v. Airscope, Inc.
282 P.2d 504 (California Supreme Court, 1955)
Bank of America National Trust & Savings Ass'n v. O'Shields
275 P.2d 153 (California Court of Appeal, 1954)
Chastain v. Belmont
271 P.2d 498 (California Supreme Court, 1954)
Langley v. Pacific Gas & Electric Co.
262 P.2d 846 (California Supreme Court, 1953)
Langley v. Pacific Gas & Elec. Co.
41 Cal. 2d 655 (California Supreme Court, 1953)
Ellis v. Klaff
216 P.2d 15 (California Court of Appeal, 1950)
Higgins v. Belson
168 P.2d 813 (Idaho Supreme Court, 1946)
Detsch & Co. v. American Products Co.
152 F.2d 473 (Emergency Court of Appeals, 1945)
Gibson v. De La Salle Institute
152 P.2d 774 (California Court of Appeal, 1944)
Spaulding v. Pardridge
83 P.2d 80 (California Court of Appeal, 1938)
Lindsay v. MacK
43 P.2d 350 (California Court of Appeal, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
27 P.2d 645, 219 Cal. 439, 1933 Cal. LEXIS 413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crawford-v-france-cal-1933.