Globe Indemnity Co. v. Hanify

20 P.2d 689, 217 Cal. 721, 1933 Cal. LEXIS 677
CourtCalifornia Supreme Court
DecidedApril 3, 1933
DocketDocket No. Sac. 4598.
StatusPublished
Cited by7 cases

This text of 20 P.2d 689 (Globe Indemnity Co. v. Hanify) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Globe Indemnity Co. v. Hanify, 20 P.2d 689, 217 Cal. 721, 1933 Cal. LEXIS 677 (Cal. 1933).

Opinion

SEAWELL, J.

On July 6, 1928, the Clarksburg High School District of the County of Yolo entered into an agreement with Daniel R. Hanify as contractor to construct within a fixed period a certain gymnasium for the use of said High School District at the agreed cost- of $56,324. Monthly payments of seventy-five per cent of the value of the labor and materials were to be made to the contractor upon the certificate of the architect. The remaining twenty-five per cent was to be retained by the High School District for a period of thirty-five days after final acceptance of the work. Appellant Globe Indemnity Company, a corporation, became surety for the contractor, Daniel R. Hanify, upon two bonds in the sum of $30,000 each, one in favor of laborers and materialmen and the other conditioned for the faithful performance of the contract.

Upon the completion of said building there remained in the hands of said High School District, owner, the final payment in the sum of $14,524.50, which sum was due and unpaid under the terms of said builder’s contract. The bank had advanced, with the consent of the surety, all of said sum of $14,524.50, but $1133.75 in discharge of material-men’s claims. The cost of constructing and completing said building, as shown by the claims of materialmen subsequently filed against it, exceeded the contract price by the sum of $10,940.29. By its answer said School District admitted its liability, by reason of its contract, in said sum of $14,524.50, and pleaded its willingness and ability to pay said sum to whomsoever the court should direct or by its decree should determine was entitled to receive the same.

Notice of completion of said building was filed for record in the official records of the county of Yolo on January 8, 1929. Three of said materialmen filed stop notices within the thirty-five day period following the filing of the notice of completion, but the trial court found that none of them had given the five days’ notice of proceedings to enforce payment, as prescribed by section 1184a of the Code of Civil Procedure. The warrants issued by the said High School District were in every instance drawn in favor of said bank. *724 The last one, covering the final payment in controversy in the sum of $14,524.50, was so drawn on February 11, 1929, and was received by the bank on February 13, 1929. Payment was refused by reason of said stop notices.

As a result of trial the court gave judgment in favor of all the material claimants and against contractor Hanify, who defaulted, and against the surety company, and directed that the moneys in the possession of the Clarksburg High School District be paid to the clerk of the court, and that the bank be reimbursed out of said sum of $14,524.50, held as a final payment, to the extent of $13,390.75, moneys which it had paid to laborers and materialmen, and that the difference between the remaining $1133.75 and the total amount found to be due the materialmen be entered as judgment against Hanify and his surety. A similar judgment was also entered in favor of the surety against Hanify. No question is raised that any claim for material was excessive or in any degree tainted with fraud.

The claimants being numerous, their several actions were joined, and the court upon consent or stipulation of counsel made orders of consolidation, as provided by sections 1184a and 1195 of the Code of Civil Procedure. Cases designated Sacramento No. 4605 and Sacramento No. 4598 are herewith presented on said consolidated record for the purposes of this appeal.

Some eighteen parties, including the Clarksburg High School District, owner of the building, Globe Indemnity Company, surety, First National Bank of Sonora, assignee, and all of the materialmen, appeared by direct proceedings or by cross-actions. The materialmen are not appealing from the judgments rendered by the trial court. Appellant Globe Indemnity Company and respondent bank are the parties really interested in the result of this appeal. Hanify, as was stated before, defaulted. The question which is decisive of the rights of said bank and surety company is whether the sum of $13,390.75 of said total final payment, to wit, $14,524.50, due from the owner upon completion of the building under the terms of its contract, should be paid to the bank in replacement of an exact amount which it advanced in payment of materialmen’s claims in the course of construction, and which was so applied, or whether said final payment withheld by the owner subject to the order of *725 court should be applied to the payment of claims of material-men, some of which were incurred in excess of the contract price, notwithstanding certain agreements entered into between the surety company and the bank with respect to the subject matter of the controversy. It may be here noted that the bank paid labor and materialmen’s claims during the progress of construction of said building amounting to $55,190.25, leaving the sum of $1133.75 in the hands of the owners in excess of the total sum paid by the bank. Said sum of $1133.75 was awarded to said surety company by the judgment.

The bank’s action was in rem against the fund, and it did not seek nor was a judgment rendered in its favor against the surety company. The right to said fund as between the surety company and said bank by reason of the latter’s participation in the matter as herein set forth is conceded by counsel to be the real issue presented by this appeal. If said bank is deprived of the moneys advanced by it to the materialmen in payment of materials which actually went into the building it will in effect be substituted for the surety company. The solution of the question depends upon the intent and understanding with which the surety company and said bank entered into a certain transaction whereby said bank became the assignee of contractor Hanify for a definite purpose. It appears that Hanify, at the time or prior to the time he executed said assignment of contract as hereafter set forth, was indebted to said bank in the sum of approximately $3',000, or possibly more. On July 18, 1928, twelve days after he had been awarded said contract, he executed an assignment of it to said bank for the special purposes therein set forth.

Said assignment restates the fact that the contract price of said building was fixed at $56,324. It is further provided therein that said assignment vests in the said bank the right to have, receive and collect any and all moneys due for the performance of said contract from said High School District, and to receipt for the same, and that a copy of the assignment shall be filed with the board of trustees of said Clarksburg High School District. It also contains the following provision: “This assignment is made for the purpose of securing to the said First National Bank of Sonora the payment of all moneys past due, now due, or which may be hereafter *726 advanced to the said Daniel R. Hanify.” (Italics supplied.) On July 23, 1928, the attorney of said bank forwarded a letter of notification to the Globe Indemnity Company calling attention to the fact that it was financing Mr. Hanify on his work of construction, and, further, “to give notice of the true conditions existing and that Mr. Hanify, in order to protect the bank, had assigned said contract to the First National Bank.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Department of Industrial Relations v. Seaboard Surety Co.
50 Cal. App. 4th 1501 (California Court of Appeal, 1996)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
Cassaretto v. City & County of San Francisco
62 P.2d 777 (California Court of Appeal, 1936)
Pneucrete Corp. v. United States Fidelity & Guaranty Co.
46 P.2d 1000 (California Court of Appeal, 1935)
Latourette-Fiscal Co. v. Hanify
20 P.2d 693 (California Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
20 P.2d 689, 217 Cal. 721, 1933 Cal. LEXIS 677, Counsel Stack Legal Research, https://law.counselstack.com/opinion/globe-indemnity-co-v-hanify-cal-1933.