James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc.

239 Cal. App. 4th 1214, 191 Cal. Rptr. 3d 825, 2015 Cal. App. LEXIS 747
CourtCalifornia Court of Appeal
DecidedAugust 27, 2015
DocketC072169
StatusPublished
Cited by8 cases

This text of 239 Cal. App. 4th 1214 (James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., 239 Cal. App. 4th 1214, 191 Cal. Rptr. 3d 825, 2015 Cal. App. LEXIS 747 (Cal. Ct. App. 2015).

Opinion

Opinion

HOCH, J.

West Bay Builders, Inc. (West Bay), and Safeco Insurance Company of America (Safeco) challenge the trial court’s denial of their motion for attorney fees under Business and Professions Code section 7108.5 and Public Contract Code sections 7107 and 10262.5 (prompt payment statutes). West Bay and Safeco were sued by James L. Harris Painting & Decorating, Inc. (Harris), for breach of contract and violation of the prompt payment statutes. In turn, West Bay filed a cross-complaint against Harris for *1217 breach of contract arising out of the same construction project. After years of litigation, the jury found both West Bay and Harris had failed to perform and thus did not award damages to either side. Safeco also did not recover because it was sued only in its capacity as issuer of a bond to West Bay for the construction project. Although West Bay and Safeco did not recover any damages, they moved for attorney fees under the fee-shifting provisions of the prompt payment statutes. The trial court denied their motion, finding there was no prevailing party in this case.

On appeal, West Bay and Safeco contend the trial court lacked discretion to refuse an award of mandatory attorney fees under the prompt payment statutes because they prevailed at trial. We disagree. Under the prompt payment statutes, the trial court has discretion to determine there is no prevailing party in an action. And in this case, the trial court did not abuse its discretion in concluding there was no prevailing party. Accordingly, we affirm the denial of the motion for attorney fees.

FACTUAL AND PROCEDURAL HISTORY

In 2003, West Bay entered into a prime contract with the Stockton Unified School District to perform work at Cesar Chavez High School. In 2004, West Bay entered into a subcontract for $530,000 with Harris that covered the application of paint and water repellants. From the beginning of the project, disagreements arose over the scope of work to be provided by Harris. West Bay asserted Harris had a contractual obligation to carry out several sections of the project’s specifications Harris disclaimed it had any duty to fulfill. Harris performed what it perceived to be extra work on assurances West Bay would pay for the additional services. According to Harris, West Bay refused to pay for the additional work.

According to West Bay, Harris refused to- fulfill its contractual obligations and simply abandoned the project. West Bay was forced to hire a third party painting subcontractor to repair and complete Harris’s work. West Bay deducted the cost of the third party painting subcontractor from the amount due Harris. By West Bay’s calculation, Harris was overpaid by $71,607 when all the adjustments were made.

In June 2007, Harris filed a complaint for breach of contract and violation of the prompt payment statutes by West Bay. Harris also claimed Safeco was obligated to release money under the payment bond issued to West Bay. West Bay filed a cross-complaint against Harris for breach of contract arising out of the same construction project.

*1218 The jury found both West Bay and Harris had failed to perform and refused to award damages to either side. The jury also found West Bay did not act in good faith when it withheld payment from Harris on June 24, 2004.

The trial court entered (1) judgment in favor of West Bay and Safeco on the complaint and (2) judgment in favor of Harris on the cross-complaint. The trial court awarded no damages on the complaint or cross-complaint. Nonetheless, the trial court awarded costs of suit to West Bay and Safeco. The trial court reserved ruling on whether there was a prevailing party for purposes of statutory attorney fees.

West Bay and Safeco moved for attorney fees under the prompt payment statutes, and Harris opposed the motion. The trial court heard argument on the motion and ruled: “The motion for attorney’s fees is denied. Each party sued for breach of contract, but neither side prevailed. The Jury denied all relief. Fairness dictates that each side should pay its own attorney’s fees.”

From the denial of the motion for fees, West Bay and Safeco timely filed a notice of appeal.

DISCUSSION

I

The Prompt Payment Statutes’ Fee-shifting Provisions

West Bay and Safeco contend the prompt payment statutes do not confer the trial court with discretion to deny attorney fees in a case in which the plaintiff asserts a claim under these statutes. (See Bus. & Prof. Code, § 7108.5; Pub. Contract Code, §§ 7107, 10262.5.) We disagree.

A.

Standard of Review

We consider the question of whether a statute provides for a mandatory award of attorney fees under the de novo standard of review. (Conservatorship of Whitley (2010) 50 Cal.4th 1206, 1213 [117 Cal.Rptr.3d 342, 241 P.3d 840].) In construing a statute, “ ‘[w]e apply well-established principles of statutory construction in seeking “to determine the Legislature’s intent in enacting the statute ‘ “so that we may adopt the construction that best effectuates the purpose of the law.” ’ ” [Citations.] We begin with the statutory language because it is generally the most reliable indication of *1219 legislative intent. [Citation.] If the statutory language is unambiguous, we presume the Legislature meant what it said, and the plain meaning of the statute controls. [Citation.]’ (Shirk v. Vista Unified School Dist. (2007) 42 Cal.4th 201, 211 [64 Cal.Rptr.3d 210, 164 P.3d 630].) But if the statutory language may reasonably be given more than one interpretation, courts may employ various extrinsic aids, including a consideration of the purpose of the statute, the evils to be remedied, the legislative history, public policy, and the statutory scheme encompassing the statute. (Ibid.)” (Conservatorship of Whitley, at p. 1214.)

B.

The Prompt Payment Statutes

Each of the three prompt payment statutes asserted by Harris against West Bay and Safeco contains a nearly identical fee-shifting provision. Business and Professions Code section 7108.5, subdivision (a), allows a prime contractor seven days to deliver an earned progress payment to a subcontractor. Subdivision (c) of section 7108.5 provides that “[i]n any action for the collection of funds wrongfully withheld, the prevailing party shall be entitled to his or her attorney’s fees and costs.” Similarly, subdivision (f) of Public Contract Code section 7107 provides that “in any action for the collection of funds wrongfully withheld, the prevailing party shall be entitled to attorney’s fees and costs” in litigation regarding the wrongful withholding of payment to a subcontractor on a public works contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vought Construction Inc. v. Stock
California Court of Appeal, 2022
Youssef v. County of Los Angeles CA2/1
California Court of Appeal, 2022
Riskin v. Downtown L.A. Property Owners Assn.
California Court of Appeal, 2022
Srouy v. San Diego Unified School District
California Court of Appeal, 2022
Lyons v. Stanford Hospital and Clinics CA6
California Court of Appeal, 2021
Jones v. Goodman
California Court of Appeal, 2020
Sutter Health v. Eden Township Healthcare District
6 Cal. App. 5th 60 (California Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
239 Cal. App. 4th 1214, 191 Cal. Rptr. 3d 825, 2015 Cal. App. LEXIS 747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-l-harris-painting-decorating-inc-v-west-bay-builders-inc-calctapp-2015.