Pneucrete Corp. v. United States Fidelity & Guaranty Co.

46 P.2d 1000, 7 Cal. App. 2d 733, 1935 Cal. App. LEXIS 812
CourtCalifornia Court of Appeal
DecidedJune 22, 1935
DocketCiv. 9085
StatusPublished
Cited by37 cases

This text of 46 P.2d 1000 (Pneucrete Corp. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pneucrete Corp. v. United States Fidelity & Guaranty Co., 46 P.2d 1000, 7 Cal. App. 2d 733, 1935 Cal. App. LEXIS 812 (Cal. Ct. App. 1935).

Opinion

ROTH, J., pro tem.

On November 12, 1929, J. D. Harms, one of the appellants, as contractor, entered into a contract with Los Angeles County Flood Control District for certain mechanical work, to wit: ‘1 Guniting of levees in San Gabriel *735 Wash”. Pursuant to the Public Works Act, Statutes of 1919, page 487, as amended to and including May 10, 1929, Harms, as principal, and appellant United States Fidelity and Guaranty Company, as surety, executed and delivered to the district a “Bond for Materialmen and Laborers”, dated November 2, 1929, whereupon appellant Harms, as contractor, entered upon the performance of and completed said contract. During the course of the work under said contract, respondent Pneucrete Corporation contracted to and did furnish to Harms certain equipment and machinery to be used and which was actually used in and upon said public works. Harms agreed to pay therefor certain sums of money as provided in the contract with respondent for the rental thereof, which contract contained the following clause: “In case of controversy, both parties agree to arbitrate the issue in accordance with the rules of the American Arbitration Association. ’ ’

On January 27, 1930, respondent filed this action against appellants, as principal and surety upon the “Materialmen’s Bond”, alleging the execution of the contract for the public improvement, the giving of the “Materialmen’s Bond”, the contract for the hiring of equipment by Harms from respondent materialman, alleging with reference to the “Materialmen’s Bond”, “that plaintiff relies particularly upon said written instrument”. Thereafter on February 24, 1930, appellants answered said complaint, which answer in addition to denying generally the material facts denied the execution of the contract executed between respondent and Harms. On the same day appellants filed their answer to the complaint, a demurrer which had been theretofore filed by appellants to the complaint was sustained. Thereafter an amended eomplant, practically identical to the original complaint save that it pleaded the contract for the hiring of the equipment by defendant Harms in its legal effect rather than in Twee verba, was filed, to which amended complaint defendants filed their verified answer on March 17, 1930, denying the contract between respondent and Harms, but admitting the execution of the “Materialmen’s Bond” and admitting also that respondent relied thereon.

Twenty-two months thereafter the case was called for trial, at which time the question of arbitration was first raised by appellants. Until the day of trial appellants had not filed *736 any petition pursuant to section 1282 of the Code of Civil Procedure for an order directing that arbitration proceed, made any motion or taken any other means to stay the action, or in any manner raised the issue of arbitration by answer filed to the original or to the amended complaint. On January 27, 1932/ which was the day before the date upon which the case had been set for trial, appellants served upon respondent a “Notice of Motion to Stay Action”, which was supported by the affidavit of Harms, in which affidavit Harms referred to the contract he had made with respondent and specifically to the arbitration clause therein, averring further that Harms had requested respondent to proceed with arbitration in the manner provided for in the contract and that respondent had refused to go ahead with said arbitration. The affidavit does not state when the demand for arbitration was made nor when plaintiff refused to arbitrate prior to the date of the affidavit. A reply affidavit was made and filed by the attorney for respondent, which affidavit denied a refusal to arbitrate but admitted a refusal to arbitrate on that date, which was the date of trial. This affidavit also averred that the action was on the bond; that the appellants had failed to petition for arbitration and that appellants had in effect waived arbitration because of their default in making any attempt to proceed therewith. The motion to stay action was denied, whereupon appellants requested and were granted permission to file an amended answer, which amended answer set forth the contract between Harms and respondent which had previously been denied by two several answers filed by said appellants, one to the original and one to the amended complaint, and no allegations are made in said amended answer as to the desire, willingness, readiness or ability of said appellants to arbitrate. Judgment went for the respondent and from that judgment appellants appeal.

Conceding that the arbitration clause in the contract between respondent and Harms was mandatory upon those parties, under the facts and circumstances here outlined the decisive question on this appeal is whether that contract became a part of the bond executed by appellants pursuant to the Public Works Act, Statutes of 1919, page 487, as amended.

