Vought Construction Inc. v. Stock

CourtCalifornia Court of Appeal
DecidedOctober 24, 2022
DocketA164823
StatusPublished

This text of Vought Construction Inc. v. Stock (Vought Construction Inc. v. Stock) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vought Construction Inc. v. Stock, (Cal. Ct. App. 2022).

Opinion

Filed 10/24/22 CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION FOUR

VOUGHT CONSTRUCTION INC., Plaintiff and Appellant, A164823 v. JAY STOCK, (Alameda County Super. Ct. No. RG 20067174) Defendant and Respondent.

Vought Construction Inc. (Vought) appeals from a judgment following a bench trial on its claims against homeowner Jay Stock. Vought sought recovery of the balance due on his contract for the renovation of a house owned by Stock, additional compensation pursuant to a disputed change order, and penalties for the violation of a prompt-payment statute, Civil Code section 8800 (section 8800). Stock did not dispute the unpaid amount Vought had earned for finished work under the terms of their agreement as modified by approved change orders, but he disputed the claim for additional compensation and asserted an offsetting claim for liquidated damages for delay. The court held that Vought was entitled to the undisputed balance due plus approximately half the disputed amount it claimed in additional compensation; that Stock was entitled to approximately half the amount he claimed as liquidated damages; and that Stock had not violated section 8800 by withholding final payment pending resolution of the controversy. The court held that neither side had prevailed, so that neither was entitled to attorney

1 fees under section 8800 or to costs of suit under Code of Civil Procedure section 1032. We conclude that the trial court correctly ruled that the recent case of United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018) 4 Cal.5th 1082 (United Riggers) did not prohibit Stock from temporarily withholding payment, and did not abuse its discretion in holding that neither party was the prevailing party for the purpose of awarding attorney fees under section 8800. However, Vought was the prevailing party for the purpose of recovering costs under Code of Civil Procedure section 1032. Factual and Procedural History In September 2019, Stock and Vought entered a modified form contract for a home renovation project. They replaced the form’s references to “architect” with “owner” because Stock’s architect had retired, and Stock intended to perform the project-administration role that the form provides will be performed by the project’s architect. The contract stated a “contract sum” of $374,000 1 to be paid in installments for the specified work. It required Vought to substantially complete the work by January 13, 2020, subject to potential adjustments. If Vought failed to complete the work by the adjusted date, Stock was entitled to $300 per day of delay as liquidated damages. Vought was required to submit a biweekly application for payment (AFP). Stock was to pay, within seven days of receiving an AFP, a sum calculated as follows: Determine the portions of the contract sum allocable to completed work and to materials and equipment procured, subtract payments already made, and subtract any

1 Dollar amounts in this opinion are rounded to the nearest $1,000.

2 amount for which Stock had wholly or partly withheld 2 or nullified an AFP based on, inter alia, evidence that the project would not be completed by the deadline and that the unpaid contract balance would not cover liquidated damages due for delay. 3 Over the course of the project, Stock approved eight change orders or other adjustments that raised the agreed contract sum by a total of $69,000, to $442,000. The parties also agreed to extend the substantial completion date to February 11, 2020. The problems arose from a “relatively small” component of the project that the court described as “installation of some fairly particular and involved railings that would match . . . ones that [Stock] already had on the interior of the home.” The court found that the railings were “sophisticated and complicated” and “required a significant amount of detail.” Further, “Stock was under the impression that these railings could be . . . purchased, ordered,

2The contract referred to Stock having “withheld” or “nullified” AFPs because the original form provided for the contractor to submit AFPs to the architect, who would in turn either certify them to the owner for payment or withhold or nullify them if certain conditions were unmet. 3 The contract states: “[T]he amount of each progress payment shall be computed as follows: [¶] .1 Take that portion of the Contract Sum properly allocable to completed Work . . . ; [¶] .2 Add that portion of the Contract Sum properly allocable to materials and equipment [procured and stored on site] . . . ; [¶] .3 Subtract the aggregate of previous payments made by the Owner; and [¶] .4 Subtract amounts, if any, for which the Homeowner has withheld or nullified [an AFP] as provided in Section 9.5 of AIA Document A201-2007.” Section 9.5 states that “The Architect may . . . withhold [an AFP] in whole or in part . . . to such extent as may be necessary in the Architect’s opinion to protect the Owner from loss for which the Contractor is responsible . . . because of [¶] * * * [¶] .6 reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay . . . .”

