Blackwood v. McCallum

203 P. 758, 187 Cal. 655, 1922 Cal. LEXIS 489
CourtCalifornia Supreme Court
DecidedJanuary 3, 1922
DocketS. F. No. 9441.
StatusPublished
Cited by9 cases

This text of 203 P. 758 (Blackwood v. McCallum) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blackwood v. McCallum, 203 P. 758, 187 Cal. 655, 1922 Cal. LEXIS 489 (Cal. 1922).

Opinion

SHURTLEFF, J.

This is an appeal by the defendants, J. H. McCallum and E. O. Benner, from a judgment against them and their codefendant, Hansbrough-Johnson Company, the latter not joining in the appeal.

The complaint alleges that on June 5, 1916, the plaintiff, as owner, entered into a building contract with the defendant Hansbrough-Johnson Company, whereby the latter agreed, for the price of $9,712, to erect for plaintiff a two-story frame residence upon a lot of land in San Francisco; that to secure the performance of said contract the Hansbrough-Johnson Company, as principal, and the appellants McCallum and Benner, as sureties, executed and delivered to plaintiff a bond in the penal sum of $4,856, conditioned that said Hansbrough-Johnson Company would in all respects comply with all the terms, covenants, and conditions of said contract and furnish the materials and perform the work according thereto, free of liens or claims arising out *657 of materials furnished or work performed thereunder; that said bond further stipulated that, in the event of any liens being filed upon the building or land upon which it was erected, arising from the performance of the work or furnishing of the materials, or in the event of plaintiff being compelled to pay any sums of money, for said work or materials, by reason of the failure of Hansbrough-Johnson Company to pay the same, then the said McCallum and Benner would repay plaintiff said sums, not exceeding the amount of the bond; that said building was completed on or prior to September 18, 1916, and that on said last-mentioned day notice of completion and acceptance was filed for record in the office of the county recorder of the city and county of San Francisco (this date is evidently a clerical error and should be December 15, 1916) ; that on January 17, 1917, two claims - of lien against the building and land for materials furnished and used in the construction of said building were filed for record and actions were commenced to foreclose them; that in each of these actions the plaintiff and Hansbrough-Johnson Company were named as defendants and were respectively served with the summons and a copy of the complaint in each of them; that the plaintiff appeared and answered in each action; that HansbroughJohnson Company made no appearance in either of said actions; that the actions were consolidated and tried; judgments rendered in favor of the claimants, the liens- foreclosed and the property ordered sold; that plaintiff was compelled to pay $250 for the services of attorneys in defending said actions; that prior to the commencement of said actions to foreclose said liens plaintiff had paid the defendant Hansbrough-Johnson Company all sums due and owing by him to said company for the work, labor, and materials furnished by it in the construction of said building, “save and except the sum of $746.30, which sum constituted a fund in plaintiff’s possession applicable to the payment pro tanto of said “final” judgments; that on December 4, 1918, in order to protect said building and property from an execution sale, plaintiff paid said judgments in full, amounting to $2,846.49, for which amount, and the said sum paid for the services of attorneys, less said $746.30, plaintiff asked judgment against the defendants.

*658 The appellants did not demur to the complaint, but answered, admitting, either expressly or by failure to deny the same, all the allegations of the complaint, except the following: Denied that the building was completed in accordance with said contract, but alleged that it was completed by said company in accordance with and pursuant to a new and different contract with plaintiff; denied that there is anything due or owing on account of the payment of said judgment or on any other account; denied that said $746.30 constitutes a fund in plaintiff’s possession for the purposes alleged in the complaint. The answer contains the further denial that the company completed the building “on the eighteenth day of September, 1916,” which is, in effect, an admission that it was completed upon some other date.

When plaintiff rested, the appellants moved for a nonsuit upon the ground that the building was not completed in accordance with the contract for the faithful performance of which they became sureties, but in accordance with or pursuant to a new and different agreement made between the plaintiff, and the Hansbrough-Johnson Company, which motion was denied, and we think properly so.

The court found upon all the issues raised by the answer as follows: That the building was completed on December 15, 1916, and “was not constructed or completed in accordance with or pursuant to a new contract with plaintiff, nor a contract different from the one of June 5, 1916, set forth in said complaint”; that there is due and owing from the defendants, J. H. McGallum and E. 0. Benner, and each of them, on account of the payment of the judgments referred to in plaintiff’s complaint, after crediting said sum of $746.30 thereon, a balance of $2,100.19 and interest. For these amounts, together with the said sum of $250, paid for attorney’s fees, as alleged and not denied, judgment was ordered and entered in favor of plaintiff, in accordance with the findings and conclusions of law.

Defendants raise the point in this court, and for the first time, that the complaint fails to state a cause of action in that it does not allege, either by setting forth the facts showing the same or in the manner permitted by the code (sec. 457, Code Civ. Proe.), that plaintiff has duly kept and performed the covenants and stipulations of the building con *659 tract which by its terms are to be kept and performed by him, and which performance appellant claims must be established in order for plaintiff to successfully maintain the action.

[1] But in order to fasten prima facie liability upon the defendants’ sureties under their bond, it was not essential for plaintiff to allege that he had performed the contract upon his part. Their undertaking was that HansbroughJohnson Company, not the plaintiff, would perform the agreement. Furthermore, they by the express terms of their bond agreed to pay all .liens placed upon plaintiff’s property arising from the performance of the work or the furnishing of materials in connection therewith, and it is the alleged breach of this condition that forms the foundation of the complaint and which breach we think is sufficiently pleaded to state a cause of action. If plaintiff was guilty of any act which would release, in whole or in part, the appellants’ obligation as sureties, it was an affirmative defense to be specially pleaded by them, which was not done.

The answer wholly failed to plead any facts showing that the original contract had been modified in a material or in any respect. It did, however, attempt to allege a new contract, but was fatally defective in that regard.

[2] The averment that the building was erected “in accordance with and pursuant to a new and different contract or agreement with plaintiff,” which is all the answer contains upon the subject, is not the statement of ultimate fact but of a conclusion of law. Moreover, if treated as an allegation of fact, there is no evidence to support it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acoustics, Inc. v. Trepte Construction Co.
14 Cal. App. 3d 887 (California Court of Appeal, 1971)
Bank of Santa Ana v. Molina
1 Cal. App. 3d 607 (California Court of Appeal, 1969)
McDonald v. Filice
252 Cal. App. 2d 613 (California Court of Appeal, 1967)
Bowman v. Santa Clara County
315 P.2d 67 (California Court of Appeal, 1957)
Pierce v. Wright
256 P.2d 1049 (California Court of Appeal, 1953)
Standard Oil Co. of California v. Houser
225 P.2d 539 (California Court of Appeal, 1950)
Ingalls v. Bell
110 P.2d 1068 (California Court of Appeal, 1941)
California Western Holding Co. v. Merrill
46 P.2d 175 (California Court of Appeal, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
203 P. 758, 187 Cal. 655, 1922 Cal. LEXIS 489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blackwood-v-mccallum-cal-1922.