The purpose of the bond provision of the Public Works Act, we believe, was to give to materialmen and labor *737 ers who furnish material for and render services upon public works an additional means of receiving compensation. This rule has been consistently recognized with reference to private works. (17 Cal. Jur. 15, 16; Peterson v. Freiermuth, 17 Cal. App. 609 [121 Pac. 299]; Avery v. Clark, 87 Cal. 619 [25 Pac. 919, 22 Am. St. Rep. 272] ; Birch & Co. v. Magic Transit Co., 139 Cal. 496 [73 Pac. 238]; Humboldt Lumber Mill Co. v. Crisp, 146 Cal. 686 [81 Pac. 30, 106 Am. St. Rep. 75, 2 Ann. Cas. 811].) No lien being available to those who perform labor or furnish material on public works (Cooley v. Freeman, 204 Cal. 59 [266 Pac. 545]), the provisions of the Public Works Act requiring a bond were obviously enacted to create a fund in lieu of the building or work itself against which materialmen and laborers might proceed as an additional and contemporaneous remedy. The bond required is not a voluntary bond but a statutory bond (Williamson v. Egan, 209 Cal. 343, 344 [287 Pac. 503]; Continental Nat. Bank v. Republic Gas Co., 202 Cal. 586, 589 [262 Pac. 300]), and affords an additional or cumulative remedy. (Sunset Lumber Co. v. Smith, 95 Cal. App. 307 [272 Pac. 1068].) As a result of the legislation mentioned there is now given to materialmen and laborers who furnish material or render services on public works an added and new security. (Globe Indemnity Co. v. Hanify, 217 Cal. 721, 730 [20 Pac. (2d) 689]; United States, to the Use of Standard Oil Co., v. City Trust etc. Co., 21 App. D. C. 369; Fidelity & Deposit Co. v. United States, etc., 20 App. D. C. 376 (affd. 187 U. S. 315 [23 Sup. Ct. 120, 47 L. Ed. 194]); City of St. Louis v. Hill- O'Meara Construction Co., 175 Mo. App. 555 [158 S. W. 98]; National Surety Co. v. Bratnober Lumber Co., 67 Wash. 601 [122 Pac. 337]; Griffith v. Stucker, 91 Kan. 47 [136 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quach v. Cal. Commerce Club, Inc.
California Supreme Court, 2024
N v. Heathorn, Inc. v. County of San Mateo
25 Cal. Rptr. 3d 400 (California Court of Appeal, 2005)
Scott Co. v. United States Fidelity & Guaranty Insurance
132 Cal. Rptr. 2d 89 (California Court of Appeal, 2003)
DEPARTMENT OF INDUS. REL. v. Fidelity Roof Co.
60 Cal. App. 4th 411 (California Court of Appeal, 1997)
Department of Industrial Relations v. Seaboard Surety Co.
50 Cal. App. 4th 1501 (California Court of Appeal, 1996)
LITON GEN. ENG'G CON., INC. v. United Pac. Ins.
16 Cal. App. 4th 577 (California Court of Appeal, 1993)
Liton General Engineering Contractor, Inc. v. United Pacific Insurance
16 Cal. App. 4th 577 (California Court of Appeal, 1993)
Sukut-Coulson, Inc. v. Allied Canon Co.
85 Cal. App. 3d 648 (California Court of Appeal, 1978)
Allstate Insurance v. Superior Court
35 Cal. App. 3d 137 (California Court of Appeal, 1973)
Player v. Geo. M. Brewster & Son, Inc.
18 Cal. App. 3d 526 (California Court of Appeal, 1971)
Consolidated Electrical Distributors, Inc. v. Kirkham, Chaon & Kirkham, Inc.
18 Cal. App. 3d 54 (California Court of Appeal, 1971)
Daugherty Co. v. Kimberly-Clark Corp.
14 Cal. App. 3d 151 (California Court of Appeal, 1971)
General Electric Co. v. Central Surety & Insurance
232 Cal. App. 2d 590 (California Court of Appeal, 1965)
Jordan v. Pacific Automobile Insurance
232 Cal. App. 2d 127 (California Court of Appeal, 1965)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
Powers Regulator Co. v. Seaboard Surety Co. of New York
204 Cal. App. 2d 338 (California Court of Appeal, 1962)
Government Employees Insurance v. Brunner
191 Cal. App. 2d 334 (California Court of Appeal, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
46 P.2d 1000, 7 Cal. App. 2d 733, 1935 Cal. App. LEXIS 812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pneucrete-corp-v-united-states-fidelity-guaranty-co-calctapp-1935.