Howard J. White, Inc. v. Varian Associates

178 Cal. App. 2d 348, 2 Cal. Rptr. 871, 1960 Cal. App. LEXIS 2602
CourtCalifornia Court of Appeal
DecidedFebruary 25, 1960
DocketCiv. 18625
StatusPublished
Cited by11 cases

This text of 178 Cal. App. 2d 348 (Howard J. White, Inc. v. Varian Associates) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard J. White, Inc. v. Varian Associates, 178 Cal. App. 2d 348, 2 Cal. Rptr. 871, 1960 Cal. App. LEXIS 2602 (Cal. Ct. App. 1960).

Opinion

DOOLING, J.

Defendant Varían Associates (hereafter called Varían) appeals from a judgment in favor of plaintiff Howard J. White, Inc. (hereafter called White) in the amount of $128,086.36.

The litigation grows out of a construction contract entered into by White and Varían on October 12,1956, whereby White agreed to construct a vacuum tube production facility for Varían on land leased from Stanford University. The agreed price for the work was $1,347,139 and White agreed to complete it within 240 days after commencement, time being expressly made of the essence.

The contract gave Varían the right to change the specifications by written order and provided that any extension of time necessitated by reason of any such change should be requested by the contractor and adjusted at the time of ordering such change. (Art. 15, General Conditions.) The contract also provided for extensions of time in the event of delay for enumerated causes, claim therefor to be made in writing to the architect, with provision that no such extension should be granted for delay occurring more than seven days before claim therefor is made in writing. (Art. 18, id.) The architect testified that claims for extensions necessitated by change orders were subject of negotiation between the contracting parties under article 15 with which he had no concern, his power under article 18 being limited to delays for other causes. On appeal the parties do not dispute this interpretation.

It is agreed that work commenced under the contract on October 15, 1956. During the progress of the work 26 change orders were issued, the first 18 being signed before June 29, 1957. Of these, two extended the time of completion for 24% days, and one shortened the time by agreement of the parties by 7 days, in consideration of Varían paying White $3,420. The parties are likewise agreed that the net extension of 17% days embodied in these three written change orders extended the date of completion to June 29,1957. No extension of time was otherwise granted in writing by change order or order of the architect.

*351 The evidence makes clear that while article 15 of the General Conditions provides that 11 except in an emergency endangering life or property, no extra work or change shall be made unless in pursuance of a written order, ’ ’ the contracting parties throughout the work disregarded this provision consistently so that White on the oral direction of Varían commenced work different from or in addition to that specified in the contract and at times even completed such work before the written change order was executed.

With this background the evidence shows that on June 18, 1957, White received oral instructions from Varían to do certain additional electrical work not called for by the original contract at a cost of $18,321.23 and to do certain other work at a cost of $14,891.46. White testified that a portion of this work would take 100 man-weeks to complete, and another portion would require 60 days. Pursuant to the oral direction of June 18 White forthwith commenced the execution of this additional work. This work was afterward embodied in Change Order 19. About June 27, 1957, White received oral instructions to do other additional work, afterwards embodied in Change Order 21. This work, which White testified would take approximately 200 man-weeks to complete, was for the extension of certain process piping at a cost of $47,897.21. The work embodied in these two orders was originally planned to be done by Varían after White had completed his contract.

In the meantime, and after White had done substantial work on what was afterwards embodied in Change Order 19 the architect notified White in writing on June 25, 1957, to increase his work force and, if necessary, to work Saturdays and Sundays, to assure completion “within stipulated completion time. ’ ’

On July 1,1957, Varían sent a telegram to White’s bonding company calling its attention to Varían’s claim that the work was to be completed “approximately July 1, 1957 counting legal holidays” and stating its estimate that it would incur damages “in excess of $15,000 a day until substantial completion.” As a result of this telegram a meeting was held on July 3, 1957, involving White, the architect and representatives of Varían. At this meeting White agreed to allow Varían access to portions of the building on July 15 and another portion by July 26. White complied with this agreement.

Varían had planned to move its equipment from a plant in San Carlos so as to be in the newly constructed building and *352 ready for operation there by September 3, 1957, the day after Labor Day. To minimize loss in such move Varían had scheduled the vacations of its employees in the San Carlos plant to commence on August 16, 1957, and to end on September 3, 1957 when, if the move was made as contemplated, they could commence work in the new plant. The move was actually completed and the employees did commence work in the new plant on September 3. However Varían claimed that because of White’s delay in completion it was compelled to, and did, incur overtime in both the moving and the work of installing and connecting the machinery in the new plant, and for this and other items it filed a counterclaim in the sum of $126,982.89, which it now concedes should be reduced to $114,410.70.

It is agreed that the building was substantially completed on September 3, 1957, the day on which Varían commenced its business operations therein. It is also conceded that the final instalment accrued to White and unpaid under the contract is $122,071.67. The balance of the judgment awarded to White consists of certain disputed claims for extra work amounting to $6,014.69.

The trial court found among other things that work under the change orders was commenced prior to the receipt of the written change orders including the work under Change Orders 19 and 21 in reliance upon the oral authorization of Varían and concluded that by reason of this and other recited facts Varían prevented White from, and made it impossible for White to, complete performance in 257% days or any other period prior to September 3, 1957. It further found that said acts legally excused White from performance at any time prior to September 3, 1957.

It is appellant’s contention that the contract in writing required extensions in time to be in writing and that no extensions could be otherwise granted either orally or by conduct of the parties. (Roberts v. Security Trust & Sav. Bank, 196 Cal. 557 [238 P. 673]; Suhr v. Metcalfe, 33 Cal. App. 59 [164 P. 407].) We may concede that as to any change orders actually executed before June 29, 1957, the date to which completion had been extended by previous written orders, this is so.

We feel however that as to the work done under Change Orders 19 and 21 which was commenced prior to June 29, 1957, under oral authorization at a time when such addi *353 tional work could not possibly have been completed by June 29,1957, the court was justified, as it did, in applying a different rule. We must take the evidence most favorable to the court’s findings and judgment, drawing every reasonable favorable inference therefrom.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vought Construction Inc. v. Stock
California Court of Appeal, 2022
Silbermann v. Shangri-La Construction CA2/7
California Court of Appeal, 2020
Reyes v. Carehouse Healthcare Center CA4/3
California Court of Appeal, 2015
Donicker Corporation v. Pittsburgh National Bank
43 F.3d 1478 (Ninth Circuit, 1994)
Hogan v. Postin
695 P.2d 1042 (Wyoming Supreme Court, 1985)
Miller v. Elite Insurance
100 Cal. App. 3d 739 (California Court of Appeal, 1980)
A. J. Industries, Inc. v. Ver Halen
75 Cal. App. 3d 751 (California Court of Appeal, 1977)
Call v. Alcan Pacific Co.
251 Cal. App. 2d 442 (California Court of Appeal, 1967)
Soon v. Beckman
234 Cal. App. 2d 33 (California Court of Appeal, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
178 Cal. App. 2d 348, 2 Cal. Rptr. 871, 1960 Cal. App. LEXIS 2602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-j-white-inc-v-varian-associates-calctapp-1960.