Crosno Construction, Inc. v. Travelers Casualty etc.

CourtCalifornia Court of Appeal
DecidedApril 17, 2020
DocketD075561
StatusPublished

This text of Crosno Construction, Inc. v. Travelers Casualty etc. (Crosno Construction, Inc. v. Travelers Casualty etc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crosno Construction, Inc. v. Travelers Casualty etc., (Cal. Ct. App. 2020).

Opinion

Filed 4/17/20 CERTIFIED FOR PUBLICATION

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

CROSNO CONSTRUCTION, INC., D075561, D075562

Cross-complainant and Respondent,

v. (Super. Ct. No. CIVDS1511273)

TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA,

Cross-defendant and Appellant.

APPEALS from a judgment and postjudgment order of the Superior Court of San

Bernardino County, Gilbert Ochoa, Judge. Affirmed.

SMTD Law, Jonathan J. Dunn, Teresa L. Polk and Ravpreet K. Bhangoo for

Defendant and Appellant.

Barnick | Hodges Law Corporation, John F. Hodges and Whitney Northington

Barnick for Plaintiff and Respondent.

Rutan & Tucker, Paul Aherne and Alyssa Roy for Construction Employers'

Association as Amicus Curiae on behalf of Defendant and Appellant.

Crawford & Bangs and E. Scott Holbrook, Jr. for American Subcontractors

Association as Amicus Curiae on behalf of Plaintiff and Respondent. North Edwards Water District (the District) selected Clark Bros., Inc. (Clark) as its

general or direct contractor on a public works project to build an arsenic removal water

treatment plant. Clark hired subcontractor Crosno Construction (Crosno) to build and

coat two steel reservoir tanks. The subcontract contained a "pay-when-paid" provision

that stated Clark would pay Crosno within a reasonable time of receiving payments from

the District, but that this reasonable time "in no event shall be less than the time

Contractor and Subcontractor require to pursue to conclusion their legal remedies against

Owner or other responsible party to obtain payment . . . ." After Crosno completed most

of its work, a dispute arose between the District and Clark halting the project. As Clark

sued the District, Crosno sought to recover payments owed under the public works

payment bond that Clark had obtained for the project.

This appeal involves Crosno's payment bond claim against the bond surety,

Travelers Casualty and Surety Company of America (Travelers). At issue is whether the

pay-when-paid provision in Crosno's subcontract precludes Crosno from recovering

under the payment bond while Clark's lawsuit against the District remains pending.

Relying on Wm. R. Clarke Corp. v. Safeco Ins. Co. (1997) 15 Cal.4th 882 (Wm. R.

Clarke), the trial court found the pay-when-paid provision here unenforceable because it

affects or impairs Crosno's payment bond rights in violation of Civil Code section 8122.1

With the facts largely undisputed, the court granted Crosno's motion for summary

judgment and entered judgment in its favor for principal due plus prejudgment interest.

1 Further statutory references are to the Civil Code unless otherwise indicated. 2 Travelers asserts the trial court misconstrued Wm. R. Clarke and erred in failing to

enforce the pay-when-paid provision against the bond claim. After carefully considering

the parties' arguments, we agree with the trial court's sound analysis. Enforcing the pay-

when-paid provision found in Crosno's subcontract would postpone Crosno's right to

recover under the payment bond for an indefinite time period until Clark's litigation

against the District concludes. Such a result would unreasonably affect or impair

Crosno's statutory payment bond remedy (§ 8122) and is unenforceable for the same

reasons expressed in Wm. R. Clarke, supra, 15 Cal.4th 882. Because Travelers may not

invoke this particular pay-when-paid provision as a defense to payment bond liability, we

affirm the judgment. Travelers raises no separate argument as to the postjudgment award

of attorney's fees; accordingly, we likewise affirm that order.

FACTUAL AND PROCEDURAL BACKGROUND

The District sought lump sum bids for a public water system improvement project

funded by the State. The specifications required general contractors submitting bids to

secure a payment bond providing coverage if it or any of its subcontractors failed to make

payments due. Clark obtained a public works payment bond from Travelers to secure the

payment of subcontractors and suppliers. As the surety, Travelers became obliged upon

Clark's failure to make payments due. In addition, the payment bond covered reasonable

attorney's fees. Clark listed Crosno as a subcontractor in its bid. The District selected

Clark as its direct contractor (§ 8108).