3 [and] installed, without a sophisticated set of . . . architectural drawings, because in his experience that had not been required for the work . . . done inside his house,” while Vought “did not have extensive experience with these railings and kept as a placeholder an amount . . . consistent with what they have used to price out other types of railing systems, which may have been possible to install without having detailed architectural drawings.” The court found that it was not until January 24, 2020—four months after work began in September 2019, and three weeks before the adjusted substantial completion date of February 11, 2020—that Vought confronted “the need to have [architectural] drawings and the need to get firm prices for the materials that it would take to make this installation,” and raised the issues with Stock. Because of ensuing delays in obtaining the requisite drawings and materials—exacerbated by the onset of the COVID-19 pandemic—Vought was unable to finish installing the railings until August 2020. Work on all other parts of the project was substantially complete and approved by inspectors by late May 2020. In April 2020, Vought sent Stock an AFP showing an updated contract sum of $73,000 then unpaid but did not request immediate payment. In May 2020 Vought sent another AFP effectively identifying the same $73,000 as unpaid, valuing the work left to perform as $41,000, and demanding immediate payment of $32,000. Stock made no payment. In June 2020 Vought sent an AFP and a proposed $50,000 change order for the railings. The June AFP included the $50,000 and sought immediate payment of $78,000, equaling the difference (with minor variances) between the agreed, adjusted contract price of $437,000 (not including the unapproved $50,000 change order) and the payments to date of $363,000. Stock rejected the change order and made no payment.

4 In early July, Vought recorded a mechanic’s lien against the property for $78,000, and filed this action. On August 6, Vought sent an AFP with a proposed “change order” for $10,000 in “legal costs” and interest on unpaid progress payments. The AFP demanded payment of $142,000 (including the value of both unapproved change orders). Stock made no payment. On August 7, 2020, the project was completed. The work was satisfactory and priced by agreement at a value at least $73,000 more than Stock had paid, but Stock claimed he was entitled to withhold liquidated damages of $53,000. 4 Four months later, in December 2020, Stock paid Vought $20,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wallis v. PHL Associates Inc.
220 Cal. App. 4th 814 (California Court of Appeal, 2013)
Burton v. Sosinsky
203 Cal. App. 3d 562 (California Court of Appeal, 1988)
Howard J. White, Inc. v. Varian Associates
178 Cal. App. 2d 348 (California Court of Appeal, 1960)
Michell v. Olick
49 Cal. App. 4th 1194 (California Court of Appeal, 1996)
Basic Modular Facilities, Inc. v. Ehsanipour
83 Cal. Rptr. 2d 462 (California Court of Appeal, 1999)
Westfour Corp. v. California First Bank
3 Cal. App. 4th 1554 (California Court of Appeal, 1992)
Brawley v. J.C. Interiors, Inc.
74 Cal. Rptr. 3d 832 (California Court of Appeal, 2008)
Peter Kiewit Sons' Co. v. Pasadena City Junior College District
379 P.2d 18 (California Supreme Court, 1963)
James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc.
239 Cal. App. 4th 1214 (California Court of Appeal, 2015)
deSaulles v. Community Hospital of the Monterey Peninsula
370 P.3d 996 (California Supreme Court, 2016)
F.People v. Monier
405 P.3d 1076 (California Supreme Court, 2017)
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.
416 P.3d 792 (California Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Vought Construction Inc. v. Stock, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vought-construction-inc-v-stock-calctapp-2022.