Thereafter, Clark executed a subcontract agreement with Crosno. Crosno agreed

to fabricate, erect, and coat two 250,000-gallon welded steel water reservoir tanks for the

3 sum of $630,000. Among other terms, the subcontract required Crosno to be paid for

labor and material in monthly progress payments, subject to a retention, upon receipt of

payments from the District.2 Critical to this case, the subcontract further contained the

following pay-when-paid provision in the event the District delayed making payments to

Clark:

"If Owner or other responsible party delays in making any payment to Contractor from which payment to Subcontractor is to be made, Contractor and its sureties shall have a reasonable time to make payment to Subcontractor. 'Reasonable time' shall be determined according to the relevant circumstances, but in no event shall be less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment, including (but not limited to) mechanics' lien remedies."

Crosno began work in March 2014. On November 6, it was ordered to halt work

because a dispute had arisen between Clark and the District. By that point, Crosno had

supplied and fabricated the steel, shop-primed the steel, transported the steel to the site,

2 "Construction contracts often call for payment in installments—known commonly as progress payments—due when a project reaches various stages of completion. [Citation.] By arranging for progress payments, participants in a construction-related transaction build in an incentive for contractors to complete work and provide an owner some protection against the risk of nonperformance [citation], while permitting contractors to obtain an essential cash flow. As an additional hedge against nonperformance and incentive for completion, an owner may withhold a small percentage of the money due at each stage—typically 5 to 10 percent—until the project is finished. [Citations.] If the contractor defaults, or subcontractors assert mechanics liens for nonpayment, the owner can use this retention fund to make payment or seek substitute performance. [Citations.] Once work is done to the owner's satisfaction and the period for filing liens has expired, the owner will release the retention." (United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018) 4 Cal.5th 1082, 1087−1088, fn. omitted (United Riggers).) 4 erected the two 250,000-gallon tanks, and almost completed field coating work. Most of

the submitted invoices remained unpaid, with a total of $562,435 owed to Crosno for the

work completed to that point.

The next day (November 7) Crosno filed a stop payment notice with the District.

Two weeks later, Clark told Crosno the District had terminated its contract. This meant

that Clark could not pay Crosno the $562,435 owed for completed work.

On December 18, 2014, Crosno gave Travelers a written notice of its claim under

the payment bond. The following month, Travelers replied by letter rejecting the bond

claim as premature.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Yamanishi v. Bleily & Collishaw, Inc.
29 Cal. App. 3d 457 (California Court of Appeal, 1972)
Coast Electric Co. v. Industrial Indemnity Co.
144 Cal. App. 3d 879 (California Court of Appeal, 1983)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
Pneucrete Corp. v. United States Fidelity & Guaranty Co.
46 P.2d 1000 (California Court of Appeal, 1935)
Electrical Electronic Control, Inc. v. Los Angeles Unified School District
24 Cal. Rptr. 3d 316 (California Court of Appeal, 2005)
N v. Heathorn, Inc. v. County of San Mateo
25 Cal. Rptr. 3d 400 (California Court of Appeal, 2005)
Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Union Asphalt, Inc. v. Planet Insurance
21 Cal. App. 4th 1762 (California Court of Appeal, 1994)
Fed. Ins. Co. v. Superior Court of Ventura Cty.
60 Cal. App. 4th 1370 (California Court of Appeal, 1998)
Department of Industrial Relations v. Seaboard Surety Co.
50 Cal. App. 4th 1501 (California Court of Appeal, 1996)
Cooley v. Freeman
266 P. 545 (California Supreme Court, 1928)
Globe Indemnity Co. v. Hanify
20 P.2d 689 (California Supreme Court, 1933)
Los Angeles S. Co. v. National S. Co.
173 P. 79 (California Supreme Court, 1918)
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.
416 P.3d 792 (California Supreme Court, 2018)
Wm. R. Clarke Corp. v. Safeco Insurance of America
938 P.2d 372 (California Supreme Court, 1997)
Liton General Engineering Contractor, Inc. v. United Pacific Insurance
16 Cal. App. 4th 577 (California Court of Appeal, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Crosno Construction, Inc. v. Travelers Casualty etc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/crosno-construction-inc-v-travelers-casualty-etc-calctapp-2020.